1 |
38870487 |
Construction of Boundary wall of Grave Yard near the house of Faruk Uddin Barbhuiya at Sewti -II. |
170000 |
Construction of Boundary wall of Grave Yard near the house of Faruk Uddin Barbhuiya at Sewti -II.1 |
In Progress |
-
latitude : 24.9298108
Longitude : 92.64784818
file name : Image_16082021143100286.png
|
2021-08-16 14:31:00.37308 |
2 |
38870244 |
Construction of Babur Bazar Market Shed at Goragram. |
|
Construction of Babur Bazar Market Shed at Goragram.1 |
25% |
-
latitude : 24.8110038
Longitude : 92.7976893
file name : Image_05042021135212749.png
|
2021-04-05 13:52:12.842856 |
3 |
38871468 |
Construction of Babur Bazar Market Shed at Goragram (Phase- II). |
400000 |
Construction of Babur Bazar Market Shed at Goragram (Phase- II).1 |
25% |
-
latitude : 24.8110038
Longitude : 92.7976893
file name : Image_05042021135409032.png
|
2021-04-05 13:54:09.130413 |
4 |
38871265 |
Construction of Community ring well in front of Swashan Ghat at Sewti – III. |
80000 |
Construction of Community ring well in front of Swashan Ghat at Sewti – III.1 |
In Progress |
-
latitude : 24.92482199
Longitude : 92.63871973
file name : Image_16082021145203361.png
|
2021-08-16 14:52:03.448654 |
5 |
38871301 |
Construction of CC Block road from Lalmohan Nath house to RLY line at Goragram. |
400000 |
Construction of CC Block road from Lalmohan Nath house to RLY line at Goragram.1 |
Earth Work |
-
latitude : 24.8110038,24.8110038
Longitude : 92.7976893,92.7976893
file name : Image_05042021144145294.png
|
2021-04-05 14:41:45.40266 |
6 |
38871448 |
Const. of CC Block road from NREGS road to Brojananda Sinha house at Sewti- III. |
200000 |
Const. of CC Block road from NREGS road to Brojananda Sinha house at Sewti- III.1 |
Earth Work |
-
latitude : 24.92709468,24.92702116
Longitude : 92.6446379,92.64516788
file name : Image_17082021135716746.png
|
2021-08-17 13:57:16.856327 |
7 |
38871428 |
Const. of Community B/Wall of Grave Yard near the house of Romijul Ali at Sewti- IV. |
150000 |
Const. of Community B/Wall of Grave Yard near the house of Romijul Ali at Sewti- IV.1 |
In Progress |
-
latitude : 24.91332458
Longitude : 92.64330885
file name : Image_16082021131709805.png
|
2021-08-16 13:17:09.912919 |
8 |
38871335 |
Construction of Stairghat near Goragram Swashan Ghat at Goragram. |
200000 |
Construction of Stairghat near Goragram Swashan Ghat at Goragram.1 |
25% |
-
latitude : 24.94658661
Longitude : 92.67212008
file name : Image_25072021120420931.png
|
2021-07-25 12:04:21.015817 |
9 |
38871517 |
Renovation of Community Ring Well near the house of Karim Uddin at Sewti- I. |
49068 |
Renovation of Community Ring Well near the house of Karim Uddin at Sewti- I.1 |
In Progress |
-
latitude : 24.8110038
Longitude : 92.7976893
file name : Image_05042021160754034.png
|
2021-04-05 16:07:54.138733 |
10 |
38871483 |
Const. of CC Block road from Abdul Malik house to Najrul Hoque house at Goragram. |
200000 |
Const. of CC Block road from Abdul Malik house to Najrul Hoque house at Goragram.1 |
Earth Work |
-
latitude : 24.8110038,24.8110038
Longitude : 92.7976893,92.7976893
file name : Image_05042021141605636.png
|
2021-04-05 14:16:05.726647 |
11 |
38871241 |
Construction of Community ring well near the house of Lotai mia at Sewti- I. |
80000 |
Construction of Community ring well near the house of Lotai mia at Sewti- I.1 |
In Progress |
-
latitude : 24.8110038
Longitude : 92.7976893
file name : Image_05042021161113187.png
|
2021-04-05 16:11:13.297283 |
12 |
38871182 |
Const. of Community B/Wall of G/Yard near Nuton Masjid near Hurmot Ali house at Sewti-I. |
168590 |
Const. of Community B/Wall of G/Yard near Nuton Masjid near Hurmot Ali house at Sewti-I. 1 |
In Progress |
-
latitude : 24.8110038
Longitude : 92.7976893
file name : Image_05042021154447675.png
|
2021-04-05 15:44:47.787354 |
13 |
44286533 |
Construction of CC Block road from Mostan Ali house to Motahir Ali house at Goragram |
350000 |
Construction of CC Block road from Mostan Ali house to Motahir Ali house at Goragram1 |
Earth Work |
-
latitude : 24.95228014,24.95189412
Longitude : 92.66626091,92.66676324
file name : Image_25072021115209201.png
|
2021-07-25 11:52:09.318631 |
14 |
44286609 |
Construction of RCC Culvert with approach of Mohadev Bari in front of Ramij Uddin at Sewti-IV |
200000 |
Construction of RCC Culvert with approach of Mohadev Bari in front of Ramij Uddin at Sewti-IV1 |
Substructure below GL |
-
latitude : 24.91712231,24.91709337
Longitude : 92.64879317,92.6488227
file name : Image_16082021140124600.png
|
2021-08-16 14:01:24.66741 |
15 |
44286656 |
Construction of Boundary wall of Grave Yard near the house of Jomir Uddin at Sewti-IV. |
150000 |
Construction of Boundary wall of Grave Yard near the house of Jomir Uddin at Sewti-IV.1 |
In Progress |
-
latitude : 24.9118536
Longitude : 92.64485873
file name : Image_16082021133506906.png
|
2021-08-16 13:35:06.99337 |
16 |
44286754 |
Construction of Stairghat at Paschim Masjid pond at Sewti-IV. |
200000 |
Construction of Stairghat at Paschim Masjid pond at Sewti-IV.1 |
25% |
-
latitude : 24.91548725
Longitude : 92.64535452
file name : Image_16082021130705806.png
|
2021-08-16 13:07:05.870288 |
17 |
44286782 |
Construction of Community ring well near the house of Sujit Nath at Sewti-II. |
80000 |
Construction of Community ring well near the house of Sujit Nath at Sewti-II.1 |
In Progress |
-
latitude : 24.92896875
Longitude : 92.64757565
file name : Image_16082021143630614.png
|
2021-08-16 14:36:30.695683 |
18 |
44287114 |
Construction of Community Boundary wall of Grave Yard near the house of Abdul Kadir Tafadar at Sewti |
150000 |
Construction of Community Boundary wall of Grave Yard near the house of Abdul Kadir Tafadar at Sewti1 |
In Progress |
-
latitude : 24.91498534
Longitude : 92.64532906
file name : Image_16082021130359592.png
|
2021-08-16 13:03:59.680035 |
19 |
44286967 |
Construction of Community Boundary wall of Nimata Bari at Goragram |
200000 |
Construction of Community Boundary wall of Nimata Bari at Goragram1 |
In Progress |
-
latitude : 24.94370283
Longitude : 92.66856924
file name : Image_25072021115323444.png
|
2021-07-25 11:53:23.554436 |
20 |
44286988 |
Construction of Community Ring well near the house of Ilas Ali at Goragram. |
80000 |
Construction of Community Ring well near the house of Ilas Ali at Goragram.1 |
In Progress |
-
latitude : 24.9534379
Longitude : 92.6649066
file name : Image_25072021112853739.png
|
2021-07-25 11:28:53.849373 |
21 |
44287098 |
Construction of RCC Culvert on the road from SJ road to the house of Iman Uddin at Goragram |
100000 |
Construction of RCC Culvert on the road from SJ road to the house of Iman Uddin at Goragram1 |
Substructure below GL |
-
latitude : 24.95064448,24.95069021
Longitude : 92.66503769,92.6650573
file name : Image_25072021121805338.png
|
2021-07-25 12:18:05.419949 |
22 |
44287158 |
Construction of Boundary wall of Badsa Bari at Goragram |
163815 |
Construction of Boundary wall of Badsa Bari at Goragram1 |
In Progress |
-
latitude : 24.95490883
Longitude : 92.67168588
file name : Image_25072021124807038.png
|
2021-07-25 12:48:07.144558 |
23 |
44287080 |
Construction of Community Boundary Wall of Grave Yard near the house of Jomir Uddin (Ph-II) at Sewti |
150000 |
Construction of Community Boundary Wall of Grave Yard near the house of Jomir Uddin (Ph-II) at Sewti1 |
In Progress |
-
latitude : 24.91193364
Longitude : 92.64526591
file name : Image_16082021133848116.png
|
2021-08-16 13:38:48.201861 |
24 |
55440799 |
Renovation of 9 no kayarpar AWC at kayapar |
115000 |
Renovation of 9 no kayarpar AWC at kayapar1 |
Completion of work |
-
latitude : 24.9136613
Longitude : 92.64399723
file name : Image_22032022184213678.png
|
2022-03-22 18:42:13.774831 |
25 |
55440755 |
Renovation of 8 no Sewti-1B AWC |
100155 |
Renovation of 8 no Sewti-1B AWC1 |
Completion of work |
-
latitude : 24.93982366
Longitude : 92.650283
file name : Image_22032022184247565.png
|
2022-03-22 18:42:47.673698 |
26 |
55440705 |
Renovation of 7 no Sewti-IA AWC at Sewti-I |
100155 |
Renovation of 7 no Sewti-IA AWC at Sewti-I1 |
Completion of work |
-
latitude : 24.93948406
Longitude : 92.66174472
file name : Image_22032022184255816.png
|
2022-03-22 18:42:55.915834 |
27 |
55440653 |
Renovation of 6 no AWC at Goragram |
100155 |
Renovation of 6 no AWC at Goragram1 |
Completion of work |
-
latitude : 24.94850586
Longitude : 92.66436065
file name : Image_22032022184321299.png
|
2022-03-22 18:43:21.412748 |
28 |
55440595 |
Renovation of Girls Toilet at Mirjan Ali Choudhury Pre.Senior U.P |
50000 |
Renovation of Girls Toilet at Mirjan Ali Choudhury Pre.Senior U.P1 |
Completion of work |
-
latitude : 24.89756132
Longitude : 92.63513247
file name : Image_22032022184130421.png
|
2022-03-22 18:41:30.522698 |
29 |
68127088 |
Creation of drainage channel for management of grey water |
284000 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 24.94341793
Longitude : 92.64397476
file name : Image_25042023094857128.png
|
2023-04-25 09:48:57.228902 |
30 |
68127088 |
Creation of drainage channel for management of grey water |
284000 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 24.94341793
Longitude : 92.64397476
file name : Image_25042023094647752.png
|
2023-04-25 09:46:47.847282 |
31 |
68127088 |
Creation of drainage channel for management of grey water |
284000 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 24.9469065
Longitude : 92.67046835
file name : Image_24042023112106114.png
|
2023-04-24 11:21:06.207756 |
32 |
55440556 |
Const.of CC Drain from Rabijul ali house to Ilas Ali Land near the NREGS road at Goragram |
261520 |
Const.of CC Drain from Rabijul ali house to Ilas Ali Land near the NREGS road at Goragram1 |
Roof laid |
-
latitude : 24.953086666666664,24.952941666666668
Longitude : 92.66479833333332,92.66504833333332
file name : Image_02112023165748509.png
|
2023-11-02 16:57:48.564948 |
33 |
55440556 |
Const.of CC Drain from Rabijul ali house to Ilas Ali Land near the NREGS road at Goragram |
261520 |
Const.of CC Drain from Rabijul ali house to Ilas Ali Land near the NREGS road at Goragram1 |
Plinth level |
-
latitude : 24.95311,24.95293333333333
Longitude : 92.66476166666668,92.66502833333334
file name : Image_02112023163640016.png
|
2023-11-02 16:36:40.0738 |
34 |
55440556 |
Const.of CC Drain from Rabijul ali house to Ilas Ali Land near the NREGS road at Goragram |
261520 |
Const.of CC Drain from Rabijul ali house to Ilas Ali Land near the NREGS road at Goragram1 |
Completion of work |
-
latitude : 24.95299197,24.95300252
Longitude : 92.66486183,92.66485132
file name : Image_22032022184332342.png
|
2022-03-22 18:43:32.452877 |
35 |
55440853 |
Const.of CC Block road from PMGSY Road to Badar house at Sewti-I |
252055 |
Const.of CC Block road from PMGSY Road to Badar house at Sewti-I1 |
Roof laid |
-
latitude : 24.942195,24.942188333333334
Longitude : 92.65520666666667,92.65519166666667
file name : Image_10112023111159929.png
|
2023-11-10 11:12:00.020812 |
36 |
55440853 |
Const.of CC Block road from PMGSY Road to Badar house at Sewti-I |
252055 |
Const.of CC Block road from PMGSY Road to Badar house at Sewti-I1 |
Plinth level |
-
latitude : 24.942153333333334,24.9416655,24.942183333333332
Longitude : 92.65516833333335,92.6560019,92.65501166666667
file name : Image_07112023095457614.png
|
2023-11-07 09:54:57.720903 |
37 |
55440853 |
Const.of CC Block road from PMGSY Road to Badar house at Sewti-I |
252055 |
Const.of CC Block road from PMGSY Road to Badar house at Sewti-I1 |
Completion of work |
-
latitude : 24.94210245,24.94210801
Longitude : 92.65512883,92.65516798
file name : Image_22032022184303513.png
|
2022-03-22 18:43:03.621576 |
38 |
68127125 |
CONST OF CC BLOCK ROAD FROM BAHAR UDDIN HOUSE TO AKBAR ALI XVFC 2020-21 2ND |
518000 |
CONST OF CC BLOCK ROAD FROM BAHAR UDDIN HOUSE TO AKBAR ALI XVFC 2020-21 2ND1 |
Roof laid |
-
latitude : 24.95356,24.953943333333335
Longitude : 92.66477833333332,92.66437833333333
file name : Image_02112023165641132.png
|
2023-11-02 16:56:41.2067 |
39 |
68127125 |
CONST OF CC BLOCK ROAD FROM BAHAR UDDIN HOUSE TO AKBAR ALI XVFC 2020-21 2ND |
518000 |
CONST OF CC BLOCK ROAD FROM BAHAR UDDIN HOUSE TO AKBAR ALI XVFC 2020-21 2ND1 |
Plinth level |
-
latitude : 24.953636666666664,24.953613333333337
Longitude : 92.66490166666667,92.66476333333334
file name : Image_02112023164812502.png
|
2023-11-02 16:48:12.559627 |
40 |
68127125 |
CONST OF CC BLOCK ROAD FROM BAHAR UDDIN HOUSE TO AKBAR ALI XVFC 2020-21 2ND |
518000 |
CONST OF CC BLOCK ROAD FROM BAHAR UDDIN HOUSE TO AKBAR ALI XVFC 2020-21 2ND1 |
Completion of work |
-
latitude : 24.95364833333333,24.953968333333332
Longitude : 92.66484166666666,92.66438166666667
file name : Image_02112023163059913.png
|
2023-11-02 16:30:59.996731 |
41 |
68127125 |
CONST OF CC BLOCK ROAD FROM BAHAR UDDIN HOUSE TO AKBAR ALI XVFC 2020-21 2ND |
518000 |
CONST OF CC BLOCK ROAD FROM BAHAR UDDIN HOUSE TO AKBAR ALI XVFC 2020-21 2ND1 |
Completion of work |
-
latitude : 24.95386897,24.95350973
Longitude : 92.6644154,92.66490551
file name : Image_24042023105906141.png
|
2023-04-24 10:59:06.265388 |
42 |
55440426 |
Const.of CMSC at Babur Bazar(Convergence with PHE) |
90000 |
Const.of CMSC at Babur Bazar(Convergence with PHE)1 |
Roof laid |
-
latitude : 24.94958166666667
Longitude : 92.66706500000001
file name : Image_02112023170326168.png
|
2023-11-02 17:03:26.252971 |
43 |
55440426 |
Const.of CMSC at Babur Bazar(Convergence with PHE) |
90000 |
Const.of CMSC at Babur Bazar(Convergence with PHE)1 |
Plinth level |
-
latitude : 24.94958166666667
Longitude : 92.66708666666666
file name : Image_02112023162528251.png
|
2023-11-02 16:25:28.314819 |
44 |
55440426 |
Const.of CMSC at Babur Bazar(Convergence with PHE) |
90000 |
Const.of CMSC at Babur Bazar(Convergence with PHE)1 |
Completion of work |
-
latitude : 24.94945639
Longitude : 92.66702526
file name : Image_30032023100749949.png
|
2023-03-30 10:07:50.049858 |
45 |
69063132 |
Operation & maintenance of drinking water supply system |
533350 |
Operation & maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 24.94197166666667
Longitude : 92.65504166666666
file name : Image_12102023093113359.png
|
2023-10-12 09:31:13.46194 |
46 |
69063873 |
CONST OF B WALL OF SHEWTI GP OFFICE XVFC 2021-22 2ND |
367650 |
CONST OF B WALL OF SHEWTI GP OFFICE XVFC 2021-22 2ND1 |
Plinth level |
-
latitude : 24.9436205
Longitude : 92.6573435
file name : Image_25122023132806366.png
|
2023-12-25 13:28:06.4533 |
47 |
69063873 |
CONST OF B WALL OF SHEWTI GP OFFICE XVFC 2021-22 2ND |
367650 |
CONST OF B WALL OF SHEWTI GP OFFICE XVFC 2021-22 2ND1 |
Completion of work |
-
latitude : 24.943806666666667
Longitude : 92.65737166666668
file name : Image_11112023110616375.png
|
2023-11-11 11:06:16.905926 |
48 |
69063770 |
Creation of drainage channel for management of grey water |
77650 |
Creation of drainage channel for management of grey water1 |
Plinth level |
-
latitude : 24.9436211
Longitude : 92.6573505
file name : Image_25122023132615750.png
|
2023-12-25 13:26:15.854581 |
49 |
69063770 |
Creation of drainage channel for management of grey water |
77650 |
Creation of drainage channel for management of grey water1 |
Plinth level |
-
latitude : 24.9436211
Longitude : 92.6573505
file name : Image_25122023131627213.png
|
2023-12-25 13:16:27.310146 |
50 |
69063770 |
Creation of drainage channel for management of grey water |
77650 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 24.9436105
Longitude : 92.6573407
file name : Image_11112023112152884.png
|
2023-11-11 11:21:52.998303 |
51 |
69063581 |
RENOVATION OF SHEWTI GP OFFICE XVFC 2021-22 1ST |
355500 |
RENOVATION OF SHEWTI GP OFFICE XVFC 2021-22 1ST1 |
Completion of work |
-
latitude : 24.943635000000004
Longitude : 92.65720166666667
file name : Image_11112023111545818.png
|
2023-11-11 11:15:45.912111 |
52 |
69063581 |
RENOVATION OF SHEWTI GP OFFICE XVFC 2021-22 1ST |
355500 |
RENOVATION OF SHEWTI GP OFFICE XVFC 2021-22 1ST1 |
Completion of work |
-
latitude : 24.94359833333333
Longitude : 92.65716166666668
file name : Image_11112023111539538.png
|
2023-11-11 11:15:39.627808 |
53 |
69063488 |
Construction of Community Sanitary Complex |
266400 |
Construction of Community Sanitary Complex1 |
Plinth level |
-
latitude : 24.94358666666667
Longitude : 92.65735166666667
file name : Image_25122023153212474.png
|
2023-12-25 15:32:12.457904 |
54 |
69063488 |
Construction of Community Sanitary Complex |
266400 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 24.9436097
Longitude : 92.6573406
file name : Image_11112023112024378.png
|
2023-11-11 11:20:24.47848 |
55 |
68127033 |
Construction of toilets in public institutions |
50000 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 24.9466141
Longitude : 92.6705664
file name : Image_27042023100417075.png
|
2023-04-27 10:04:17.162384 |
56 |
69063668 |
Construction of Community Sanitary Complex |
189300 |
Construction of Community Sanitary Complex1 |
Plinth level |
-
latitude : 24.946608333333334
Longitude : 92.67093500000001
file name : Image_25122023154239192.png
|
2023-12-25 15:42:38.647521 |
57 |
69063668 |
Construction of Community Sanitary Complex |
189300 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 24.9465389
Longitude : 92.6706574
file name : Image_11112023113456253.png
|
2023-11-11 11:34:56.347314 |
58 |
87341917 |
Const.of CC block road from village road to GP office campus at Sewti PT-I |
150000 |
Const.of CC block road from village road to GP office campus at Sewti PT-I1 |
Completion of work |
-
latitude : 24.94355,24.943726666666667
Longitude : 92.65715833333334,92.65714666666666
file name : Image_19012024151716123.png
|
2024-01-19 15:17:16.204964 |
59 |
87342189 |
Const.of CC block road from MGNREGs road to moinul Hoque house at Sewti PT-I |
217000 |
Const.of CC block road from MGNREGs road to moinul Hoque house at Sewti PT-I1 |
Completion of work |
-
latitude : 24.943321666666666,24.943981666666666
Longitude : 92.65152000000002,92.651445
file name : Image_19012024122702562.png
|
2024-01-19 12:27:02.661533 |
60 |
87341830 |
Renovation of AWC No.76 at Goragram |
217650 |
Renovation of AWC No.76 at Goragram1 |
Completion of work |
-
latitude : 24.948918333333335
Longitude : 92.66761833333334
file name : Image_19012024123848348.png
|
2024-01-19 12:38:48.445809 |
61 |
87342237 |
Const.of boundary wall 512 no.Babur bazar LP School |
150650 |
Const.of boundary wall 512 no.Babur bazar LP School1 |
Completion of work |
-
latitude : 24.94917666666667
Longitude : 92.66730333333335
file name : Image_19012024124115991.png
|
2024-01-19 12:41:16.101518 |
62 |
87341687 |
Operation & maintenance of drinking water supply system |
275500 |
Operation & maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 24.951843333333333
Longitude : 92.66689666666667
file name : Image_03022024141248170.png
|
2024-02-03 14:12:48.257442 |
63 |
87342049 |
Operation & maintenance of drinking water supply system |
276000 |
Operation & maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 24.941963333333334
Longitude : 92.65510333333334
file name : Image_04022024134213687.png
|
2024-02-04 13:42:13.767075 |
64 |
68127169 |
CONST OF B WALL OF BABUR BAZAR KALIMANDIR XVFC 2020-21 2ND |
150000 |
CONST OF B WALL OF BABUR BAZAR KALIMANDIR XVFC 2020-21 2ND1 |
Roof laid |
-
latitude : 24.94703666666667
Longitude : 92.67040666666665
file name : Image_02112023170736387.png
|
2023-11-02 17:07:36.438122 |
65 |
68127169 |
CONST OF B WALL OF BABUR BAZAR KALIMANDIR XVFC 2020-21 2ND |
150000 |
CONST OF B WALL OF BABUR BAZAR KALIMANDIR XVFC 2020-21 2ND1 |
Plinth level |
-
latitude : 24.947091666666665
Longitude : 92.67046333333334
file name : Image_02112023160209502.png
|
2023-11-02 16:02:09.557647 |
66 |
68127169 |
CONST OF B WALL OF BABUR BAZAR KALIMANDIR XVFC 2020-21 2ND |
150000 |
CONST OF B WALL OF BABUR BAZAR KALIMANDIR XVFC 2020-21 2ND1 |
Completion of work |
-
latitude : 24.946617
Longitude : 92.6705641
file name : Image_27042023100238898.png
|
2023-04-27 10:02:38.991417 |
67 |
55440510 |
Const.of CC Drain from Abdul Wahid house to Saidul Rahman House Via Bidhubhushan Nath house at Sewti |
266000 |
Const.of CC Drain from Abdul Wahid house to Saidul Rahman House Via Bidhubhushan Nath house at Sewti1 |
Plinth level |
-
latitude : 24.931363333333334,24.931319999999996
Longitude : 92.64730333333334,92.64726333333334
file name : Image_11112023161945615.png
|
2023-11-11 16:19:45.710325 |
68 |
55440510 |
Const.of CC Drain from Abdul Wahid house to Saidul Rahman House Via Bidhubhushan Nath house at Sewti |
266000 |
Const.of CC Drain from Abdul Wahid house to Saidul Rahman House Via Bidhubhushan Nath house at Sewti1 |
Completion of work |
-
latitude : 24.931378333333335,24.93125166666667
Longitude : 92.64726999999999,92.64724666666667
file name : Image_09112023150258352.png
|
2023-11-09 15:02:58.481354 |
69 |
55440510 |
Const.of CC Drain from Abdul Wahid house to Saidul Rahman House Via Bidhubhushan Nath house at Sewti |
266000 |
Const.of CC Drain from Abdul Wahid house to Saidul Rahman House Via Bidhubhushan Nath house at Sewti1 |
Completion of work |
-
latitude : 24.93148461,24.9314964
Longitude : 92.64746701,92.64748292
file name : Image_23032022214854814.png
|
2022-03-23 21:48:54.948431 |
70 |
103481609 |
Operation and Maintenance of drinking water supply system |
557650 |
Operation and Maintenance of drinking water supply system1 |
Plinth level |
-
latitude : 24.936631666666667
Longitude : 92.59395666666666
file name : Image_24062024143423587.png
|
2024-06-24 14:34:23.690449 |
71 |
103481609 |
Operation and Maintenance of drinking water supply system |
557650 |
Operation and Maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 24.936653333333332
Longitude : 92.59403666666667
file name : Image_24062024142029503.png
|
2024-06-24 14:20:29.612314 |