1 |
55780471 |
CONST OF TOILET AT BALIGAON YUBAK SANGHA |
170000 |
CONST OF TOILET AT BALIGAON YUBAK SANGHA1 |
Roof laid |
-
latitude : 27.30190416
Longitude : 94.85582747
file name : Image_12052022111315976.png
|
2022-05-12 11:13:16.0626 |
2 |
55780471 |
CONST OF TOILET AT BALIGAON YUBAK SANGHA |
170000 |
CONST OF TOILET AT BALIGAON YUBAK SANGHA1 |
Completion of work |
-
latitude : 27.30289965
Longitude : 94.86797551
file name : Image_14012022140214218.png
|
2022-01-14 14:02:14.317369 |
3 |
55780471 |
CONST OF TOILET AT BALIGAON YUBAK SANGHA |
170000 |
CONST OF TOILET AT BALIGAON YUBAK SANGHA1 |
Plinth level |
-
latitude : 27.3018975
Longitude : 94.85594143
file name : Image_18022022123626823.png
|
2022-02-18 12:36:26.939608 |
4 |
55780365 |
CONST OF COMMUNITY MANAGE SANITARY COMPLEX AT KAWOMARI |
90000 |
CONST OF COMMUNITY MANAGE SANITARY COMPLEX AT KAWOMARI1 |
Completion of work |
-
latitude : 27.28145213
Longitude : 94.88651556
file name : Image_23122021125624527.png
|
2021-12-23 12:56:24.646818 |
5 |
64513674 |
CONST. OF DRINKING WATER FACILITY AT NOTUN BOLAI P.H.C. |
148200 |
CONST. OF DRINKING WATER FACILITY AT NOTUN BOLAI P.H.C.1 |
Roof laid |
-
latitude : 27.33632014
Longitude : 94.90620939
file name : Image_10112022155338213.png
|
2022-11-10 15:53:38.319093 |
6 |
64513674 |
CONST. OF DRINKING WATER FACILITY AT NOTUN BOLAI P.H.C. |
148200 |
CONST. OF DRINKING WATER FACILITY AT NOTUN BOLAI P.H.C.1 |
Plinth level |
-
latitude : 27.3362819
Longitude : 94.9061253
file name : Image_13102022100856373.png
|
2022-10-13 10:08:56.476583 |
7 |
64513674 |
CONST. OF DRINKING WATER FACILITY AT NOTUN BOLAI P.H.C. |
148200 |
CONST. OF DRINKING WATER FACILITY AT NOTUN BOLAI P.H.C.1 |
Completion of work |
-
latitude : 27.336185525345847
Longitude : 94.90617383868509
file name : Image_31082022151746073.png
|
2022-08-31 15:17:46.186861 |
8 |
65663331 |
Operation & maintenance of drinking water supply system |
658000 |
Operation & maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 27.33538953,27.33545725
Longitude : 94.90549043,94.90550315
file name : Image_09022023170732482.png
|
2023-02-09 17:07:32.589602 |
9 |
66570417 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.47399833333333
Longitude : 94.91373166666666
file name : Image_10012024090637006.png
|
2024-01-10 09:06:37.093534 |
10 |
66570417 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.32331
Longitude : 94.87551666666668
file name : Image_26062023173025930.png
|
2023-06-26 17:30:26.018557 |
11 |
66570417 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.32337207
Longitude : 94.87550704
file name : Image_25032023160736183.png
|
2023-03-25 16:07:36.301009 |
12 |
66570417 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.32334034
Longitude : 94.8756985
file name : Image_06022023134818839.png
|
2023-02-06 13:48:18.951269 |
13 |
66570454 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.31607632
Longitude : 94.88016703
file name : Image_04042023164146344.png
|
2023-04-04 16:41:46.437813 |
14 |
66570454 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.31611982
Longitude : 94.88014398
file name : Image_17022023140119836.png
|
2023-02-17 14:01:19.940639 |
15 |
66570454 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.31468769
Longitude : 94.8795872
file name : Image_02022023131745314.png
|
2023-02-02 13:17:45.427596 |
16 |
66570713 |
REPAIRING OF ANGANWADI CENTRE AT KAWAIMARI MAJULI |
125100 |
REPAIRING OF ANGANWADI CENTRE AT KAWAIMARI MAJULI1 |
Roof laid |
-
latitude : 27.28039093
Longitude : 94.87338147
file name : Image_11042023140131566.png
|
2023-04-11 14:01:31.703959 |
17 |
66570713 |
REPAIRING OF ANGANWADI CENTRE AT KAWAIMARI MAJULI |
125100 |
REPAIRING OF ANGANWADI CENTRE AT KAWAIMARI MAJULI1 |
Plinth level |
-
latitude : 27.28050728
Longitude : 94.87345676
file name : Image_17032023165803655.png
|
2023-03-17 16:58:03.768215 |
18 |
66570713 |
REPAIRING OF ANGANWADI CENTRE AT KAWAIMARI MAJULI |
125100 |
REPAIRING OF ANGANWADI CENTRE AT KAWAIMARI MAJULI1 |
Completion of work |
-
latitude : 27.2805937
Longitude : 94.87339391
file name : Image_17022023173356604.png
|
2023-02-17 17:33:56.687824 |
19 |
67328215 |
Construction of toilets in public institutions |
52500 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.473941666666665
Longitude : 94.91381833333335
file name : Image_17052024183323811.png
|
2024-05-17 18:33:23.900835 |
20 |
67328215 |
Construction of toilets in public institutions |
52500 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.4741485
Longitude : 94.9137439
file name : Image_17052024183104070.png
|
2024-05-17 18:31:04.154414 |
21 |
67328215 |
Construction of toilets in public institutions |
52500 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.280520000000003
Longitude : 94.87344
file name : Image_01062023160107015.png
|
2023-06-01 16:01:07.132891 |
22 |
65659198 |
REPAIRING OF ANGANWADI CENTRE AT BHOGAMUR TINIALI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT BHOGAMUR TINIALI1 |
Roof laid |
-
latitude : 27.28008333333333
Longitude : 94.83489666666668
file name : Image_08072023160753976.png
|
2023-07-08 16:07:54.064987 |
23 |
65659198 |
REPAIRING OF ANGANWADI CENTRE AT BHOGAMUR TINIALI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT BHOGAMUR TINIALI1 |
Plinth level |
-
latitude : 27.28000921
Longitude : 94.83491849
file name : Image_18052023170004680.png
|
2023-05-18 17:00:04.787194 |
24 |
65659198 |
REPAIRING OF ANGANWADI CENTRE AT BHOGAMUR TINIALI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT BHOGAMUR TINIALI1 |
Completion of work |
-
latitude : 27.28015943
Longitude : 94.83493854
file name : Image_17022023155311295.png
|
2023-02-17 15:53:11.409258 |
25 |
65659217 |
REPAIRING OF ANGANWADI CENTRE AT NAGAON |
131550 |
REPAIRING OF ANGANWADI CENTRE AT NAGAON1 |
Roof laid |
-
latitude : 27.306780000000003
Longitude : 94.87189500000001
file name : Image_08072023162925671.png
|
2023-07-08 16:29:25.7552 |
26 |
65659217 |
REPAIRING OF ANGANWADI CENTRE AT NAGAON |
131550 |
REPAIRING OF ANGANWADI CENTRE AT NAGAON1 |
Plinth level |
-
latitude : 27.306829999999998
Longitude : 94.87185333333333
file name : Image_24062023142819982.png
|
2023-06-24 14:28:20.080907 |
27 |
65659217 |
REPAIRING OF ANGANWADI CENTRE AT NAGAON |
131550 |
REPAIRING OF ANGANWADI CENTRE AT NAGAON1 |
Completion of work |
-
latitude : 27.30690668
Longitude : 94.87187107
file name : Image_17022023152142767.png
|
2023-02-17 15:21:42.870435 |
28 |
67193850 |
Construction of toilets in public institutions |
150000 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.330184999999997
Longitude : 94.89498166666665
file name : Image_24072023172125937.png
|
2023-07-24 17:21:26.036423 |
29 |
67193850 |
Construction of toilets in public institutions |
150000 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.33017166666667
Longitude : 94.89476833333335
file name : Image_09062023151341993.png
|
2023-06-09 15:13:42.091428 |
30 |
67158681 |
INFRASTRUCTURE DEVELOPMENT AT 9 GHARIYA NAMGHAR |
143000 |
INFRASTRUCTURE DEVELOPMENT AT 9 GHARIYA NAMGHAR1 |
Roof laid |
-
latitude : 27.356426666666668
Longitude : 94.919265
file name : Image_12102023173235749.png
|
2023-10-12 17:32:35.880603 |
31 |
67158681 |
INFRASTRUCTURE DEVELOPMENT AT 9 GHARIYA NAMGHAR |
143000 |
INFRASTRUCTURE DEVELOPMENT AT 9 GHARIYA NAMGHAR1 |
Plinth level |
-
latitude : 27.356405000000002
Longitude : 94.91919333333333
file name : Image_24072023181442142.png
|
2023-07-24 18:14:42.240144 |
32 |
67158681 |
INFRASTRUCTURE DEVELOPMENT AT 9 GHARIYA NAMGHAR |
143000 |
INFRASTRUCTURE DEVELOPMENT AT 9 GHARIYA NAMGHAR1 |
Completion of work |
-
latitude : 27.35638666666667
Longitude : 94.91921499999998
file name : Image_05072023185956708.png
|
2023-07-05 18:59:56.822094 |
33 |
67158666 |
CONST. OF CULTURAL CENTRE AT KAWAIMARI SHIBSAGORIA |
137000 |
CONST. OF CULTURAL CENTRE AT KAWAIMARI SHIBSAGORIA1 |
Roof laid |
-
latitude : 27.280956666666665
Longitude : 94.88314166666666
file name : Image_28112023150806759.png
|
2023-11-28 15:08:06.858673 |
34 |
67158666 |
CONST. OF CULTURAL CENTRE AT KAWAIMARI SHIBSAGORIA |
137000 |
CONST. OF CULTURAL CENTRE AT KAWAIMARI SHIBSAGORIA1 |
Plinth level |
-
latitude : 27.280925000000003
Longitude : 94.88317833333333
file name : Image_28072023155414961.png
|
2023-07-28 15:54:15.052597 |
35 |
67158666 |
CONST. OF CULTURAL CENTRE AT KAWAIMARI SHIBSAGORIA |
137000 |
CONST. OF CULTURAL CENTRE AT KAWAIMARI SHIBSAGORIA1 |
Completion of work |
-
latitude : 27.280731666666664
Longitude : 94.88331500000001
file name : Image_01062023180751324.png
|
2023-06-01 18:07:51.46954 |
36 |
67158725 |
INFRASTRUCTURE DEVELOPMENT OF CHAW SENG RANG |
250000 |
INFRASTRUCTURE DEVELOPMENT OF CHAW SENG RANG1 |
Plinth level |
-
latitude : 27.302699999999998
Longitude : 94.86826166666667
file name : Image_02092023144036079.png
|
2023-09-02 14:40:36.173629 |
37 |
67158725 |
INFRASTRUCTURE DEVELOPMENT OF CHAW SENG RANG |
250000 |
INFRASTRUCTURE DEVELOPMENT OF CHAW SENG RANG1 |
Completion of work |
-
latitude : 27.302609999999998
Longitude : 94.86836666666667
file name : Image_24062023141041750.png
|
2023-06-24 14:10:41.83479 |
38 |
66570467 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.330644999999997
Longitude : 94.90912666666667
file name : Image_19082023153646976.png
|
2023-08-19 15:36:47.076585 |
39 |
66570467 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.33045517
Longitude : 94.90928829
file name : Image_18052023174637708.png
|
2023-05-18 17:46:37.814489 |
40 |
66570467 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.33051094
Longitude : 94.90916175
file name : Image_02022023155011216.png
|
2023-02-02 15:50:11.327502 |
41 |
86763227 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 27.34663333333333
Longitude : 94.92585666666668
file name : Image_19082023130634651.png
|
2023-08-19 13:06:34.750198 |
42 |
67193827 |
Construction of toilets in public institutions |
165079 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.319193333333335
Longitude : 94.87597499999998
file name : Image_14102023072833146.png
|
2023-10-14 07:28:33.264086 |
43 |
67193827 |
Construction of toilets in public institutions |
165079 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.319245000000002
Longitude : 94.876045
file name : Image_12092023145025639.png
|
2023-09-12 14:50:25.737233 |
44 |
67193827 |
Construction of toilets in public institutions |
165079 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.319215
Longitude : 94.87599666666668
file name : Image_26062023173010101.png
|
2023-06-26 17:30:10.195429 |
45 |
86763620 |
RENOVATION AT BALIGAON L.P. SCHOOL |
400000 |
RENOVATION AT BALIGAON L.P. SCHOOL1 |
Roof laid |
-
latitude : 27.30049
Longitude : 94.84717
file name : Image_22112023141220232.png
|
2023-11-22 14:12:20.344868 |
46 |
86763620 |
RENOVATION AT BALIGAON L.P. SCHOOL |
400000 |
RENOVATION AT BALIGAON L.P. SCHOOL1 |
Plinth level |
-
latitude : 27.30055333333333
Longitude : 94.84730333333333
file name : Image_08112023134028181.png
|
2023-11-08 13:40:28.684766 |
47 |
86763620 |
RENOVATION AT BALIGAON L.P. SCHOOL |
400000 |
RENOVATION AT BALIGAON L.P. SCHOOL1 |
Completion of work |
-
latitude : 27.300483333333332
Longitude : 94.84730666666668
file name : Image_13102023171450939.png
|
2023-10-13 17:14:51.036579 |
48 |
67193734 |
Creation of community soak pits for group of Households |
55500 |
Creation of community soak pits for group of Households1 |
Roof laid |
-
latitude : 27.474259999999997
Longitude : 94.91387333333333
file name : Image_10012024172053672.png
|
2024-01-10 17:20:53.762391 |
49 |
67193734 |
Creation of community soak pits for group of Households |
55500 |
Creation of community soak pits for group of Households1 |
Plinth level |
-
latitude : 27.4741197
Longitude : 94.9135401
file name : Image_10012024171355173.png
|
2024-01-10 17:13:55.270128 |
50 |
67193734 |
Creation of community soak pits for group of Households |
55500 |
Creation of community soak pits for group of Households1 |
Completion of work |
-
latitude : 27.302741666666666
Longitude : 94.86771833333333
file name : Image_24062023134919448.png
|
2023-06-24 13:49:19.54275 |
51 |
67193538 |
Creation of community compost pits for a group of Households |
87269 |
Creation of community compost pits for a group of Households1 |
Roof laid |
-
latitude : 27.474023333333335
Longitude : 94.91339166666667
file name : Image_10012024172926461.png
|
2024-01-10 17:29:26.549389 |
52 |
67193538 |
Creation of community compost pits for a group of Households |
87269 |
Creation of community compost pits for a group of Households1 |
Plinth level |
-
latitude : 27.474023333333335
Longitude : 94.91339166666667
file name : Image_10012024172609175.png
|
2024-01-10 17:26:09.261636 |
53 |
67193538 |
Creation of community compost pits for a group of Households |
87269 |
Creation of community compost pits for a group of Households1 |
Completion of work |
-
latitude : 27.302786666666666
Longitude : 94.86788666666668
file name : Image_24062023135300243.png
|
2023-06-24 13:53:00.346246 |
54 |
66570520 |
RENOVATION OF CHAW SANG RAN AT KUTUHA G. P. |
300000 |
RENOVATION OF CHAW SANG RAN AT KUTUHA G. P.1 |
Roof laid |
-
latitude : 27.302665
Longitude : 94.86815
file name : Image_02092023143902580.png
|
2023-09-02 14:39:02.686764 |
55 |
66570520 |
RENOVATION OF CHAW SANG RAN AT KUTUHA G. P. |
300000 |
RENOVATION OF CHAW SANG RAN AT KUTUHA G. P.1 |
Plinth level |
-
latitude : 27.30267452
Longitude : 94.8678321
file name : Image_06032023164622436.png
|
2023-03-06 16:46:22.540278 |
56 |
66570520 |
RENOVATION OF CHAW SANG RAN AT KUTUHA G. P. |
300000 |
RENOVATION OF CHAW SANG RAN AT KUTUHA G. P.1 |
Completion of work |
-
latitude : 27.30260115
Longitude : 94.86820351
file name : Image_02022023134927426.png
|
2023-02-02 13:49:27.543941 |
57 |
66570750 |
INFRASTRUCTURE DEVELOPMENT AT BHOGAMUR SWIS GATE |
125100 |
INFRASTRUCTURE DEVELOPMENT AT BHOGAMUR SWIS GATE1 |
Roof laid |
-
latitude : 27.28742833333333,27.287388333333336
Longitude : 94.82914666666666,94.82908333333334
file name : Image_26012024115958026.png
|
2024-01-26 11:59:58.113786 |
58 |
66570750 |
INFRASTRUCTURE DEVELOPMENT AT BHOGAMUR SWIS GATE |
125100 |
INFRASTRUCTURE DEVELOPMENT AT BHOGAMUR SWIS GATE1 |
Plinth level |
-
latitude : 27.28741074,27.28741075
Longitude : 94.82912405,94.82912429
file name : Image_17022023130610749.png
|
2023-02-17 13:06:10.851365 |
59 |
66570750 |
INFRASTRUCTURE DEVELOPMENT AT BHOGAMUR SWIS GATE |
125100 |
INFRASTRUCTURE DEVELOPMENT AT BHOGAMUR SWIS GATE1 |
Completion of work |
-
latitude : 27.28731622,27.28740539
Longitude : 94.82894835,94.82901251
file name : Image_14022023131146255.png
|
2023-02-14 13:11:46.345214 |
60 |
86763734 |
RENOVATION OF COMMUNITY HALL AT NOTUN BOLAI |
317000 |
RENOVATION OF COMMUNITY HALL AT NOTUN BOLAI1 |
Plinth level |
-
latitude : 27.336413333333333
Longitude : 94.90581833333333
file name : Image_21022024163834038.png
|
2024-02-21 16:38:34.235286 |
61 |
86763734 |
RENOVATION OF COMMUNITY HALL AT NOTUN BOLAI |
317000 |
RENOVATION OF COMMUNITY HALL AT NOTUN BOLAI1 |
Completion of work |
-
latitude : 27.336426666666664
Longitude : 94.90585666666666
file name : Image_18112023232820836.png
|
2023-11-18 23:28:20.925889 |
62 |
41594730 |
Const. of Kristi Vikash Sangha at Deori Block |
300000 |
Const. of Kristi Vikash Sangha at Deori Block1 |
Roof laid |
-
latitude : 27.32274964
Longitude : 94.91877866
file name : Image_23092022123400346.png
|
2022-09-23 12:34:00.518596 |
63 |
41594730 |
Const. of Kristi Vikash Sangha at Deori Block |
300000 |
Const. of Kristi Vikash Sangha at Deori Block1 |
Plinth level |
-
latitude : 27.32276822
Longitude : 94.91867657
file name : Image_12052022143043529.png
|
2022-05-12 14:30:43.68516 |
64 |
41594730 |
Const. of Kristi Vikash Sangha at Deori Block |
300000 |
Const. of Kristi Vikash Sangha at Deori Block1 |
Completion of work |
-
latitude : 27.32274497
Longitude : 94.91878966
file name : Image_18022022135422060.png
|
2022-02-18 13:54:22.242115 |
65 |
64513723 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR P.H.C. |
148200 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR P.H.C.1 |
Roof laid |
-
latitude : 27.29360511
Longitude : 94.84017101
file name : Image_11012023155806680.png
|
2023-01-11 15:58:06.81451 |
66 |
64513723 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR P.H.C. |
148200 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR P.H.C.1 |
Plinth level |
-
latitude : 27.29365519
Longitude : 94.83986236
file name : Image_04112022141509170.png
|
2022-11-04 14:15:09.265734 |
67 |
64513723 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR P.H.C. |
148200 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR P.H.C.1 |
Completion of work |
-
latitude : 27.29351917
Longitude : 94.8402059
file name : Image_16082022135807182.png
|
2022-08-16 13:58:07.308767 |
68 |
64513756 |
CONST. OF DRINKING WATER FACILITY AT 26 GHARIA CULTURAL CENTRE |
148200 |
CONST. OF DRINKING WATER FACILITY AT 26 GHARIA CULTURAL CENTRE1 |
Roof laid |
-
latitude : 27.34977332
Longitude : 94.92865233
file name : Image_05112022105837626.png
|
2022-11-05 10:58:37.732014 |
69 |
64513756 |
CONST. OF DRINKING WATER FACILITY AT 26 GHARIA CULTURAL CENTRE |
148200 |
CONST. OF DRINKING WATER FACILITY AT 26 GHARIA CULTURAL CENTRE1 |
Plinth level |
-
latitude : 27.34978104
Longitude : 94.92864868
file name : Image_21092022164730600.png
|
2022-09-21 16:47:30.706668 |
70 |
64513756 |
CONST. OF DRINKING WATER FACILITY AT 26 GHARIA CULTURAL CENTRE |
148200 |
CONST. OF DRINKING WATER FACILITY AT 26 GHARIA CULTURAL CENTRE1 |
Completion of work |
-
latitude : 27.34999913
Longitude : 94.92858981
file name : Image_16082022121940011.png
|
2022-08-16 12:19:40.125608 |
71 |
55780522 |
UPGRADATION OF CHAW SANG REN AT BALIGAON |
500000 |
UPGRADATION OF CHAW SANG REN AT BALIGAON1 |
Roof laid |
-
latitude : 27.30267951
Longitude : 94.86826264
file name : Image_29082022134123333.png
|
2022-08-29 13:41:23.447146 |
72 |
55780522 |
UPGRADATION OF CHAW SANG REN AT BALIGAON |
500000 |
UPGRADATION OF CHAW SANG REN AT BALIGAON1 |
Plinth level |
-
latitude : 27.30265516
Longitude : 94.86819704
file name : Image_25072022144736572.png
|
2022-07-25 14:47:36.696391 |
73 |
55780522 |
UPGRADATION OF CHAW SANG REN AT BALIGAON |
500000 |
UPGRADATION OF CHAW SANG REN AT BALIGAON1 |
Completion of work |
-
latitude : 27.30258372
Longitude : 94.86814559
file name : Image_06072022161442941.png
|
2022-07-06 16:14:43.039587 |
74 |
64513554 |
CONST. OF TOILET AT MAZGAON CULTURAL CENTRE NAGAON |
148200 |
CONST. OF TOILET AT MAZGAON CULTURAL CENTRE NAGAON1 |
Roof laid |
-
latitude : 27.3053775
Longitude : 94.86738789
file name : Image_19112022144943356.png
|
2022-11-19 14:49:43.492771 |
75 |
64513554 |
CONST. OF TOILET AT MAZGAON CULTURAL CENTRE NAGAON |
148200 |
CONST. OF TOILET AT MAZGAON CULTURAL CENTRE NAGAON1 |
Plinth level |
-
latitude : 27.30523031
Longitude : 94.86738991
file name : Image_10092022153213988.png
|
2022-09-10 15:32:14.09564 |
76 |
64513554 |
CONST. OF TOILET AT MAZGAON CULTURAL CENTRE NAGAON |
148200 |
CONST. OF TOILET AT MAZGAON CULTURAL CENTRE NAGAON1 |
Completion of work |
-
latitude : 27.30533351
Longitude : 94.8675085
file name : Image_16082022134327613.png
|
2022-08-16 13:43:27.724315 |
77 |
64514406 |
CONST. OF BHOGAMUR BLOCK GAON SWIS GATE |
382000 |
CONST. OF BHOGAMUR BLOCK GAON SWIS GATE1 |
Roof laid |
-
latitude : 27.28741416,27.28742377
Longitude : 94.82889362,94.82890456
file name : Image_28092022144547013.png
|
2022-09-28 14:45:47.126523 |
78 |
64514406 |
CONST. OF BHOGAMUR BLOCK GAON SWIS GATE |
382000 |
CONST. OF BHOGAMUR BLOCK GAON SWIS GATE1 |
Plinth level |
-
latitude : 27.28719189,27.28726495
Longitude : 94.82888694,94.82899823
file name : Image_23092022191544485.png
|
2022-09-23 19:15:44.572048 |
79 |
64514406 |
CONST. OF BHOGAMUR BLOCK GAON SWIS GATE |
382000 |
CONST. OF BHOGAMUR BLOCK GAON SWIS GATE1 |
Completion of work |
-
latitude : 27.28721789,27.28732543
Longitude : 94.82899936,94.82906157
file name : Image_16082022152117390.png
|
2022-08-16 15:21:17.491672 |
80 |
64513901 |
CONST. OF G. P. OFFICE COMMUNITY HALL |
500000 |
CONST. OF G. P. OFFICE COMMUNITY HALL1 |
Roof laid |
-
latitude : 27.31940859
Longitude : 94.87563395
file name : Image_07042023134238465.png
|
2023-04-07 13:42:38.557873 |
81 |
64513901 |
CONST. OF G. P. OFFICE COMMUNITY HALL |
500000 |
CONST. OF G. P. OFFICE COMMUNITY HALL1 |
Plinth level |
-
latitude : 27.31951335
Longitude : 94.87552826
file name : Image_18012023163717003.png
|
2023-01-18 16:37:17.163341 |
82 |
64513901 |
CONST. OF G. P. OFFICE COMMUNITY HALL |
500000 |
CONST. OF G. P. OFFICE COMMUNITY HALL1 |
Completion of work |
-
latitude : 27.31946821
Longitude : 94.87556967
file name : Image_29082022154432542.png
|
2022-08-29 15:44:32.646166 |
83 |
55780433 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BHOGAMUR NEPALI BLOCK ME SCHOOL |
400000 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BHOGAMUR NEPALI BLOCK ME SCHOOL1 |
Roof laid |
-
latitude : 27.2801017
Longitude : 94.83464129
file name : Image_12052022112637422.png
|
2022-05-12 11:26:37.516554 |
84 |
55780433 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BHOGAMUR NEPALI BLOCK ME SCHOOL |
400000 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BHOGAMUR NEPALI BLOCK ME SCHOOL1 |
Completion of work |
-
latitude : 27.27997692
Longitude : 94.83475379
file name : Image_14012022142843641.png
|
2022-01-14 14:28:43.752519 |
85 |
55780433 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BHOGAMUR NEPALI BLOCK ME SCHOOL |
400000 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BHOGAMUR NEPALI BLOCK ME SCHOOL1 |
Plinth level |
-
latitude : 27.28013883
Longitude : 94.83466618
file name : Image_18022022125106912.png
|
2022-02-18 12:51:07.046803 |
86 |
55780433 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BHOGAMUR NEPALI BLOCK ME SCHOOL |
400000 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BHOGAMUR NEPALI BLOCK ME SCHOOL1 |
Plinth level |
-
latitude : 27.28013883
Longitude : 94.83466618
file name : Image_18022022125231100.png
|
2022-02-18 12:52:31.214323 |
87 |
55780564 |
CONST OF FOOT BRIDGE AT JOKAI BON KACHARI GAON |
184530 |
CONST OF FOOT BRIDGE AT JOKAI BON KACHARI GAON1 |
Roof laid |
-
latitude : 27.36015388
Longitude : 94.9306484
file name : Image_25082022134954540.png
|
2022-08-25 13:49:54.64596 |
88 |
55780564 |
CONST OF FOOT BRIDGE AT JOKAI BON KACHARI GAON |
184530 |
CONST OF FOOT BRIDGE AT JOKAI BON KACHARI GAON1 |
Plinth level |
-
latitude : 27.36007049
Longitude : 94.93058528
file name : Image_28072022174620543.png
|
2022-07-28 17:46:20.669001 |
89 |
55780564 |
CONST OF FOOT BRIDGE AT JOKAI BON KACHARI GAON |
184530 |
CONST OF FOOT BRIDGE AT JOKAI BON KACHARI GAON1 |
Completion of work |
-
latitude : 27.36039517
Longitude : 94.93232547
file name : Image_06072022174228716.png
|
2022-07-06 17:42:28.809153 |
90 |
64513954 |
CONST. OF PURONI BOLAI MARKET SHOP |
400000 |
CONST. OF PURONI BOLAI MARKET SHOP1 |
Roof laid |
-
latitude : 27.33012161
Longitude : 94.89476191
file name : Image_30112022084603569.png
|
2022-11-30 08:46:03.671293 |
91 |
64513954 |
CONST. OF PURONI BOLAI MARKET SHOP |
400000 |
CONST. OF PURONI BOLAI MARKET SHOP1 |
Plinth level |
-
latitude : 27.33024178
Longitude : 94.89481237
file name : Image_23092022123416553.png
|
2022-09-23 12:34:16.674038 |
92 |
64513954 |
CONST. OF PURONI BOLAI MARKET SHOP |
400000 |
CONST. OF PURONI BOLAI MARKET SHOP1 |
Completion of work |
-
latitude : 27.33015058
Longitude : 94.89488787
file name : Image_21082022085610694.png
|
2022-08-21 08:56:10.814219 |
93 |
55780393 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BINAPANI HIGH SCHOOL |
400000 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BINAPANI HIGH SCHOOL1 |
Roof laid |
-
latitude : 27.30274088
Longitude : 94.86784035
file name : Image_12052022114400018.png
|
2022-05-12 11:44:00.124017 |
94 |
55780393 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BINAPANI HIGH SCHOOL |
400000 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BINAPANI HIGH SCHOOL1 |
Completion of work |
-
latitude : 27.30276975
Longitude : 94.86802877
file name : Image_14012022134536959.png
|
2022-01-14 13:45:37.049911 |
95 |
55780393 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BINAPANI HIGH SCHOOL |
400000 |
CONST OF TOILET AND DRINKING WATER FACILITY AT BINAPANI HIGH SCHOOL1 |
Plinth level |
-
latitude : 27.3027179
Longitude : 94.86782555
file name : Image_18022022122600606.png
|
2022-02-18 12:26:00.735656 |
96 |
55780487 |
CONST OF TOILET AT NOTUN BOLAI COMMUNITY HALL |
152811 |
CONST OF TOILET AT NOTUN BOLAI COMMUNITY HALL1 |
Roof laid |
-
latitude : 27.33354082
Longitude : 94.90692434
file name : Image_23052022151227614.png
|
2022-05-23 15:12:27.714074 |
97 |
55780487 |
CONST OF TOILET AT NOTUN BOLAI COMMUNITY HALL |
152811 |
CONST OF TOILET AT NOTUN BOLAI COMMUNITY HALL1 |
Completion of work |
-
latitude : 27.33327299
Longitude : 94.90707623
file name : Image_18012022121908929.png
|
2022-01-18 12:19:09.053651 |
98 |
55780487 |
CONST OF TOILET AT NOTUN BOLAI COMMUNITY HALL |
152811 |
CONST OF TOILET AT NOTUN BOLAI COMMUNITY HALL1 |
Plinth level |
-
latitude : 27.33348696
Longitude : 94.90700397
file name : Image_18022022132242929.png
|
2022-02-18 13:22:43.043667 |
99 |
64513778 |
CONST. OF DRINKING WATER FACILTY AT BOLAIBARI ANGANWADI CENTRE |
148200 |
CONST. OF DRINKING WATER FACILTY AT BOLAIBARI ANGANWADI CENTRE1 |
Roof laid |
-
latitude : 27.36886682
Longitude : 94.91395749
file name : Image_30112022080249798.png
|
2022-11-30 08:02:49.880005 |
100 |
64513778 |
CONST. OF DRINKING WATER FACILTY AT BOLAIBARI ANGANWADI CENTRE |
148200 |
CONST. OF DRINKING WATER FACILTY AT BOLAIBARI ANGANWADI CENTRE1 |
Plinth level |
-
latitude : 27.36883222
Longitude : 94.91405528
file name : Image_22092022115254368.png
|
2022-09-22 11:52:54.529769 |
101 |
64513778 |
CONST. OF DRINKING WATER FACILTY AT BOLAIBARI ANGANWADI CENTRE |
148200 |
CONST. OF DRINKING WATER FACILTY AT BOLAIBARI ANGANWADI CENTRE1 |
Completion of work |
-
latitude : 27.36881425
Longitude : 94.91402222
file name : Image_09082022121249183.png
|
2022-08-09 12:12:49.290931 |
102 |
64513928 |
CONST. OF BALIGAON CULTURAL CENTRE |
200000 |
CONST. OF BALIGAON CULTURAL CENTRE 1 |
Roof laid |
-
latitude : 27.30171032
Longitude : 94.85597389
file name : Image_23032023163410782.png
|
2023-03-23 16:34:10.901708 |
103 |
64513928 |
CONST. OF BALIGAON CULTURAL CENTRE |
200000 |
CONST. OF BALIGAON CULTURAL CENTRE 1 |
Plinth level |
-
latitude : 27.30198998
Longitude : 94.85561592
file name : Image_05122022162805395.png
|
2022-12-05 16:28:05.525008 |
104 |
64513928 |
CONST. OF BALIGAON CULTURAL CENTRE |
200000 |
CONST. OF BALIGAON CULTURAL CENTRE 1 |
Completion of work |
-
latitude : 27.30184104
Longitude : 94.85584138
file name : Image_29082022134954789.png
|
2022-08-29 13:49:54.910992 |
105 |
64513623 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR TINIALI YUBAK SANGHA |
148200 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR TINIALI YUBAK SANGHA1 |
Roof laid |
-
latitude : 27.2832111
Longitude : 94.83552848
file name : Image_11012023161805037.png
|
2023-01-11 16:18:05.144934 |
106 |
64513623 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR TINIALI YUBAK SANGHA |
148200 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR TINIALI YUBAK SANGHA1 |
Plinth level |
-
latitude : 27.28314023
Longitude : 94.8354956
file name : Image_04112022142358266.png
|
2022-11-04 14:23:58.368426 |
107 |
64513623 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR TINIALI YUBAK SANGHA |
148200 |
CONST. OF DRINKING WATER FACILITY AT BHOGAMUR TINIALI YUBAK SANGHA1 |
Completion of work |
-
latitude : 27.28320373
Longitude : 94.835511
file name : Image_16082022145956765.png
|
2022-08-16 14:59:56.879797 |
108 |
55780331 |
CONST OF COMMUNITY MANAGE SANITARY COMPLEX AT NAOJAN |
90000 |
CONST OF COMMUNITY MANAGE SANITARY COMPLEX AT NAOJAN1 |
Completion of work |
-
latitude : 27.32074736
Longitude : 94.87828571
file name : Image_23122021130840511.png
|
2021-12-23 13:08:40.624889 |
109 |
55780507 |
IMP OF PANGOYACHUK CULTURAL CENTRE |
350000 |
IMP OF PANGOYACHUK CULTURAL CENTRE1 |
Roof laid |
-
latitude : 27.30234937
Longitude : 94.86530188
file name : Image_12052022110750492.png
|
2022-05-12 11:07:50.598662 |
110 |
55780507 |
IMP OF PANGOYACHUK CULTURAL CENTRE |
350000 |
IMP OF PANGOYACHUK CULTURAL CENTRE1 |
Completion of work |
-
latitude : 27.30225796
Longitude : 94.86523459
file name : Image_14012022152326647.png
|
2022-01-14 15:23:26.753928 |
111 |
55780507 |
IMP OF PANGOYACHUK CULTURAL CENTRE |
350000 |
IMP OF PANGOYACHUK CULTURAL CENTRE1 |
Plinth level |
-
latitude : 27.30247906
Longitude : 94.86492194
file name : Image_18022022123151124.png
|
2022-02-18 12:31:51.24787 |
112 |
65659210 |
REPAIRING OF ANGANWADI CENTRE AT JOKAI BONKOIBATRA GAON |
131550 |
REPAIRING OF ANGANWADI CENTRE AT JOKAI BONKOIBATRA GAON1 |
Roof laid |
-
latitude : 27.34998446
Longitude : 94.92876611
file name : Image_11042023201128905.png
|
2023-04-11 20:11:29.021683 |
113 |
65659210 |
REPAIRING OF ANGANWADI CENTRE AT JOKAI BONKOIBATRA GAON |
131550 |
REPAIRING OF ANGANWADI CENTRE AT JOKAI BONKOIBATRA GAON1 |
Plinth level |
-
latitude : 27.35003089
Longitude : 94.92877796
file name : Image_09022023153005900.png
|
2023-02-09 15:30:06.02203 |
114 |
65659210 |
REPAIRING OF ANGANWADI CENTRE AT JOKAI BONKOIBATRA GAON |
131550 |
REPAIRING OF ANGANWADI CENTRE AT JOKAI BONKOIBATRA GAON1 |
Completion of work |
-
latitude : 27.34985702
Longitude : 94.92877497
file name : Image_06022023170136760.png
|
2023-02-06 17:01:36.885389 |
115 |
64294417 |
CONST. OF TOILET AT KAWOIMARI SHIBSAGORIA CULTURAL CENTRE |
148200 |
CONST. OF TOILET AT KAWOIMARI SHIBSAGORIA CULTURAL CENTRE1 |
Roof laid |
-
latitude : 27.28083986
Longitude : 94.88341764
file name : Image_30112022092813049.png
|
2022-11-30 09:28:13.1723 |
116 |
64294417 |
CONST. OF TOILET AT KAWOIMARI SHIBSAGORIA CULTURAL CENTRE |
148200 |
CONST. OF TOILET AT KAWOIMARI SHIBSAGORIA CULTURAL CENTRE1 |
Plinth level |
-
latitude : 27.28087666
Longitude : 94.8834687
file name : Image_24082022171545919.png
|
2022-08-24 17:15:46.021315 |
117 |
64294417 |
CONST. OF TOILET AT KAWOIMARI SHIBSAGORIA CULTURAL CENTRE |
148200 |
CONST. OF TOILET AT KAWOIMARI SHIBSAGORIA CULTURAL CENTRE1 |
Completion of work |
-
latitude : 27.28097108
Longitude : 94.88337027
file name : Image_15082022123124704.png
|
2022-08-15 12:31:24.801479 |
118 |
64513585 |
CONST. OF TOILET AT 27 GHARIA WEEKLY MARKET |
148200 |
CONST. OF TOILET AT 27 GHARIA WEEKLY MARKET1 |
Roof laid |
-
latitude : 27.3480035
Longitude : 94.91774105
file name : Image_27092022114221486.png
|
2022-09-27 11:42:21.61209 |
119 |
64513585 |
CONST. OF TOILET AT 27 GHARIA WEEKLY MARKET |
148200 |
CONST. OF TOILET AT 27 GHARIA WEEKLY MARKET1 |
Plinth level |
-
latitude : 27.34787586
Longitude : 94.91777018
file name : Image_10092022124606403.png
|
2022-09-10 12:46:06.539276 |
120 |
64513585 |
CONST. OF TOILET AT 27 GHARIA WEEKLY MARKET |
148200 |
CONST. OF TOILET AT 27 GHARIA WEEKLY MARKET1 |
Completion of work |
-
latitude : 27.34794499
Longitude : 94.91778243
file name : Image_13082022175750770.png
|
2022-08-13 17:57:50.900575 |
121 |
64294427 |
CONST, OF TOILET AT KAWOIMARI KALI MANDIR |
148200 |
CONST, OF TOILET AT KAWOIMARI KALI MANDIR1 |
Roof laid |
-
latitude : 27.28010924
Longitude : 94.88000288
file name : Image_30112022092054869.png
|
2022-11-30 09:20:54.963113 |
122 |
64294427 |
CONST, OF TOILET AT KAWOIMARI KALI MANDIR |
148200 |
CONST, OF TOILET AT KAWOIMARI KALI MANDIR1 |
Plinth level |
-
latitude : 27.28003232
Longitude : 94.8797056
file name : Image_24082022153416424.png
|
2022-08-24 15:34:16.549979 |
123 |
64294427 |
CONST, OF TOILET AT KAWOIMARI KALI MANDIR |
148200 |
CONST, OF TOILET AT KAWOIMARI KALI MANDIR1 |
Completion of work |
-
latitude : 27.28000585
Longitude : 94.8795411
file name : Image_15082022123622648.png
|
2022-08-15 12:36:22.738905 |
124 |
64513799 |
CONST. OF TOILET AT BALIGAON PANIGAYA CHUK NAMGHAR |
148200 |
CONST. OF TOILET AT BALIGAON PANIGAYA CHUK NAMGHAR1 |
Roof laid |
-
latitude : 27.30236983
Longitude : 94.86552044
file name : Image_29092022141720391.png
|
2022-09-29 14:17:20.504193 |
125 |
64513799 |
CONST. OF TOILET AT BALIGAON PANIGAYA CHUK NAMGHAR |
148200 |
CONST. OF TOILET AT BALIGAON PANIGAYA CHUK NAMGHAR1 |
Plinth level |
-
latitude : 27.30229096
Longitude : 94.86539256
file name : Image_10092022153800070.png
|
2022-09-10 15:38:00.165891 |
126 |
64513799 |
CONST. OF TOILET AT BALIGAON PANIGAYA CHUK NAMGHAR |
148200 |
CONST. OF TOILET AT BALIGAON PANIGAYA CHUK NAMGHAR1 |
Completion of work |
-
latitude : 27.30226336
Longitude : 94.86548127
file name : Image_09082022145640680.png
|
2022-08-09 14:56:40.783687 |
127 |
55780452 |
SOLID WASTE MANAGEMENT PROJECT AT KUTUHA GP AREA |
180000 |
SOLID WASTE MANAGEMENT PROJECT AT KUTUHA GP AREA1 |
Roof laid |
-
latitude : 27.34786362
Longitude : 94.9176996
file name : Image_19092022160934688.png
|
2022-09-19 16:09:34.799837 |
128 |
55780452 |
SOLID WASTE MANAGEMENT PROJECT AT KUTUHA GP AREA |
180000 |
SOLID WASTE MANAGEMENT PROJECT AT KUTUHA GP AREA1 |
Plinth level |
-
latitude : 27.34792327
Longitude : 94.91784823
file name : Image_24082022121817208.png
|
2022-08-24 12:18:17.339031 |
129 |
55780452 |
SOLID WASTE MANAGEMENT PROJECT AT KUTUHA GP AREA |
180000 |
SOLID WASTE MANAGEMENT PROJECT AT KUTUHA GP AREA1 |
Completion of work |
-
latitude : 27.34824761
Longitude : 94.91740412
file name : Image_29062022145549818.png
|
2022-06-29 14:55:49.9563 |
130 |
66570603 |
INFRASTRUCTURE DEVELOPMENT AT 2 NO. NAWJAN KALI MANDIR |
166500 |
INFRASTRUCTURE DEVELOPMENT AT 2 NO. NAWJAN KALI MANDIR1 |
Roof laid |
-
latitude : 27.32684871
Longitude : 94.87636036
file name : Image_04042023175620002.png
|
2023-04-04 17:56:20.074647 |
131 |
66570603 |
INFRASTRUCTURE DEVELOPMENT AT 2 NO. NAWJAN KALI MANDIR |
166500 |
INFRASTRUCTURE DEVELOPMENT AT 2 NO. NAWJAN KALI MANDIR1 |
Plinth level |
-
latitude : 27.32698182
Longitude : 94.87631315
file name : Image_06032023122522909.png
|
2023-03-06 12:25:23.001378 |
132 |
66570603 |
INFRASTRUCTURE DEVELOPMENT AT 2 NO. NAWJAN KALI MANDIR |
166500 |
INFRASTRUCTURE DEVELOPMENT AT 2 NO. NAWJAN KALI MANDIR1 |
Completion of work |
-
latitude : 27.32695543
Longitude : 94.87628823
file name : Image_06022023132514323.png
|
2023-02-06 13:25:14.41878 |
133 |
65659114 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.336238333333334
Longitude : 94.90619166666666
file name : Image_05072023184652613.png
|
2023-07-05 18:46:52.711388 |
134 |
65659114 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.33633047
Longitude : 94.90616661
file name : Image_05012023121933213.png
|
2023-01-05 12:19:33.321616 |
135 |
65659114 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.33613828
Longitude : 94.90621729
file name : Image_30112022083228042.png
|
2022-11-30 08:32:28.141989 |
136 |
65659128 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.33290025
Longitude : 94.8963965
file name : Image_07042023130511666.png
|
2023-04-07 13:05:11.776749 |
137 |
65659128 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.33298018
Longitude : 94.8963825
file name : Image_11012023142131013.png
|
2023-01-11 14:21:31.133938 |
138 |
65659128 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.33287089
Longitude : 94.8963577
file name : Image_30112022085013368.png
|
2022-11-30 08:50:13.463593 |
139 |
65659149 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.3019
Longitude : 94.84947500000001
file name : Image_01062023134156360.png
|
2023-06-01 13:41:56.491828 |
140 |
65659149 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.30195191
Longitude : 94.84956918
file name : Image_04042023173002941.png
|
2023-04-04 17:30:03.022025 |
141 |
65659149 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.3018472
Longitude : 94.84966414
file name : Image_30112022095955886.png
|
2022-11-30 09:59:55.990056 |
142 |
66570731 |
INFRASTRUCTURE DEVELOPMENT AT PURONI BOLAI YUBAK SANGHA |
166500 |
INFRASTRUCTURE DEVELOPMENT AT PURONI BOLAI YUBAK SANGHA1 |
Roof laid |
-
latitude : 27.33249472
Longitude : 94.89692114
file name : Image_07042023131032649.png
|
2023-04-07 13:10:32.737521 |
143 |
66570731 |
INFRASTRUCTURE DEVELOPMENT AT PURONI BOLAI YUBAK SANGHA |
166500 |
INFRASTRUCTURE DEVELOPMENT AT PURONI BOLAI YUBAK SANGHA1 |
Plinth level |
-
latitude : 27.33211262
Longitude : 94.89676304
file name : Image_17022023134514279.png
|
2023-02-17 13:45:14.378008 |
144 |
66570731 |
INFRASTRUCTURE DEVELOPMENT AT PURONI BOLAI YUBAK SANGHA |
166500 |
INFRASTRUCTURE DEVELOPMENT AT PURONI BOLAI YUBAK SANGHA1 |
Completion of work |
-
latitude : 27.33241137
Longitude : 94.89682222
file name : Image_02022023130010460.png
|
2023-02-02 13:00:10.629234 |
145 |
66570479 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.35647015
Longitude : 94.9192263
file name : Image_13042023233253731.png
|
2023-04-13 23:32:53.837391 |
146 |
66570479 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.3565676
Longitude : 94.91939122
file name : Image_09032023173324514.png
|
2023-03-09 17:33:24.623823 |
147 |
66570479 |
Construction of toilets in public institutions |
156250 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.35653085
Longitude : 94.9194478
file name : Image_31012023155342468.png
|
2023-01-31 15:53:42.583265 |
148 |
65659164 |
REPAIRING OF ANGANWADI CENTRE AT KUTUHA (NIBUK) |
131550 |
REPAIRING OF ANGANWADI CENTRE AT KUTUHA (NIBUK)1 |
Roof laid |
-
latitude : 27.323316666666663
Longitude : 94.87539999999998
file name : Image_26062023173132695.png
|
2023-06-26 17:31:32.818965 |
149 |
65659164 |
REPAIRING OF ANGANWADI CENTRE AT KUTUHA (NIBUK) |
131550 |
REPAIRING OF ANGANWADI CENTRE AT KUTUHA (NIBUK)1 |
Plinth level |
-
latitude : 27.32342458
Longitude : 94.87540527
file name : Image_25032023160336031.png
|
2023-03-25 16:03:36.135589 |
150 |
65659164 |
REPAIRING OF ANGANWADI CENTRE AT KUTUHA (NIBUK) |
131550 |
REPAIRING OF ANGANWADI CENTRE AT KUTUHA (NIBUK)1 |
Completion of work |
-
latitude : 27.32340273
Longitude : 94.87537489
file name : Image_06022023134522973.png
|
2023-02-06 13:45:23.085764 |
151 |
65659188 |
REPAIRING OF ANGANWADI CENTRE AT PURONI BOLAI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT PURONI BOLAI1 |
Roof laid |
-
latitude : 27.332558333333335
Longitude : 94.89679
file name : Image_28062023171628308.png
|
2023-06-28 17:16:28.398144 |
152 |
65659188 |
REPAIRING OF ANGANWADI CENTRE AT PURONI BOLAI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT PURONI BOLAI1 |
Plinth level |
-
latitude : 27.33251864
Longitude : 94.89675876
file name : Image_07042023131213858.png
|
2023-04-07 13:12:13.951341 |
153 |
65659188 |
REPAIRING OF ANGANWADI CENTRE AT PURONI BOLAI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT PURONI BOLAI1 |
Completion of work |
-
latitude : 27.33260511
Longitude : 94.89684981
file name : Image_17022023134520517.png
|
2023-02-17 13:45:20.626483 |
154 |
65659178 |
REPAIRING OF ANGANWADI CENTRE AT NOTUN BOLAI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT NOTUN BOLAI1 |
Roof laid |
-
latitude : 27.33281833333333
Longitude : 94.90575666666668
file name : Image_28062023183333138.png
|
2023-06-28 18:33:33.224014 |
155 |
65659178 |
REPAIRING OF ANGANWADI CENTRE AT NOTUN BOLAI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT NOTUN BOLAI1 |
Plinth level |
-
latitude : 27.33270548
Longitude : 94.90576656
file name : Image_18052023174641938.png
|
2023-05-18 17:46:42.063942 |
156 |
65659178 |
REPAIRING OF ANGANWADI CENTRE AT NOTUN BOLAI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT NOTUN BOLAI1 |
Plinth level |
-
latitude : 27.33270548
Longitude : 94.90576656
file name : Image_18052023174646161.png
|
2023-05-18 17:46:46.272506 |
157 |
65659178 |
REPAIRING OF ANGANWADI CENTRE AT NOTUN BOLAI |
131550 |
REPAIRING OF ANGANWADI CENTRE AT NOTUN BOLAI1 |
Completion of work |
-
latitude : 27.33275364
Longitude : 94.90569357
file name : Image_17022023130614513.png
|
2023-02-17 13:06:14.612241 |
158 |
67158637 |
CONST. OF CULTURAL CENTRE AT 10 GHARIYA |
137000 |
CONST. OF CULTURAL CENTRE AT 10 GHARIYA1 |
Roof laid |
-
latitude : 27.356550000000002
Longitude : 94.933055
file name : Image_31082023155404274.png
|
2023-08-31 15:54:04.372064 |
159 |
67158637 |
CONST. OF CULTURAL CENTRE AT 10 GHARIYA |
137000 |
CONST. OF CULTURAL CENTRE AT 10 GHARIYA1 |
Plinth level |
-
latitude : 27.356538333333333
Longitude : 94.93290999999999
file name : Image_05072023190831393.png
|
2023-07-05 19:08:31.489303 |
160 |
67158637 |
CONST. OF CULTURAL CENTRE AT 10 GHARIYA |
137000 |
CONST. OF CULTURAL CENTRE AT 10 GHARIYA1 |
Completion of work |
-
latitude : 27.35657
Longitude : 94.93278833333333
file name : Image_02062023171834742.png
|
2023-06-02 17:18:34.83333 |
161 |
55780585 |
COVID 19 EXPENSES (10% OF UNTIED FUND ) |
148281 |
COVID 19 EXPENSES (10% OF UNTIED FUND )1 |
Roof laid |
-
latitude : 27.4740239
Longitude : 94.913821
file name : Image_04052024120645715.png
|
2024-05-04 12:06:46.513753 |
162 |
55780585 |
COVID 19 EXPENSES (10% OF UNTIED FUND ) |
148281 |
COVID 19 EXPENSES (10% OF UNTIED FUND )1 |
Plinth level |
-
latitude : 27.4740267
Longitude : 94.9138186
file name : Image_04052024115848739.png
|
2024-05-04 11:58:49.609394 |
163 |
55780585 |
COVID 19 EXPENSES (10% OF UNTIED FUND ) |
148281 |
COVID 19 EXPENSES (10% OF UNTIED FUND )1 |
Completion of work |
-
latitude : 27.31950083
Longitude : 94.87553611
file name : Image_29062022132746037.png
|
2022-06-29 13:27:46.145108 |
164 |
67193648 |
Purchase of Tricycles/other battery-operated vehicles for door to door collection of waste |
78300 |
Purchase of Tricycles/other battery-operated vehicles for door to door collection of waste1 |
Roof laid |
-
latitude : 27.485658333333337
Longitude : 94.90798500000001
file name : Image_04052024134419001.png
|
2024-05-04 13:44:19.183006 |
165 |
67193648 |
Purchase of Tricycles/other battery-operated vehicles for door to door collection of waste |
78300 |
Purchase of Tricycles/other battery-operated vehicles for door to door collection of waste1 |
Plinth level |
-
latitude : 27.4805408
Longitude : 94.901728
file name : Image_04052024134245331.png
|
2024-05-04 13:42:45.424202 |
166 |
67193648 |
Purchase of Tricycles/other battery-operated vehicles for door to door collection of waste |
78300 |
Purchase of Tricycles/other battery-operated vehicles for door to door collection of waste1 |
Completion of work |
-
latitude : 27.474091666666663
Longitude : 94.91335833333332
file name : Image_22122023205356618.png
|
2023-12-22 20:53:56.603136 |
167 |
66570686 |
INFRASTRUCTURE DEVELOPMENT AT MAHABIR L. P. SCHOOL |
166500 |
INFRASTRUCTURE DEVELOPMENT AT MAHABIR L. P. SCHOOL1 |
Roof laid |
-
latitude : 27.368395000000003
Longitude : 94.91389333333333
file name : Image_12012024145636111.png
|
2024-01-12 14:56:36.203285 |
168 |
66570686 |
INFRASTRUCTURE DEVELOPMENT AT MAHABIR L. P. SCHOOL |
166500 |
INFRASTRUCTURE DEVELOPMENT AT MAHABIR L. P. SCHOOL1 |
Plinth level |
-
latitude : 27.36839828
Longitude : 94.9142166
file name : Image_06032023175254031.png
|
2023-03-06 17:52:54.202918 |
169 |
66570686 |
INFRASTRUCTURE DEVELOPMENT AT MAHABIR L. P. SCHOOL |
166500 |
INFRASTRUCTURE DEVELOPMENT AT MAHABIR L. P. SCHOOL1 |
Completion of work |
-
latitude : 27.36831434
Longitude : 94.91394471
file name : Image_02022023171000285.png
|
2023-02-02 17:10:00.364308 |
170 |
65659141 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 27.286831666666664
Longitude : 94.81808166666666
file name : Image_26012024123116712.png
|
2024-01-26 12:31:16.801387 |
171 |
65659141 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 27.286681666666663
Longitude : 94.81838
file name : Image_30082023164327783.png
|
2023-08-30 16:43:27.877627 |
172 |
65659141 |
Construction of toilets in public institutions |
164500 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 27.28656058
Longitude : 94.81839067
file name : Image_06122022155649037.png
|
2022-12-06 15:56:49.143921 |