1 |
10923843 |
Const. of culvert at gabhroo pothar path |
50000 |
Culvert1 |
In Progress |
-
latitude : 26.74179403,26.74179416
Longitude : 94.47529714,94.47529825
file name : Image_18072019110048324.png
|
2019-07-18 11:00:48.374917 |
2 |
10923523 |
Const. of youth club at Lahing Moran |
150000 |
Cultural Stage1 |
25% |
-
latitude : 26.739097237586975
Longitude : 94.4520753622055
file name : Image_16072019135330026.png
|
2019-07-16 13:53:30.131786 |
3 |
10924113 |
Const. of culvert near Kalithan |
50000 |
Culvert1 |
In Progress |
-
latitude : 26.74016901,26.74016901
Longitude : 94.45766731,94.45766731
file name : Image_12072019115954182.png
|
2019-07-12 11:59:54.282776 |
4 |
10924269 |
Const. of ring well at gabroo bojar field |
50000 |
Well1 |
In Progress |
-
latitude : 26.74016901
Longitude : 94.45766731
file name : Image_12072019124507926.png
|
2019-07-12 12:45:08.02694 |
5 |
10924065 |
development of wodden of gabhroo munda line |
100000 |
Agricultural Land1 |
25% |
-
latitude : 26.74623461,26.74623461
Longitude : 94.45631551,94.45631551
file name : Image_16072019151841138.png
|
2019-07-16 15:18:41.205512 |
6 |
10924065 |
development of wodden of gabhroo munda line |
100000 |
Agricultural Land1 |
25% |
-
latitude : 26.74623461,26.74623461
Longitude : 94.45631551,94.45631551
file name : Image_16072019151823942.png
|
2019-07-16 15:18:24.019574 |
7 |
10923629 |
Const. of Ring well at Ghoria chuk |
50000 |
Well1 |
In Progress |
-
latitude : 26.739097237586975
Longitude : 94.4520753622055
file name : Image_16072019135956000.png
|
2019-07-16 13:59:56.086829 |
8 |
10924158 |
Const. at culvert at Hindu gaon |
50000 |
Culvert1 |
In Progress |
-
latitude : 26.792752146720886,26.792752146720886
Longitude : 94.47940170764923,94.47940170764923
file name : Image_18072019110044983.png
|
2019-07-18 11:00:45.050095 |
9 |
10924158 |
Const. at culvert at Hindu gaon |
50000 |
Culvert1 |
In Progress |
-
latitude : 26.792752146720886,26.792752146720886
Longitude : 94.47940170764923,94.47940170764923
file name : Image_18072019110041639.png
|
2019-07-18 11:00:41.707748 |
10 |
10924221 |
Const. of ring well at gabhoroo Pahar line |
50000 |
Well1 |
In Progress |
-
latitude : 26.74016901
Longitude : 94.45766731
file name : Image_12072019120005896.png
|
2019-07-12 12:00:06.008454 |
11 |
10923739 |
Const. of ring well at Gabhroo 7no. line |
50000 |
Well1 |
In Progress |
-
latitude : 26.74016901
Longitude : 94.45766731
file name : Image_12072019124251791.png
|
2019-07-12 12:42:51.891195 |
12 |
10924327 |
Development of gp Office |
52000 |
Panchayat Resource Centre1 |
25% |
-
latitude : 26.83987907
Longitude : 94.4685245
file name : Image_16072019111649794.png
|
2019-07-16 11:16:49.872443 |
13 |
10923651 |
Const. of Ring well at near Khogeswar talukdar path |
50000 |
Well1 |
In Progress |
-
latitude : 26.739097237586975
Longitude : 94.4520753622055
file name : Image_16072019135048550.png
|
2019-07-16 13:50:48.658104 |
14 |
10923322 |
Gravelling and Earthwork at Hemlai Bogi ali |
100000 |
Rural Road BT1 |
25% |
-
latitude : 26.75778613,26.75778613
Longitude : 94.45684944,94.45684944
file name : Image_16072019130429159.png
|
2019-07-16 13:04:29.234935 |
15 |
11081416 |
Const. of Ring well at 5 no. line |
50000 |
Well1 |
In Progress |
-
latitude : 26.74016901
Longitude : 94.45766731
file name : Image_12072019141834777.png
|
2019-07-12 14:18:34.822516 |
16 |
43714473 |
Const of mongla than at gabhroo 8 no line |
150000 |
Const of mongla than at gabhroo 8 no line1 |
25% |
-
latitude : 26.745777
Longitude : 94.47552781
file name : Image_01122020133402853.png
|
2020-12-01 13:34:02.954233 |
17 |
32618527 |
Const of Library of Gabhroo TE |
150000 |
Const of Library of Gabhroo TE1 |
25% |
-
latitude : 26.74124755
Longitude : 94.47692067
file name : Image_11112020112733820.png
|
2020-11-11 11:27:37.717757 |
18 |
43714846 |
Const of hemlai gp office urinal |
148438 |
Const of hemlai gp office urinal1 |
25% |
-
latitude : 26.7405585
Longitude : 94.4570769
file name : Image_27112020141510012.png
|
2020-11-27 14:15:10.092837 |
19 |
32618727 |
Const of khogeswar talukdar path with culverr ph II |
200000 |
Const of khogeswar talukdar path with culverr ph II1 |
Earth Work |
-
latitude : 26.75674499,26.75675249
Longitude : 94.43999514,94.43998218
file name : Image_13112020144901799.png
|
2020-11-13 14:49:06.665196 |
20 |
43713425 |
Const of bridge at gakhirkhua to lahing moran connecting road |
500000 |
Const of bridge at gakhirkhua to lahing moran connecting road 1 |
Substructure below GL |
-
latitude : 26.76219403
Longitude : 94.45302319
file name : Image_07122020174307303.png
|
2020-12-07 17:43:07.409033 |
21 |
43714599 |
Const of hemlai Bogi ali road |
150000 |
Const of hemlai Bogi ali road1 |
Earth Work |
-
latitude : 26.74830372,26.74830382
Longitude : 94.45651803,94.45651913
file name : Image_27112020151829112.png
|
2020-11-27 15:18:29.252502 |
22 |
32618677 |
Const of hemlai road to welfare road |
200000 |
Const of hemlai road to welfare road1 |
Earth Work |
-
latitude : 26.73888122,26.7388812,26.7388812,26.73888099
Longitude : 94.45592498,94.45592502,94.45592502,94.455944
file name : Image_13112020121741232.png
|
2020-11-13 12:17:46.045365 |
23 |
43684094 |
Dev of community hall at lahing moran notun namghar |
250000 |
Dev of community hall at lahing moran notun namghar1 |
25% |
-
latitude : 26.76170431
Longitude : 94.44733242
file name : Image_07122020174214802.png
|
2020-12-07 17:42:14.904328 |
24 |
43684710 |
Const of boundary wall at hemlai moran gaon rajohua pukhuri |
200000 |
Const of boundary wall at hemlai moran gaon rajohua pukhuri 1 |
In Progress |
-
latitude : 26.75839073
Longitude : 94.46891142
file name : Image_03122020122729504.png
|
2020-12-03 12:27:29.593878 |
25 |
43712798 |
Dev of lahing alichuk path |
200000 |
Dev of lahing alichuk path1 |
Earth Work |
-
latitude : 26.74020775,26.74020761
Longitude : 94.4375259,94.43752569
file name : Image_07122020123948928.png
|
2020-12-07 12:39:49.033942 |
26 |
43712937 |
Dev of lahing post office |
100000 |
Dev of lahing post office1 |
25% |
-
latitude : 26.7414343
Longitude : 94.4389696
file name : Image_07122020123957674.png
|
2020-12-07 12:39:57.783145 |
27 |
32618394 |
Const. Of Boundary wall at Hemlai Kamona Mandir |
77532 |
Const. Of Boundary wall at Hemlai Kamona Mandir1 |
In Progress |
-
latitude : 26.74565938
Longitude : 94.46239634
file name : Image_17112020143036577.png
|
2020-11-17 14:30:36.677589 |
28 |
32618418 |
Const of Boundary wall at Hemlai Moran Gaon primary school |
150000 |
Const of Boundary wall at Hemlai Moran Gaon primary school1 |
In Progress |
-
latitude : 26.75742052
Longitude : 94.46992158
file name : Image_13112020145008395.png
|
2020-11-13 14:50:13.264702 |
29 |
32731266 |
Const of pev block of hemlai T.E road |
300000 |
Const of pev block of hemlai T.E road1 |
Earth Work |
-
latitude : 26.7448113,26.74480051,26.74480065
Longitude : 94.46290217,94.46290206,94.46290199
file name : Image_11112020133130690.png
|
2020-11-11 13:31:34.66356 |
30 |
32618446 |
Hemlai Kali mandir road with culvert |
100000 |
Hemlai Kali mandir road with culvert1 |
Substructure below GL |
-
latitude : 26.74594344,26.7459432
Longitude : 94.46398537,94.46398489
file name : Image_09112020111323685.png
|
2020-11-09 11:13:26.62212 |
31 |
32618642 |
Const. Of pcc road from Dhodar ali to Gp office |
400000 |
Const. Of pcc road from Dhodar ali to Gp office1 |
Earth Work |
-
latitude : 26.7405327,26.7405327
Longitude : 94.4571166,94.4571166
file name : Image_09112020113153713.png
|
2020-11-09 11:31:56.664561 |
32 |
32618642 |
Const. Of pcc road from Dhodar ali to Gp office |
400000 |
Const. Of pcc road from Dhodar ali to Gp office1 |
Earth Work |
-
latitude : 26.7405327,26.7405327
Longitude : 94.4571166,94.4571166
file name : Image_09112020111652771.png
|
2020-11-09 11:16:55.715674 |
33 |
32618818 |
Dev of 2 no ward church |
100000 |
Dev of 2 no ward church1 |
25% |
-
latitude : 26.75205299
Longitude : 94.46944815
file name : Image_09112020110822269.png
|
2020-11-09 11:08:25.199222 |
34 |
32618269 |
Const. Of urinal at Puroni Lunpuria Namghar |
100000 |
Const. Of urinal at Puroni Lunpuria Namghar1 |
25% |
-
latitude : 26.763306
Longitude : 94.47600187
file name : Image_17112020143040637.png
|
2020-11-17 14:30:40.739206 |
35 |
32618564 |
Dev of Hemlai Masjid |
150000 |
Dev of Hemlai Masjid1 |
25% |
-
latitude : 26.74234434
Longitude : 94.45771123
file name : Image_11112020133123544.png
|
2020-11-11 13:31:27.500237 |
36 |
32618293 |
Const of urinal at 4 no ward Anganbadi center |
100000 |
Const of urinal at 4 no ward Anganbadi center1 |
25% |
-
latitude : 26.73861061
Longitude : 94.47166365
file name : Image_11112020114346867.png
|
2020-11-11 11:43:50.766004 |
37 |
32618238 |
Const. Of road from Lahdoigarh connecting path to Lahing Alichuk path |
200000 |
Const. Of road from Lahdoigarh connecting path to Lahing Alichuk path1 |
Earth Work |
-
latitude : 26.7413393,26.7413393
Longitude : 94.4389124,94.4389124
file name : Image_13112020144933946.png
|
2020-11-13 14:49:38.814639 |
38 |
32618200 |
Const. Of Lahing panbari gaon Sikojan road with culvert |
200000 |
Const. Of Lahing panbari gaon Sikojan road with culvert1 |
Earth Work |
-
latitude : 26.75046147,26.7504563
Longitude : 94.44080339,94.44080006
file name : Image_13112020144906110.png
|
2020-11-13 14:49:10.97697 |
39 |
32731287 |
Const of hemlai namghar community hall |
224422 |
Const of hemlai namghar community hall1 |
25% |
-
latitude : 26.74603865
Longitude : 94.45641882
file name : Image_13112020145000633.png
|
2020-11-13 14:50:05.500021 |
40 |
32731212 |
Const. Of Nagharia lahing mahila samrti ghor |
330000 |
Const. Of Nagharia lahing mahila samrti ghor1 |
25% |
-
latitude : 26.75746267
Longitude : 94.44609362
file name : Image_13112020130116453.png
|
2020-11-13 13:01:21.296981 |
41 |
32731235 |
Dev. Of hemlai kabarshthan road culvert ph II |
100000 |
Dev. Of hemlai kabarshthan road culvert ph II1 |
Substructure below GL |
-
latitude : 26.74841895,26.74841895
Longitude : 94.45639406,94.45639406
file name : Image_17112020143032889.png
|
2020-11-17 14:30:32.991148 |
42 |
32618835 |
Const of Boundary wall at hemlai moram gaom community hall |
150000 |
Const of Boundary wall at hemlai moram gaom community hall1 |
25% |
-
latitude : 26.75550143
Longitude : 94.47201461
file name : Image_13112020145004486.png
|
2020-11-13 14:50:09.366296 |
43 |
32618774 |
Const of lahing cremation Ground road |
134245 |
Const of lahing cremation Ground road1 |
25% |
-
latitude : 26.75038543,26.75038543
Longitude : 94.44072674,94.44072674
file name : Image_13112020144910869.png
|
2020-11-13 14:49:15.738694 |
44 |
32618659 |
Const of Lahing sati Sadhoni Boundary wall |
150000 |
Const of Lahing sati Sadhoni Boundary wall1 |
In Progress |
-
latitude : 26.74250788
Longitude : 94.44129849
file name : Image_13112020144952714.png
|
2020-11-13 14:49:57.579326 |
45 |
32618713 |
Dev of Gabhroo Paharline Anganbadi center to Gabhroo 24 no bagan |
200000 |
Dev of Gabhroo Paharline Anganbadi center to Gabhroo 24 no bagan1 |
25% |
-
latitude : 26.73859359
Longitude : 94.47209154
file name : Image_11112020113841076.png
|
2020-11-11 11:38:44.977577 |
46 |
32618761 |
Land dev at lahing moran Lp school |
100000 |
Land dev at lahing moran Lp school1 |
25% |
-
latitude : 26.76038275,26.76038424
Longitude : 94.44722527,94.44722467
file name : Image_13112020124240416.png
|
2020-11-13 12:42:45.242187 |
47 |
32618621 |
Dev of Kharonijan Namghar |
150000 |
Dev of Kharonijan Namghar1 |
25% |
-
latitude : 26.74083425
Longitude : 94.44666647
file name : Image_13112020123045884.png
|
2020-11-13 12:30:50.703459 |
48 |
32618800 |
Dev of Hemlai kabarsthan road with culvert |
100000 |
Dev of Hemlai kabarsthan road with culvert1 |
Earth Work |
-
latitude : 26.85488502,26.85488502
Longitude : 94.49350521,94.49350521
file name : Image_17112020143029046.png
|
2020-11-17 14:30:29.143153 |
49 |
32618162 |
Const of road at noisiporia gaon |
450000 |
Const of road at noisiporia gaon1 |
Earth Work |
-
latitude : 26.75012969,26.75012969,26.75013139
Longitude : 94.44413248,94.44413248,94.44412806
file name : Image_13112020123433059.png
|
2020-11-13 12:34:37.887005 |
50 |
32618324 |
Const. Of bridge at gabhroo Bogarajan ph II |
350000 |
Const. Of bridge at gabhroo Bogarajan ph II1 |
Substructure below GL |
-
latitude : 26.74091374
Longitude : 94.47718808
file name : Image_11112020112901883.png
|
2020-11-11 11:29:05.79042 |
51 |
31261341 |
Dev of noisipora namghar |
200000 |
Dev of noisipora namghar1 |
25% |
-
latitude : 26.75198284
Longitude : 94.44556451
file name : Image_13112020123656943.png
|
2020-11-13 12:37:01.770794 |
52 |
32608705 |
Dev. Of Hemlai gp office |
104826 |
Dev. Of Hemlai gp office1 |
25% |
-
latitude : 26.7405326
Longitude : 94.4571167
file name : Image_11112020133126902.png
|
2020-11-11 13:31:30.901139 |
53 |
31260383 |
Const of gakhirkhua lahing moran connecting road with RCC pool |
200000 |
Const of gakhirkhua lahing moran connecting road with RCC pool1 |
Substructure below GL |
-
latitude : 26.76454169,26.76453944,26.7645357
Longitude : 94.45130469,94.45130524,94.45129752
file name : Image_13112020124957072.png
|
2020-11-13 12:50:01.903382 |
54 |
31260730 |
Dev of cremation ground at lahing panbari gaon |
200000 |
Dev of cremation ground at lahing panbari gaon1 |
25% |
-
latitude : 26.75212333,26.75211506
Longitude : 94.43911113,94.4391145
file name : Image_13112020144915475.png
|
2020-11-13 14:49:20.335895 |
55 |
31260835 |
Const of boundary wall at 4no rajohua pukhuri |
150000 |
Const of boundary wall at 4no rajohua pukhuri 1 |
In Progress |
-
latitude : 26.73905915
Longitude : 94.47079823
file name : Image_11112020114114744.png
|
2020-11-11 11:41:18.667368 |
56 |
43683950 |
Const of 3nos of dustbin at gabhroo chariali |
200000 |
Const of 3nos of dustbin at gabhroo chariali1 |
25% |
-
latitude : 26.74408789
Longitude : 94.47781273
file name : Image_01122020133358762.png
|
2020-12-01 13:33:58.876254 |
57 |
43714331 |
Dev of community hall at GP office |
220000 |
Dev of community hall at GP office 1 |
25% |
-
latitude : 26.7405585
Longitude : 94.4570769
file name : Image_27112020113439399.png
|
2020-11-27 11:34:39.490219 |
58 |
43683532 |
Const of boundary wall at notun lunpuria namghar |
155488 |
Const of boundary wall at notun lunpuria namghar1 |
In Progress |
-
latitude : 26.75786824
Longitude : 94.47702828
file name : Image_03122020142622123.png
|
2020-12-03 14:26:22.217011 |
59 |
43683532 |
Const of boundary wall at notun lunpuria namghar |
155488 |
Const of boundary wall at notun lunpuria namghar1 |
In Progress |
-
latitude : 26.75786824
Longitude : 94.47702828
file name : Image_03122020142628873.png
|
2020-12-03 14:26:28.961414 |
60 |
43846420 |
Dev of komoldaya namghar |
150000 |
Dev of komoldaya namghar1 |
25% |
-
latitude : 26.75044282
Longitude : 94.45609476
file name : Image_27112020140012046.png
|
2020-11-27 14:00:12.14151 |
61 |
43846726 |
Dev of jnyan vikash school |
100000 |
Dev of jnyan vikash school 1 |
25% |
-
latitude : 26.74755361
Longitude : 94.46667185
file name : Image_27112020150942069.png
|
2020-11-27 15:09:42.149005 |
62 |
43846220 |
Dev of hemlai school playground |
125000 |
Dev of hemlai school playground1 |
25% |
-
latitude : 26.73908101
Longitude : 94.45589583
file name : Image_27112020140004596.png
|
2020-11-27 14:00:04.696502 |
63 |
43846305 |
Const of community hall at gabhroo playground |
249266 |
Const of community hall at gabhroo playground1 |
25% |
-
latitude : 26.7391453
Longitude : 94.47681599
file name : Image_03122020142612361.png
|
2020-12-03 14:26:12.452462 |
64 |
43846590 |
Dev of hemlai moran gaon jom bura path |
250000 |
Dev of hemlai moran gaon jom bura path1 |
Earth Work |
-
latitude : 26.75936946,26.75936946
Longitude : 94.46996527,94.46996527
file name : Image_01122020132811982.png
|
2020-12-01 13:28:12.08883 |
65 |
43847588 |
Const of bicycle stand lahing school |
200000 |
Const of bicycle stand lahing school1 |
25% |
-
latitude : 26.7414322
Longitude : 94.4389674
file name : Image_07122020124012171.png
|
2020-12-07 12:40:12.294109 |
66 |
43683796 |
Const of community hall at puroni lunpuria gaon |
200000 |
Const of community hall at puroni lunpuria gaon1 |
25% |
-
latitude : 26.76388537
Longitude : 94.47868654
file name : Image_03122020142634977.png
|
2020-12-03 14:26:35.073024 |
67 |
43683796 |
Const of community hall at puroni lunpuria gaon |
200000 |
Const of community hall at puroni lunpuria gaon1 |
25% |
-
latitude : 26.76388537
Longitude : 94.47868654
file name : Image_03122020142641882.png
|
2020-12-03 14:26:41.974922 |
68 |
43684281 |
Const of CC pravers block road at hemlai T.E ph II |
500000 |
Const of CC pravers block road at hemlai T.E ph II1 |
Earth Work |
-
latitude : 26.74529087,26.74529246
Longitude : 94.46261271,94.46261225
file name : Image_27112020151301743.png
|
2020-11-27 15:13:01.825683 |
69 |
43684597 |
Const of boundary wall at gabhroo mongola than |
200000 |
Const of boundary wall at gabhroo mongola than1 |
In Progress |
-
latitude : 26.73801929
Longitude : 94.47811156
file name : Image_03122020122748687.png
|
2020-12-03 12:27:48.778369 |
70 |
43713323 |
Const of komoldoya gaon road |
150000 |
Const of komoldoya gaon road1 |
Earth Work |
-
latitude : 26.75009078,26.75009969
Longitude : 94.45597164,94.45597142
file name : Image_27112020140019348.png
|
2020-11-27 14:00:19.442872 |
71 |
43713532 |
Dev of gakhirkhua namghar community hall |
200000 |
Dev of gakhirkhua namghar community hall1 |
25% |
-
latitude : 26.75755126
Longitude : 94.45636415
file name : Image_07122020174446668.png
|
2020-12-07 17:44:46.834708 |
72 |
43714142 |
Const of RCC pool at lahing noisiporia to panbari connecting road |
200000 |
Const of RCC pool at lahing noisiporia to panbari connecting road1 |
Substructure below GL |
-
latitude : 26.75212079,26.75211973
Longitude : 94.44145137,94.4414535
file name : Image_07122020174138262.png
|
2020-12-07 17:41:38.369898 |
73 |
43714244 |
Dev of gabhroo chariali binudan kendra |
225000 |
Dev of gabhroo chariali binudan kendra1 |
25% |
-
latitude : 26.74112661
Longitude : 94.47787891
file name : Image_01122020133912935.png
|
2020-12-01 13:39:13.028586 |
74 |
32618785 |
Const of road at new lunpuria gaon main road |
150000 |
Const of road at new lunpuria gaon main road1 |
Earth Work |
-
latitude : 26.75822699,26.75822475
Longitude : 94.47627891,94.47629337
file name : Image_09112020110324793.png
|
2020-11-09 11:03:27.714476 |
75 |
43846161 |
Earth filling at gabhroo playground |
125000 |
Earth filling at gabhroo playground1 |
25% |
-
latitude : 26.73915758
Longitude : 94.47659327
file name : Image_01122020132806907.png
|
2020-12-01 13:28:07.005098 |
76 |
43847018 |
Dev of satriya samaj namghar noisiporia |
150000 |
Dev of satriya samaj namghar noisiporia1 |
25% |
-
latitude : 26.75171628
Longitude : 94.44599067
file name : Image_07122020124017276.png
|
2020-12-07 12:40:17.40635 |
77 |
43847743 |
Dev. Of Sati Sadhani Bhawan |
200000 |
Dev. Of Sati Sadhani Bhawan 1 |
25% |
-
latitude : 26.7413714
Longitude : 94.4389947
file name : Image_13112020144947195.png
|
2020-11-13 14:49:52.063893 |
78 |
43845722 |
Dev of jnyan vikash school PH II |
100000 |
Dev of jnyan vikash school PH II1 |
25% |
-
latitude : 26.74780433
Longitude : 94.46691833
file name : Image_27112020150901276.png
|
2020-11-27 15:09:01.374778 |
79 |
43846019 |
Const of community hall at mura gaon |
250000 |
Const of community hall at mura gaon1 |
25% |
-
latitude : 26.74148871
Longitude : 94.45089081
file name : Image_07122020120545491.png
|
2020-12-07 12:05:45.585662 |
80 |
43845205 |
const of pravers block road at 3 no ward |
500000 |
const of pravers block road at 3 no ward1 |
Earth Work |
-
latitude : 26.74154391,26.7415407
Longitude : 94.47769692,94.47767155
file name : Image_01122020125513057.png
|
2020-12-01 12:55:13.16654 |
81 |
43845510 |
Dev of community hall at noisiporia gaon |
400000 |
Dev of community hall at noisiporia gaon1 |
25% |
-
latitude : 26.75223818
Longitude : 94.44566874
file name : Image_07122020124351827.png
|
2020-12-07 12:43:51.93248 |
82 |
43845626 |
Const of road at new line path bokulguri cc pravers |
450000 |
Const of road at new line path bokulguri cc pravers1 |
Earth Work |
-
latitude : 26.75157977,26.75157768
Longitude : 94.46976455,94.46976648
file name : Image_27112020150556370.png
|
2020-11-27 15:05:56.465156 |
83 |
43845029 |
Const of khogeswar talukdar path cc pravers |
900000 |
Const of khogeswar talukdar path cc pravers1 |
Earth Work |
-
latitude : 26.75661492,26.75661631
Longitude : 94.43994526,94.43994305
file name : Image_07122020174157604.png
|
2020-12-07 17:41:57.722417 |
84 |
43847345 |
Const of nepali basti gaon road |
150000 |
Const of nepali basti gaon road1 |
Earth Work |
-
latitude : 26.7643801,26.7643801
Longitude : 94.46381467,94.46381467
file name : Image_01122020133431549.png
|
2020-12-01 13:34:31.647332 |
85 |
43847908 |
Dev of hemlai masjid PH ii |
200000 |
Dev of hemlai masjid PH ii1 |
25% |
-
latitude : 26.74225676
Longitude : 94.45765361
file name : Image_27112020140200324.png
|
2020-11-27 14:02:00.408306 |
86 |
43847257 |
Const of community hall at nepali basti namghar |
150000 |
Const of community hall at nepali basti namghar1 |
25% |
-
latitude : 26.76433808
Longitude : 94.46392312
file name : Image_01122020133427537.png
|
2020-12-01 13:34:27.646135 |
87 |
43846894 |
Const of boundary wall at lahing sahid bedi |
150000 |
Const of boundary wall at lahing sahid bedi1 |
In Progress |
-
latitude : 26.7414442
Longitude : 94.4389811
file name : Image_07122020124004710.png
|
2020-12-07 12:40:04.822318 |
88 |
43845841 |
pucca dustbin at gp office |
52340 |
pucca dustbin at gp office1 |
25% |
-
latitude : 26.7405586
Longitude : 94.457077
file name : Image_27112020141506116.png
|
2020-11-27 14:15:06.201184 |
89 |
43846819 |
Const of Hume pipe pool at near dhodar ali bridge |
50000 |
Const of Hume pipe pool at near dhodar ali bridge1 |
Substructure below GL |
-
latitude : 26.73870902,26.73870902
Longitude : 94.45581891,94.45581891
file name : Image_27112020135956722.png
|
2020-11-27 13:59:56.819812 |
90 |
43847809 |
Dev of alichuk gaon namghar |
200000 |
Dev of alichuk gaon namghar1 |
25% |
-
latitude : 26.73653784
Longitude : 94.44011839
file name : Image_13112020144956975.png
|
2020-11-13 14:50:01.846084 |
91 |
49871773 |
Const of bridge at gakhirkhua to lahing moran connecting road PH II |
460000 |
Const of bridge at gakhirkhua to lahing moran connecting road PH II1 |
Plinth level |
-
latitude : 26.76228722
Longitude : 94.45292143
file name : Image_16102023145846801.png
|
2023-10-16 14:58:46.901897 |
92 |
49871773 |
Const of bridge at gakhirkhua to lahing moran connecting road PH II |
460000 |
Const of bridge at gakhirkhua to lahing moran connecting road PH II1 |
Completion of work |
-
latitude : 26.76220238
Longitude : 94.45312453
file name : Image_28032022132033990.png
|
2022-03-28 13:20:34.14234 |
93 |
65194421 |
Construction of Boundary Wall at Lahing Panbari Anchalik Namghar |
100000 |
Construction of Boundary Wall at Lahing Panbari Anchalik Namghar1 |
Plinth level |
-
latitude : 26.75058667
Longitude : 94.44188022
file name : Image_16102023151820997.png
|
2023-10-16 15:18:20.661367 |
94 |
65194421 |
Construction of Boundary Wall at Lahing Panbari Anchalik Namghar |
100000 |
Construction of Boundary Wall at Lahing Panbari Anchalik Namghar1 |
Completion of work |
-
latitude : 26.75049953
Longitude : 94.44183557
file name : Image_26122022135617022.png
|
2022-12-26 13:56:17.129574 |
95 |
65456446 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Plinth level |
-
latitude : 26.7405347
Longitude : 94.4570569
file name : Image_28062024143813049.png
|
2024-06-28 14:38:13.153862 |
96 |
65456446 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 26.74071646
Longitude : 94.45680409
file name : Image_23112022113301525.png
|
2022-11-23 11:33:01.673871 |
97 |
49871945 |
Const of Gabhroo 10 no ward anganbadi kendra boundary wall |
154775 |
Const of Gabhroo 10 no ward anganbadi kendra boundary wall1 |
Plinth level |
-
latitude : 26.73909935
Longitude : 94.47602141
file name : Image_08092023113226045.png
|
2023-09-08 11:32:26.159799 |
98 |
49871945 |
Const of Gabhroo 10 no ward anganbadi kendra boundary wall |
154775 |
Const of Gabhroo 10 no ward anganbadi kendra boundary wall1 |
Completion of work |
-
latitude : 26.73925127
Longitude : 94.47601078
file name : Image_25032022150443553.png
|
2022-03-25 15:04:43.643533 |
99 |
66625081 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 26.73811251
Longitude : 94.45556307
file name : Image_26072023152216433.png
|
2023-07-26 15:22:16.549419 |
100 |
66624431 |
Dev. of Atma Office in GP Campus |
100000 |
Dev. of Atma Office in GP Campus1 |
Plinth level |
-
latitude : 26.74064762
Longitude : 94.45714646
file name : Image_29112023144043034.png
|
2023-11-29 14:40:43.117345 |
101 |
66624431 |
Dev. of Atma Office in GP Campus |
100000 |
Dev. of Atma Office in GP Campus1 |
Completion of work |
-
latitude : 26.74055078
Longitude : 94.45723349
file name : Image_23082023121053379.png
|
2023-08-23 12:10:53.466497 |
102 |
65457113 |
Construction of Community Sanitary Complex |
150000 |
Construction of Community Sanitary Complex1 |
Plinth level |
-
latitude : 26.74157908
Longitude : 94.47703071
file name : Image_28082023144019691.png
|
2023-08-28 14:40:19.806303 |
103 |
65457113 |
Construction of Community Sanitary Complex |
150000 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 26.74159704
Longitude : 94.47697559
file name : Image_17112022130407740.png
|
2022-11-17 13:04:07.837127 |
104 |
49864170 |
Const of urinal at Gabhroo bagan staff club |
45000 |
Const of urinal at Gabhroo bagan staff club1 |
Plinth level |
-
latitude : 26.74160784
Longitude : 94.4770504
file name : Image_28082023144131682.png
|
2023-08-28 14:41:31.802133 |
105 |
49864170 |
Const of urinal at Gabhroo bagan staff club |
45000 |
Const of urinal at Gabhroo bagan staff club1 |
Completion of work |
-
latitude : 26.74149545
Longitude : 94.47725653
file name : Image_25032022145655071.png
|
2022-03-25 14:56:55.177484 |
106 |
66625198 |
Construction of toilets in public institutions |
94275 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 26.74338477
Longitude : 94.45455045
file name : Image_10032023144851101.png
|
2023-03-10 14:48:51.205772 |
107 |
65457923 |
Creation of a new source of drinking water |
103682 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 26.74052404
Longitude : 94.45693647
file name : Image_28082023121053020.png
|
2023-08-28 12:10:53.127227 |
108 |
65457923 |
Creation of a new source of drinking water |
103682 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 26.74056228
Longitude : 94.45700169
file name : Image_28082023115155310.png
|
2023-08-28 11:51:55.415586 |
109 |
65457923 |
Creation of a new source of drinking water |
103682 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 26.74046064
Longitude : 94.45694167
file name : Image_20022023133208942.png
|
2023-02-20 13:32:09.049834 |
110 |
66623750 |
Construction of community hall at puroni lunporia gaon ph ii |
170000 |
Construction of community hall at puroni lunporia gaon ph ii1 |
Plinth level |
-
latitude : 26.763844
Longitude : 94.47858794
file name : Image_29112023140016022.png
|
2023-11-29 14:00:16.135111 |
111 |
66623750 |
Construction of community hall at puroni lunporia gaon ph ii |
170000 |
Construction of community hall at puroni lunporia gaon ph ii1 |
Completion of work |
-
latitude : 26.7638314
Longitude : 94.47865888
file name : Image_04042023153245191.png
|
2023-04-04 15:32:45.298551 |
112 |
65457618 |
Construction of cc paver block in GP campus PH 2 |
100378 |
Construction of cc paver block in GP campus PH 21 |
Roof laid |
-
latitude : 26.74063304,26.7405683
Longitude : 94.45689159,94.45693948
file name : Image_28082023123929672.png
|
2023-08-28 12:39:29.780239 |
113 |
65457618 |
Construction of cc paver block in GP campus PH 2 |
100378 |
Construction of cc paver block in GP campus PH 21 |
Plinth level |
-
latitude : 26.74052871,26.74052979
Longitude : 94.45692721,94.45693665
file name : Image_28082023115300393.png
|
2023-08-28 11:53:00.500493 |
114 |
65457618 |
Construction of cc paver block in GP campus PH 2 |
100378 |
Construction of cc paver block in GP campus PH 21 |
Completion of work |
-
latitude : 26.74051513,26.74051511
Longitude : 94.45688073,94.45688056
file name : Image_30112022123751110.png
|
2022-11-30 12:37:51.216527 |
115 |
65457697 |
Buying of GP furniture |
70000 |
Buying of GP furniture 1 |
Roof laid |
-
latitude : 26.74056797
Longitude : 94.45684771
file name : Image_28082023124115861.png
|
2023-08-28 12:41:15.985917 |
116 |
65457697 |
Buying of GP furniture |
70000 |
Buying of GP furniture 1 |
Plinth level |
-
latitude : 26.74054496
Longitude : 94.45687819
file name : Image_28082023115430345.png
|
2023-08-28 11:54:30.459381 |
117 |
65457697 |
Buying of GP furniture |
70000 |
Buying of GP furniture 1 |
Completion of work |
-
latitude : 26.74047758
Longitude : 94.45692696
file name : Image_30112022123534464.png
|
2022-11-30 12:35:34.589997 |
118 |
52052756 |
SANITAIZATION AND MASK |
91225 |
SANITAIZATION AND MASK1 |
Roof laid |
-
latitude : 26.74056007
Longitude : 94.45687411
file name : Image_28082023124019913.png
|
2023-08-28 12:40:20.036657 |
119 |
52052756 |
SANITAIZATION AND MASK |
91225 |
SANITAIZATION AND MASK1 |
Plinth level |
-
latitude : 26.74052078
Longitude : 94.45691208
file name : Image_28082023115345428.png
|
2023-08-28 11:53:45.544115 |
120 |
52052756 |
SANITAIZATION AND MASK |
91225 |
SANITAIZATION AND MASK1 |
Completion of work |
-
latitude : 26.7404927
Longitude : 94.4568972
file name : Image_24032022125411695.png
|
2022-03-24 12:54:11.807404 |
121 |
49868216 |
Drinking water facility at GP office |
220000 |
Drinking water facility at GP office1 |
Roof laid |
-
latitude : 26.74061817
Longitude : 94.45678247
file name : Image_28082023123823892.png
|
2023-08-28 12:38:24.015538 |
122 |
49868216 |
Drinking water facility at GP office |
220000 |
Drinking water facility at GP office1 |
Plinth level |
-
latitude : 26.74061137
Longitude : 94.45679459
file name : Image_28082023115510387.png
|
2023-08-28 11:55:10.504401 |
123 |
49868216 |
Drinking water facility at GP office |
220000 |
Drinking water facility at GP office1 |
Completion of work |
-
latitude : 26.74056385
Longitude : 94.45677624
file name : Image_03082022144318826.png
|
2022-08-03 14:43:18.939139 |
124 |
66624096 |
Construction of Milon gaon Namghar |
100000 |
Construction of Milon gaon Namghar1 |
Plinth level |
-
latitude : 26.74653129
Longitude : 94.46843881
file name : Image_28082023144806404.png
|
2023-08-28 14:48:06.531378 |
125 |
66624096 |
Construction of Milon gaon Namghar |
100000 |
Construction of Milon gaon Namghar1 |
Completion of work |
-
latitude : 26.74648242
Longitude : 94.46838133
file name : Image_18032023150805134.png
|
2023-03-18 15:08:05.253507 |
126 |
66623905 |
Construction of Library of Gabhoro TE (PH ii) |
65000 |
Construction of Library of Gabhoro TE (PH ii)1 |
Plinth level |
-
latitude : 26.74144752
Longitude : 94.47703548
file name : Image_28082023144248174.png
|
2023-08-28 14:42:48.276016 |
127 |
66623905 |
Construction of Library of Gabhoro TE (PH ii) |
65000 |
Construction of Library of Gabhoro TE (PH ii)1 |
Completion of work |
-
latitude : 26.74133895
Longitude : 94.47693391
file name : Image_09032023153722602.png
|
2023-03-09 15:37:22.691795 |
128 |
65455571 |
CONSTRUCTION OF COMMUNITY HALL AT BAKULGURI PH ii |
170000 |
CONSTRUCTION OF COMMUNITY HALL AT BAKULGURI PH ii1 |
Plinth level |
-
latitude : 26.75443514
Longitude : 94.46947217
file name : Image_02092023123843251.png
|
2023-09-02 12:38:50.66512 |
129 |
65455571 |
CONSTRUCTION OF COMMUNITY HALL AT BAKULGURI PH ii |
170000 |
CONSTRUCTION OF COMMUNITY HALL AT BAKULGURI PH ii1 |
Completion of work |
-
latitude : 26.75436158
Longitude : 94.4694571
file name : Image_20022023140934624.png
|
2023-02-20 14:09:34.716408 |
130 |
49868633 |
Const of CMSC TOILET AT 7 NO WARD |
90000 |
Const of CMSC TOILET AT 7 NO WARD1 |
Plinth level |
-
latitude : 26.75916556
Longitude : 94.46677433
file name : Image_02092023130451630.png
|
2023-09-02 13:04:51.72829 |
131 |
49868633 |
Const of CMSC TOILET AT 7 NO WARD |
90000 |
Const of CMSC TOILET AT 7 NO WARD1 |
Completion of work |
-
latitude : 26.75914281
Longitude : 94.46674749
file name : Image_20052022132525591.png
|
2022-05-20 13:25:25.69252 |
132 |
65194117 |
Construction of boundarywall at Hemlai Moran gaon Rajohuwa Pukhuri (Phii) |
200000 |
Construction of boundarywall at Hemlai Moran gaon Rajohuwa Pukhuri (Phii)1 |
Plinth level |
-
latitude : 26.75866019
Longitude : 94.46887308
file name : Image_02092023130942250.png
|
2023-09-02 13:09:42.347815 |
133 |
65194117 |
Construction of boundarywall at Hemlai Moran gaon Rajohuwa Pukhuri (Phii) |
200000 |
Construction of boundarywall at Hemlai Moran gaon Rajohuwa Pukhuri (Phii)1 |
Plinth level |
-
latitude : 26.7586807
Longitude : 94.46883158
file name : Image_02092023131045787.png
|
2023-09-02 13:10:45.881816 |
134 |
65194117 |
Construction of boundarywall at Hemlai Moran gaon Rajohuwa Pukhuri (Phii) |
200000 |
Construction of boundarywall at Hemlai Moran gaon Rajohuwa Pukhuri (Phii)1 |
Completion of work |
-
latitude : 26.75873245
Longitude : 94.46914235
file name : Image_20022023141441486.png
|
2023-02-20 14:14:41.591569 |
135 |
49871515 |
Const of boundary wall at hindu gaon parthamik school |
206252 |
Const of boundary wall at hindu gaon parthamik school1 |
Plinth level |
-
latitude : 26.75667583
Longitude : 94.48251244
file name : Image_02092023132217430.png
|
2023-09-02 13:22:17.529253 |
136 |
49871515 |
Const of boundary wall at hindu gaon parthamik school |
206252 |
Const of boundary wall at hindu gaon parthamik school1 |
Completion of work |
-
latitude : 26.75653079
Longitude : 94.48251251
file name : Image_28032022133702483.png
|
2022-03-28 13:37:02.603733 |
137 |
65455916 |
Development of V. O office at Hemlai |
62000 |
Development of V. O office at Hemlai 1 |
Plinth level |
-
latitude : 26.7402683
Longitude : 94.45745788
file name : Image_02092023133345397.png
|
2023-09-02 13:33:45.500306 |
138 |
65455916 |
Development of V. O office at Hemlai |
62000 |
Development of V. O office at Hemlai 1 |
Completion of work |
-
latitude : 26.74043927
Longitude : 94.45730185
file name : Image_01022023125027291.png
|
2023-02-01 12:50:27.415464 |
139 |
66623839 |
Construction of one nos. culvert at hemlai PHE center road |
40000 |
Construction of one nos. culvert at hemlai PHE center road1 |
Plinth level |
-
latitude : 26.74037543,26.74038522
Longitude : 94.45768839,94.45768941
file name : Image_31082023130622095.png
|
2023-08-31 13:06:22.190875 |
140 |
66623839 |
Construction of one nos. culvert at hemlai PHE center road |
40000 |
Construction of one nos. culvert at hemlai PHE center road1 |
Completion of work |
-
latitude : 26.74039846,26.74039813
Longitude : 94.45775033,94.45775071
file name : Image_30032023130827137.png
|
2023-03-30 13:08:27.235411 |
141 |
65455856 |
CONSTRUCTION OF BOUNDARY WALL AT AT NATUN LUNPARIA LP SCHOOL |
100000 |
CONSTRUCTION OF BOUNDARY WALL AT AT NATUN LUNPARIA LP SCHOOL1 |
Plinth level |
-
latitude : 26.75666319
Longitude : 94.47453033
file name : Image_08092023112133993.png
|
2023-09-08 11:21:34.079551 |
142 |
65455856 |
CONSTRUCTION OF BOUNDARY WALL AT AT NATUN LUNPARIA LP SCHOOL |
100000 |
CONSTRUCTION OF BOUNDARY WALL AT AT NATUN LUNPARIA LP SCHOOL1 |
Completion of work |
-
latitude : 26.75663819
Longitude : 94.47443448
file name : Image_01022023132316256.png
|
2023-02-01 13:23:16.367156 |
143 |
49864644 |
Drinking water facility at 4 no ward paharline |
220000 |
Drinking water facility at 4 no ward paharline1 |
Plinth level |
-
latitude : 26.73867977
Longitude : 94.47164028
file name : Image_08092023112307894.png
|
2023-09-08 11:23:07.985875 |
144 |
49864644 |
Drinking water facility at 4 no ward paharline |
220000 |
Drinking water facility at 4 no ward paharline1 |
Completion of work |
-
latitude : 26.73860034
Longitude : 94.4716396
file name : Image_20052022113824890.png
|
2022-05-20 11:38:24.999894 |
145 |
65194320 |
Construction of Gram than at paharline 4 no. ward |
100000 |
Construction of Gram than at paharline 4 no. ward1 |
Plinth level |
-
latitude : 26.73908541
Longitude : 94.473573
file name : Image_08092023113020431.png
|
2023-09-08 11:30:20.542095 |
146 |
65194320 |
Construction of Gram than at paharline 4 no. ward |
100000 |
Construction of Gram than at paharline 4 no. ward1 |
Completion of work |
-
latitude : 26.73907803
Longitude : 94.47358878
file name : Image_23112022132131105.png
|
2022-11-23 13:21:31.202039 |
147 |
65456830 |
Creation of a new source of drinking water |
63000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 26.74443706
Longitude : 94.47362946
file name : Image_30092023153523839.png
|
2023-09-30 15:35:24.049167 |
148 |
65456830 |
Creation of a new source of drinking water |
63000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 26.74445079
Longitude : 94.47363229
file name : Image_17112022122519390.png
|
2022-11-17 12:25:19.498495 |
149 |
65456946 |
Creation of a new source of drinking water |
63000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 26.74038405
Longitude : 94.47784107
file name : Image_30092023155643880.png
|
2023-09-30 15:56:43.982199 |
150 |
65456946 |
Creation of a new source of drinking water |
63000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 26.74033375
Longitude : 94.47778446
file name : Image_17112022124532703.png
|
2022-11-17 12:45:32.827149 |
151 |
66624550 |
Construction of 1 nos. culvert at kali mondir road at 2 no. ward |
47350 |
Construction of 1 nos. culvert at kali mondir road at 2 no. ward1 |
Plinth level |
-
latitude : 26.74626735,26.74628488
Longitude : 94.46403208,94.46399386
file name : Image_14122023134059114.png
|
2023-12-14 13:40:59.214349 |
152 |
66624550 |
Construction of 1 nos. culvert at kali mondir road at 2 no. ward |
47350 |
Construction of 1 nos. culvert at kali mondir road at 2 no. ward1 |
Completion of work |
-
latitude : 26.74625601,26.74625334
Longitude : 94.46407109,94.46407398
file name : Image_11102023122544330.png
|
2023-10-11 12:25:45.210051 |
153 |
66624716 |
Adjustment plan |
525000 |
Adjustment plan1 |
Completion of work |
-
latitude : 26.7405885
Longitude : 94.4575652
file name : Image_09012024130134788.png
|
2024-01-09 13:01:34.903286 |
154 |
87754763 |
Const of Puroni Lunpuria Community Hall |
80000 |
Const of Puroni Lunpuria Community Hall1 |
Plinth level |
-
latitude : 26.76375165
Longitude : 94.47866582
file name : Image_25062024130207431.png
|
2024-06-25 13:02:07.533079 |
155 |
87754763 |
Const of Puroni Lunpuria Community Hall |
80000 |
Const of Puroni Lunpuria Community Hall1 |
Completion of work |
-
latitude : 26.76377912
Longitude : 94.47866168
file name : Image_20012024141428883.png
|
2024-01-20 14:14:29.045105 |
156 |
87754252 |
Development of Gabharoo 10 No Ward Anganwadi Centre |
50000 |
Development of Gabharoo 10 No Ward Anganwadi Centre1 |
Completion of work |
-
latitude : 26.74076868
Longitude : 94.47696515
file name : Image_03022024142901887.png
|
2024-02-03 14:29:01.974201 |
157 |
66625342 |
Creation of drainage channel for management of grey water |
85275 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 26.75573192
Longitude : 94.44568963
file name : Image_02022024152026734.png
|
2024-02-02 15:20:26.827683 |
158 |
66624183 |
Construction of Gram than at 10 No. ward munda line |
100000 |
Construction of Gram than at 10 No. ward munda line1 |
Completion of work |
-
latitude : 26.74027201
Longitude : 94.47601411
file name : Image_03022024143056339.png
|
2024-02-03 14:30:56.441522 |
159 |
87752150 |
Construction of Boundary wall at GP campus |
452550 |
Construction of Boundary wall at GP campus1 |
Completion of work |
-
latitude : 26.7405267
Longitude : 94.4573584
file name : Image_05022024164145143.png
|
2024-02-05 16:41:45.256004 |
160 |
87758975 |
Construction of Boundary wall at Nalbari Pukhuri |
100000 |
Construction of Boundary wall at Nalbari Pukhuri1 |
Completion of work |
-
latitude : 26.75501493
Longitude : 94.4666917
file name : Image_27062024134556780.png
|
2024-06-27 13:45:56.892446 |
161 |
65455793 |
Repairing of Lahing Panbari Mohila Somitee Griho |
80000 |
Repairing of Lahing Panbari Mohila Somitee Griho1 |
Plinth level |
-
latitude : 26.75478697
Longitude : 94.43876925
file name : Image_01122023130825021.png
|
2023-12-01 13:08:25.147765 |
162 |
65455793 |
Repairing of Lahing Panbari Mohila Somitee Griho |
80000 |
Repairing of Lahing Panbari Mohila Somitee Griho1 |
Completion of work |
-
latitude : 26.75478975
Longitude : 94.43876891
file name : Image_13122022144445473.png
|
2022-12-13 14:44:45.627565 |
163 |
65455675 |
Construction of boundary wall at Navabikash Vidyapith lahing |
100000 |
Construction of boundary wall at Navabikash Vidyapith lahing1 |
Plinth level |
-
latitude : 26.74291091
Longitude : 94.44069792
file name : Image_01122023125533962.png
|
2023-12-01 12:55:34.084877 |
164 |
65455675 |
Construction of boundary wall at Navabikash Vidyapith lahing |
100000 |
Construction of boundary wall at Navabikash Vidyapith lahing1 |
Completion of work |
-
latitude : 26.74277639
Longitude : 94.44076281
file name : Image_03012023120936967.png
|
2023-01-03 12:09:37.061392 |
165 |
49869315 |
Const of urinal at notun lahing namghar |
117252 |
Const of urinal at notun lahing namghar1 |
Plinth level |
-
latitude : 26.74552598
Longitude : 94.43862619
file name : Image_01122023130130711.png
|
2023-12-01 13:01:30.841915 |
166 |
49869315 |
Const of urinal at notun lahing namghar |
117252 |
Const of urinal at notun lahing namghar1 |
Completion of work |
-
latitude : 26.74546507
Longitude : 94.43860128
file name : Image_05082022113427100.png
|
2022-08-05 11:34:27.206423 |
167 |
49869613 |
Drinking water facility at 9 no ward lahing naghoria |
220000 |
Drinking water facility at 9 no ward lahing naghoria1 |
Plinth level |
-
latitude : 26.75707167
Longitude : 94.44688039
file name : Image_01122023131700256.png
|
2023-12-01 13:17:00.369573 |
168 |
49869613 |
Drinking water facility at 9 no ward lahing naghoria |
220000 |
Drinking water facility at 9 no ward lahing naghoria1 |
Completion of work |
-
latitude : 26.75696414
Longitude : 94.44688909
file name : Image_05082022121758597.png
|
2022-08-05 12:17:58.699113 |
169 |
66624267 |
Construction of boundary wall at Lahing anganbadi Kendra to Lahing LP School |
200000 |
Construction of boundary wall at Lahing anganbadi Kendra to Lahing LP School1 |
Plinth level |
-
latitude : 26.7490159
Longitude : 94.44550702
file name : Image_01122023132402265.png
|
2023-12-01 13:24:02.366619 |
170 |
66624267 |
Construction of boundary wall at Lahing anganbadi Kendra to Lahing LP School |
200000 |
Construction of boundary wall at Lahing anganbadi Kendra to Lahing LP School1 |
Completion of work |
-
latitude : 26.74899383
Longitude : 94.44558015
file name : Image_09032023133633068.png
|
2023-03-09 13:36:33.172617 |
171 |
66624007 |
Construction of Lahing Adorkha Prathomic Namghar |
138000 |
Construction of Lahing Adorkha Prathomic Namghar1 |
Plinth level |
-
latitude : 26.74960745
Longitude : 94.44528782
file name : Image_01122023132228982.png
|
2023-12-01 13:22:29.090032 |
172 |
66624007 |
Construction of Lahing Adorkha Prathomic Namghar |
138000 |
Construction of Lahing Adorkha Prathomic Namghar1 |
Completion of work |
-
latitude : 26.74970278
Longitude : 94.44520632
file name : Image_10032023171130532.png
|
2023-03-10 17:11:30.668999 |
173 |
66625393 |
Construction of toilets in public institutions |
100000 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 26.74082867
Longitude : 94.44799383
file name : Image_01122023133438489.png
|
2023-12-01 13:34:38.587772 |
174 |
66625393 |
Construction of toilets in public institutions |
100000 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 26.74077549
Longitude : 94.44799275
file name : Image_23032023125345847.png
|
2023-03-23 12:53:45.940793 |
175 |
66625129 |
Construction of toilets in public institutions |
200000 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 26.76158115
Longitude : 94.44995028
file name : Image_14122023141611386.png
|
2023-12-14 14:16:11.485022 |
176 |
66625129 |
Construction of toilets in public institutions |
200000 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 26.76160883
Longitude : 94.45001747
file name : Image_09032023140301528.png
|
2023-03-09 14:03:01.621169 |
177 |
87756917 |
Creation of plastic waste storage unit |
218550 |
Creation of plastic waste storage unit 1 |
Plinth level |
-
latitude : 26.73898644
Longitude : 94.47774325
file name : Image_15122023165315827.png
|
2023-12-15 16:53:15.94614 |
178 |
87756917 |
Creation of plastic waste storage unit |
218550 |
Creation of plastic waste storage unit 1 |
Completion of work |
-
latitude : 26.73901899
Longitude : 94.47777827
file name : Image_16102023160000099.png
|
2023-10-16 16:00:00.756847 |
179 |
66624357 |
Construction of one Nos. Culvert at Hemlai bagan road |
40000 |
Construction of one Nos. Culvert at Hemlai bagan road1 |
Plinth level |
-
latitude : 26.74821048,26.74822016
Longitude : 94.4613426,94.46134103
file name : Image_31052024134339017.png
|
2024-05-31 13:43:39.106519 |
180 |
66624357 |
Construction of one Nos. Culvert at Hemlai bagan road |
40000 |
Construction of one Nos. Culvert at Hemlai bagan road1 |
Completion of work |
-
latitude : 26.7481169,26.74811319
Longitude : 94.46135733,94.46135523
file name : Image_22082023121556955.png
|
2023-08-22 12:15:57.053594 |
181 |
66625299 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 26.76107628
Longitude : 94.4490662
file name : Image_06042023150334273.png
|
2023-04-06 15:03:34.376415 |
182 |
66625247 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 26.73981594
Longitude : 94.47555439
file name : Image_26072023143929500.png
|
2023-07-26 14:39:29.616105 |
183 |
87752288 |
Construction of Cremation ground at 9no. ward |
52550 |
Construction of Cremation ground at 9no. ward1 |
Completion of work |
-
latitude : 26.75161234
Longitude : 94.43925385
file name : Image_02022024150811803.png
|
2024-02-02 15:08:11.897984 |
184 |
87754394 |
Development of Gabharoo Pahar Line Anganwadi Centre |
50000 |
Development of Gabharoo Pahar Line Anganwadi Centre1 |
Completion of work |
-
latitude : 26.73877354
Longitude : 94.47168033
file name : Image_03022024143415421.png
|
2024-02-03 14:34:15.531046 |
185 |
87757920 |
Creation of deep burial pits for safe disposal of menstrual waste |
80000 |
Creation of deep burial pits for safe disposal of menstrual waste1 |
Completion of work |
-
latitude : 26.74389254
Longitude : 94.47486684
file name : Image_05012024124058353.png
|
2024-01-05 12:40:58.445671 |
186 |
65456272 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Plinth level |
-
latitude : 26.7414018
Longitude : 94.4390227
file name : Image_20062024123650913.png
|
2024-06-20 12:36:51.025403 |
187 |
65456272 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 26.74156534
Longitude : 94.4392022
file name : Image_26122022141002440.png
|
2022-12-26 14:10:02.552931 |