1 |
44391914 |
IMPROVEMENT OF WARD 1 TO WARD 2 CONNECTING ROAD |
200000 |
IMPROVEMENT OF WARD 1 TO WARD 2 CONNECTING ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174631535.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174631535.png)
latitude : 27.44678644,27.44678644
Longitude : 95.25718896,95.25718896
file name : Image_19122020174631535.png
|
2020-12-19 17:46:31.643176 |
2 |
44391925 |
IMPROVEMENT OF PUB UJANI CHUK TO CHENI CHUK ROAD |
200000 |
IMPROVEMENT OF PUB UJANI CHUK TO CHENI CHUK ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174628022.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174628022.png)
latitude : 27.44634142,27.44634163
Longitude : 95.25935705,95.25935361
file name : Image_19122020174628022.png
|
2020-12-19 17:46:28.128682 |
3 |
44391962 |
IMPROVEMENT OF ROAD FROM KHATACHUK FIELD TO BAGHMORA CHUK |
200000 |
IMPROVEMENT OF ROAD FROM KHATACHUK FIELD TO BAGHMORA CHUK1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174647847.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174647847.png)
latitude : 27.44984696,27.44984557,27.44983881
Longitude : 95.24102276,95.24103069,95.24103019
file name : Image_19122020174647847.png
|
2020-12-19 17:46:47.966759 |
4 |
44391829 |
CONSTRUCTION OF MODHYA BALIJAN AAI COMMUNITY CENTRE |
200000 |
CONSTRUCTION OF MODHYA BALIJAN AAI COMMUNITY CENTRE1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174654275.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174654275.png)
latitude : 27.45425891
Longitude : 95.23278651
file name : Image_19122020174654275.png
|
2020-12-19 17:46:54.376221 |
5 |
44391806 |
IMPROVEMENT OF PAKABAM TO DUBI GAON ROAD |
189712 |
IMPROVEMENT OF PAKABAM TO DUBI GAON ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174723880.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174723880.png)
latitude : 27.46014808,27.46014861
Longitude : 95.25328861,95.25329616
file name : Image_19122020174723880.png
|
2020-12-19 17:47:23.98831 |
6 |
44391767 |
IMPROVEMENT OF BHATICHUK TO NAMGHAR ROAD |
200000 |
IMPROVEMENT OF BHATICHUK TO NAMGHAR ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174727803.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174727803.png)
latitude : 27.45242457,27.4506256
Longitude : 95.2545331,95.2532637
file name : Image_19122020174727803.png
|
2020-12-19 17:47:27.910466 |
7 |
44391767 |
IMPROVEMENT OF BHATICHUK TO NAMGHAR ROAD |
200000 |
IMPROVEMENT OF BHATICHUK TO NAMGHAR ROAD1 |
50% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153615381.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153615381.png)
latitude : 27.45243315,27.45243516,27.45243516,27.45246094
Longitude : 95.25452324,95.25452474,95.25452474,95.25451213
file name : Image_14112020153615381.png
|
2020-11-14 15:36:20.717508 |
8 |
44410278 |
CONSTRUCTION OF COMMUNITY HALL AT PUBERUN SANGHA |
450000 |
CONSTRUCTION OF COMMUNITY HALL AT PUBERUN SANGHA1 |
50% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174610667.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174610667.png)
latitude : 27.45018233
Longitude : 95.25389655
file name : Image_19122020174610667.png
|
2020-12-19 17:46:10.765272 |
9 |
44391819 |
IMPROVEMENT OF BALIJAN SAMSAN ROAD |
300000 |
IMPROVEMENT OF BALIJAN SAMSAN ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153553650.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153553650.png)
latitude : 27.45835336,27.45835617,27.45835315
Longitude : 95.23416567,95.2341829,95.23418981
file name : Image_14112020153553650.png
|
2020-11-14 15:35:58.994295 |
10 |
44391797 |
IMPROVEMENT OF BISACHUK TO UJANI CHUK ROAD |
200000 |
IMPROVEMENT OF BISACHUK TO UJANI CHUK ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174614289.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174614289.png)
latitude : 27.44900318,27.44900785
Longitude : 95.2694018,95.26940258
file name : Image_19122020174614289.png
|
2020-12-19 17:46:14.392426 |
11 |
44391797 |
IMPROVEMENT OF BISACHUK TO UJANI CHUK ROAD |
200000 |
IMPROVEMENT OF BISACHUK TO UJANI CHUK ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153523661.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153523661.png)
latitude : 27.44900292,27.44897191,27.44896854
Longitude : 95.26940486,95.26936628,95.26936324
file name : Image_14112020153523661.png
|
2020-11-14 15:35:28.998888 |
12 |
44410315 |
CONSTRUCTION OF CULTURAL CENTRE NEAR PAKABAM PANIMUDI |
200000 |
CONSTRUCTION OF CULTURAL CENTRE NEAR PAKABAM PANIMUDI1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174717377.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174717377.png)
latitude : 27.45942161
Longitude : 95.25540176
file name : Image_19122020174717377.png
|
2020-12-19 17:47:17.477271 |
13 |
44410351 |
IMPROVEMENT OF BALIJAN NAHORANI JANAKALYAN TO BORUAH CHUK ROAD |
200000 |
IMPROVEMENT OF BALIJAN NAHORANI JANAKALYAN TO BORUAH CHUK ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174700883.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174700883.png)
latitude : 27.46106914,27.46106719,27.46103864
Longitude : 95.23502146,95.23501822,95.235012
file name : Image_19122020174700883.png
|
2020-12-19 17:47:00.983625 |
14 |
44410354 |
CONSTRUCTION OF BARUAHOLA CHUK KALA KRISHTRI KENDRA |
150000 |
CONSTRUCTION OF BARUAHOLA CHUK KALA KRISHTRI KENDRA1 |
50% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174634841.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174634841.png)
latitude : 27.4455015
Longitude : 95.2532637
file name : Image_19122020174634841.png
|
2020-12-19 17:46:34.944289 |
15 |
44410387 |
IMPROVEMENT OF BHATICHUK GU-BAAT |
100000 |
IMPROVEMENT OF BHATICHUK GU-BAAT1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174731153.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174731153.png)
latitude : 27.45164561,27.45165178
Longitude : 95.25296869,95.25296343
file name : Image_19122020174731153.png
|
2020-12-19 17:47:31.250448 |
16 |
44410329 |
IMPROVEMENT OF BARUAHOLA CHUK TO KHATACHUK ROAD |
162655 |
IMPROVEMENT OF BARUAHOLA CHUK TO KHATACHUK ROAD1 |
25% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174641278.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174641278.png)
latitude : 27.45005386,27.45003156
Longitude : 95.24778839,95.24781965
file name : Image_19122020174641278.png
|
2020-12-19 17:46:41.391945 |
17 |
44410404 |
IMPROVEMENT OF BETIANI SAMSAN ROAD |
100000 |
IMPROVEMENT OF BETIANI SAMSAN ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174707505.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174707505.png)
latitude : 27.47150937,27.47152174
Longitude : 95.24144912,95.2414372
file name : Image_19122020174707505.png
|
2020-12-19 17:47:07.615989 |
18 |
44410404 |
IMPROVEMENT OF BETIANI SAMSAN ROAD |
100000 |
IMPROVEMENT OF BETIANI SAMSAN ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153603245.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153603245.png)
latitude : 27.47148513,27.47148565
Longitude : 95.24142973,95.24143064
file name : Image_14112020153603245.png
|
2020-11-14 15:36:08.584924 |
19 |
44410361 |
IMPROVEMENT OF ROAD FROM PUB UJANI ROAD TO UJANICHUK |
200000 |
IMPROVEMENT OF ROAD FROM PUB UJANI ROAD TO UJANICHUK1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174620927.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174620927.png)
latitude : 27.4477914,27.44779249
Longitude : 95.26432208,95.2643235
file name : Image_19122020174620927.png
|
2020-12-19 17:46:21.034448 |
20 |
44410392 |
IMPROVEMENT OF BEJICHUK TO DIHINGIA CHUK ROAD |
277609 |
IMPROVEMENT OF BEJICHUK TO DIHINGIA CHUK ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174651089.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174651089.png)
latitude : 27.45413816,27.45413749,27.45415659
Longitude : 95.23796643,95.2379665,95.23796548
file name : Image_19122020174651089.png
|
2020-12-19 17:46:51.188879 |
21 |
44410399 |
CONSTRUCTION OF DUBI GAON MANDIR |
150000 |
CONSTRUCTION OF DUBI GAON MANDIR1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174720610.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174720610.png)
latitude : 27.46076733
Longitude : 95.26020498
file name : Image_19122020174720610.png
|
2020-12-19 17:47:20.719364 |
22 |
44414466 |
CONSTRUCTION OF WAITING SHED AT BARUAHOLA SAMSHAN GHAT |
300000 |
CONSTRUCTION OF WAITING SHED AT BARUAHOLA SAMSHAN GHAT1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174607209.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174607209.png)
latitude : 27.44837332
Longitude : 95.25405321
file name : Image_19122020174607209.png
|
2020-12-19 17:46:07.335961 |
23 |
44414798 |
CONSTRUCTION OF BISA CHUK CHUBURI GHAR |
200000 |
CONSTRUCTION OF BISA CHUK CHUBURI GHAR1 |
25% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174624804.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174624804.png)
latitude : 27.44737597
Longitude : 95.25946972
file name : Image_19122020174624804.png
|
2020-12-19 17:46:24.897562 |
24 |
44414419 |
IMPROVEMENT OF KHATACHUK FIELD TO DHARIAPATHIA ROAD |
300000 |
IMPROVEMENT OF KHATACHUK FIELD TO DHARIAPATHIA ROAD1 |
25% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174644560.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174644560.png)
latitude : 27.44992502,27.44991872,27.44989481
Longitude : 95.24484658,95.24483931,95.24483234
file name : Image_19122020174644560.png
|
2020-12-19 17:46:44.664432 |
25 |
44414367 |
IMPROVEMENT OF URANG PATTY ROAD |
250000 |
IMPROVEMENT OF URANG PATTY ROAD1 |
25% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174657603.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174657603.png)
latitude : 27.45439859,27.45440146
Longitude : 95.22571166,95.22572261
file name : Image_19122020174657603.png
|
2020-12-19 17:46:57.698741 |
26 |
44414339 |
REPAIRING OF GANDHIA NAHORANI BARUAH CHUCK ROAD |
200000 |
REPAIRING OF GANDHIA NAHORANI BARUAH CHUCK ROAD1 |
25% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174704259.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174704259.png)
latitude : 27.46398449,27.46397526
Longitude : 95.23825534,95.23822487
file name : Image_19122020174704259.png
|
2020-12-19 17:47:04.371305 |
27 |
44414297 |
CONSTRUCTION OF CULTURAL CENTRE AT DHARIA GAON |
200000 |
CONSTRUCTION OF CULTURAL CENTRE AT DHARIA GAON1 |
50% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174617570.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_19122020174617570.png)
latitude : 27.44897905
Longitude : 95.27013107
file name : Image_19122020174617570.png
|
2020-12-19 17:46:17.662412 |
28 |
44414173 |
REPAIRING OF JALPANIA LPS ROAD |
200000 |
REPAIRING OF JALPANIA LPS ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_14112020153608550.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_14112020153608550.png)
latitude : 27.47028588,27.47028588,27.47027388
Longitude : 95.23608339,95.23608339,95.23605281
file name : Image_14112020153608550.png
|
2020-11-14 15:36:13.877373 |
29 |
44391844 |
CONSTRUCTION OF BORCHAPORI GUWALA PUJA MANDAP |
144367 |
CONSTRUCTION OF BORCHAPORI GUWALA PUJA MANDAP1 |
50% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174710683.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174710683.png)
latitude : 27.4813606
Longitude : 95.24460123
file name : Image_19122020174710683.png
|
2020-12-19 17:47:10.784634 |
30 |
44392044 |
EXTENSION OF BARUAHOLA ANNAKHYA MARKET SHED (PERFORMANCE) |
667650 |
EXTENSION OF BARUAHOLA ANNAKHYA MARKET SHED (PERFORMANCE)1 |
50% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153517617.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153517617.png)
latitude : 27.44924202
Longitude : 95.2533369
file name : Image_14112020153517617.png
|
2020-11-14 15:35:22.965892 |
31 |
44391971 |
IMPROVEMENT OF BALIJAN TINGIRI CHUCK ROAD |
150000 |
IMPROVEMENT OF BALIJAN TINGIRI CHUCK ROAD1 |
25% |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174638075.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_19122020174638075.png)
latitude : 27.4503483,27.4503483
Longitude : 95.24862906,95.24862906
file name : Image_19122020174638075.png
|
2020-12-19 17:46:38.183105 |
32 |
44410369 |
IMPROVEMENT OF BAMCHUMONI COLONY ROAD |
150000 |
IMPROVEMENT OF BAMCHUMONI COLONY ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153541555.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153541555.png)
latitude : 27.45961913,27.4596236
Longitude : 95.22478436,95.22478651
file name : Image_14112020153541555.png
|
2020-11-14 15:35:46.883805 |
33 |
44410369 |
IMPROVEMENT OF BAMCHUMONI COLONY ROAD |
150000 |
IMPROVEMENT OF BAMCHUMONI COLONY ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153547742.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153547742.png)
latitude : 27.45961913,27.4596236
Longitude : 95.22478436,95.22478651
file name : Image_14112020153547742.png
|
2020-11-14 15:35:53.070448 |
34 |
44410294 |
IMPROVEMENT OF GANDHIA KUHIARBARI ROAD |
200000 |
IMPROVEMENT OF GANDHIA KUHIARBARI ROAD1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174714087.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_19122020174714087.png)
latitude : 27.47380788,27.47380814,27.47381468
Longitude : 95.22684103,95.22684146,95.2268375
file name : Image_19122020174714087.png
|
2020-12-19 17:47:14.19517 |
35 |
44414205 |
CONSTRUCTION OF BETIANI SAMSHAN GHAT WAITING SHED |
200000 |
CONSTRUCTION OF BETIANI SAMSHAN GHAT WAITING SHED1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_14112020153558422.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2019/Image_14112020153558422.png)
latitude : 27.47067473
Longitude : 95.23965164
file name : Image_14112020153558422.png
|
2020-11-14 15:36:03.766488 |
36 |
44391904 |
CONSTRUCTION OF PUCCA DRAIN AT PANITOLA RAILWAY COLONY |
200000 |
CONSTRUCTION OF PUCCA DRAIN AT PANITOLA RAILWAY COLONY1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153623125.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2017/Image_14112020153623125.png)
latitude : 27.49360571,27.4936074
Longitude : 95.25398753,95.25398943
file name : Image_14112020153623125.png
|
2020-11-14 15:36:28.450181 |
37 |
44410373 |
IMPROVEMENT OF ROAD FROM DHARIA LPS TO DHARIA ROITAK |
250000 |
IMPROVEMENT OF ROAD FROM DHARIA LPS TO DHARIA ROITAK1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153529573.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153529573.png)
latitude : 27.44941752,27.44941695,27.44945046
Longitude : 95.27295596,95.27295726,95.27293269
file name : Image_14112020153529573.png
|
2020-11-14 15:35:34.927637 |
38 |
44410373 |
IMPROVEMENT OF ROAD FROM DHARIA LPS TO DHARIA ROITAK |
250000 |
IMPROVEMENT OF ROAD FROM DHARIA LPS TO DHARIA ROITAK1 |
Completed |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153535733.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2018/Image_14112020153535733.png)
latitude : 27.44941752,27.44941695,27.44945046
Longitude : 95.27295596,95.27295726,95.27293269
file name : Image_14112020153535733.png
|
2020-11-14 15:35:41.063586 |
39 |
51025196 |
CONSTRUCTION OF SANITARY LATRINE AT MADHYA BALIJAN LP SCHOOL |
45000 |
CONSTRUCTION OF SANITARY LATRINE AT MADHYA BALIJAN LP SCHOOL1 |
Roof laid |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_30082022124615849.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_30082022124615849.png)
latitude : 27.45503965
Longitude : 95.23255594
file name : Image_30082022124615849.png
|
2022-08-30 12:46:15.978552 |
40 |
51025196 |
CONSTRUCTION OF SANITARY LATRINE AT MADHYA BALIJAN LP SCHOOL |
45000 |
CONSTRUCTION OF SANITARY LATRINE AT MADHYA BALIJAN LP SCHOOL1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04042022160124563.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04042022160124563.png)
latitude : 27.45515001
Longitude : 95.23250804
file name : Image_04042022160124563.png
|
2022-04-04 16:01:24.68428 |
41 |
51025092 |
CONSTRUCTION OF SANITARY LATRINE AT BARUAHOLA LP SCHOOL |
45000 |
CONSTRUCTION OF SANITARY LATRINE AT BARUAHOLA LP SCHOOL 1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_05042022020258603.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_05042022020258603.png)
latitude : 27.45187409
Longitude : 95.24783118
file name : Image_05042022020258603.png
|
2022-04-05 02:02:58.732149 |
42 |
51026035 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK |
510000 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_28122023224341119.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_28122023224341119.png)
latitude : 27.460935000000003,27.460951666666666
Longitude : 95.253055,95.25312833333334
file name : Image_28122023224341119.png
|
2023-12-28 22:43:41.201468 |
43 |
51026035 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK |
510000 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_28122023224337315.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_28122023224337315.png)
latitude : 27.460986666666667,27.46099
Longitude : 95.25251833333331,95.25258833333334
file name : Image_28122023224337315.png
|
2023-12-28 22:43:37.406377 |
44 |
51026035 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK |
510000 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_01122023130104207.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_01122023130104207.png)
latitude : 27.461478333333336,27.46148333333333
Longitude : 95.25213166666666,95.25214666666668
file name : Image_01122023130104207.png
|
2023-12-01 13:01:04.355278 |
45 |
51026035 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK |
510000 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_01122023130047731.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_01122023130047731.png)
latitude : 27.461508333333335,27.461501666666663
Longitude : 95.25213166666666,95.25213833333333
file name : Image_01122023130047731.png
|
2023-12-01 13:00:47.88734 |
46 |
51026035 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK |
510000 |
CONSTRUCTION OF POKABAM PURANI NAMGHAR ROAD WITH PAVER BLOCK1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_05042022020302480.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_05042022020302480.png)
latitude : 27.46089593,27.46090522,27.46092125
Longitude : 95.25313497,95.25300134,95.25268777
file name : Image_05042022020302480.png
|
2022-04-05 02:03:02.567603 |
47 |
66110647 |
Supply of Material and Equipment for Volleyball Filed at Gondhoiguri ME School and Baruahola High Sc |
40000 |
Supply of Material and Equipment for Volleyball Filed at Gondhoiguri ME School and Baruahola High Sc1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_29112023150734121.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_29112023150734121.png)
latitude : 27.44948,27.449484999999996
Longitude : 95.25156999999999,95.25155666666666
file name : Image_29112023150734121.png
|
2023-11-29 15:07:34.209749 |
48 |
66110647 |
Supply of Material and Equipment for Volleyball Filed at Gondhoiguri ME School and Baruahola High Sc |
40000 |
Supply of Material and Equipment for Volleyball Filed at Gondhoiguri ME School and Baruahola High Sc1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_29112023150727642.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_29112023150727642.png)
latitude : 27.449505,27.449503333333336,27.449486666666665
Longitude : 95.25156,95.25155833333335,95.25155666666666
file name : Image_29112023150727642.png
|
2023-11-29 15:07:27.744313 |
49 |
51025274 |
CONSTRUCTION OF SANITARY LATRINE AT HABICHUK NAHARANI LP SCHOOL |
45000 |
CONSTRUCTION OF SANITARY LATRINE AT HABICHUK NAHARANI LP SCHOOL1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_07062022152348130.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_07062022152348130.png)
latitude : 27.48151192
Longitude : 95.22529786
file name : Image_07062022152348130.png
|
2022-06-07 15:23:48.237965 |
50 |
66103206 |
RENOVATION OF GP OFFICE COMPOUND 2020-21_2nd |
208000 |
RENOVATION OF GP OFFICE COMPOUND 2020-21_2nd1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04072023122817831.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04072023122817831.png)
latitude : 27.44893276
Longitude : 95.24487279
file name : Image_04072023122817831.png
|
2023-07-04 12:28:17.930215 |
51 |
87174766 |
Construction of toilets in public institutions |
117325 |
Construction of toilets in public institutions1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_24012024134453211.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_24012024134453211.png)
latitude : 27.461206666666666
Longitude : 95.237355
file name : Image_24012024134453211.png
|
2024-01-24 13:44:53.316009 |
52 |
87174766 |
Construction of toilets in public institutions |
117325 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_02012024142017745.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_02012024142017745.png)
latitude : 27.461203333333334
Longitude : 95.23733333333332
file name : Image_02012024142017745.png
|
2024-01-02 14:20:17.836538 |
53 |
87174766 |
Construction of toilets in public institutions |
117325 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_02012024142014381.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_02012024142014381.png)
latitude : 27.461178333333336
Longitude : 95.23724166666668
file name : Image_02012024142014381.png
|
2024-01-02 14:20:14.504777 |
54 |
87174695 |
Construction of toilets in public institutions |
117325 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_29122023154620808.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_29122023154620808.png)
latitude : 27.45429
Longitude : 95.22412833333334
file name : Image_29122023154620808.png
|
2023-12-29 15:46:20.896649 |
55 |
87174695 |
Construction of toilets in public institutions |
117325 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_29122023154613783.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_29122023154613783.png)
latitude : 27.45433666666667
Longitude : 95.22428166666666
file name : Image_29122023154613783.png
|
2023-12-29 15:46:13.868026 |
56 |
66103073 |
Construction of toilets in public institutions |
142000 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_10052024141118525.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_10052024141118525.png)
latitude : 27.484015
Longitude : 95.23502333333333
file name : Image_10052024141118525.png
|
2024-05-10 14:11:18.619142 |
57 |
66103094 |
Construction of toilets in public institutions |
142000 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_01022024134039308.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_01022024134039308.png)
latitude : 27.47605666666667
Longitude : 95.24308666666666
file name : Image_01022024134039308.png
|
2024-02-01 13:40:39.424824 |
58 |
66103094 |
Construction of toilets in public institutions |
142000 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_01022024134036282.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_01022024134036282.png)
latitude : 27.475949999999997
Longitude : 95.24306499999999
file name : Image_01022024134036282.png
|
2024-02-01 13:40:36.436098 |
59 |
54023177 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE |
252571 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE1 |
Roof laid |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_08062023135553691.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_08062023135553691.png)
latitude : 27.44887268
Longitude : 95.24489075
file name : Image_08062023135553691.png
|
2023-06-08 13:55:53.797266 |
60 |
54023177 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE |
252571 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_11072022022438339.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_11072022022438339.png)
latitude : 27.44876
Longitude : 95.24484168
file name : Image_11072022022438339.png
|
2022-07-11 02:24:38.442943 |
61 |
54023177 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE |
252571 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_11072022022442340.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_11072022022442340.png)
latitude : 27.44876346
Longitude : 95.24485297
file name : Image_11072022022442340.png
|
2022-07-11 02:24:42.422393 |
62 |
54023177 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE |
252571 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_14062022143714737.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_14062022143714737.png)
latitude : 27.44887867
Longitude : 95.2448684
file name : Image_14062022143714737.png
|
2022-06-14 14:37:14.851946 |
63 |
54023177 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE |
252571 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_14062022143721694.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_14062022143721694.png)
latitude : 27.44885341
Longitude : 95.24489279
file name : Image_14062022143721694.png
|
2022-06-14 14:37:21.788311 |
64 |
54023177 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE |
252571 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04042022152613241.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04042022152613241.png)
latitude : 27.44880633
Longitude : 95.24479806
file name : Image_04042022152613241.png
|
2022-04-04 15:26:13.364589 |
65 |
54023177 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE |
252571 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_03042022115640918.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_03042022115640918.png)
latitude : 27.44879684
Longitude : 95.24477853
file name : Image_03042022115640918.png
|
2022-04-03 11:56:41.045716 |
66 |
54023177 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE |
252571 |
INSTALLATION OF DRINKING WATER FACILITY AT BARUAHOLA GP OFFICE1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_03042022115647241.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_03042022115647241.png)
latitude : 27.44889098
Longitude : 95.24481094
file name : Image_03042022115647241.png
|
2022-04-03 11:56:47.375099 |
67 |
66110523 |
Construction of Open Stage at Puberun Sangha Playground Ph II |
262400 |
Construction of Open Stage at Puberun Sangha Playground Ph II1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_22082023145912510.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_22082023145912510.png)
latitude : 27.45019403
Longitude : 95.25379791
file name : Image_22082023145912510.png
|
2023-08-22 14:59:12.023445 |
68 |
66110523 |
Construction of Open Stage at Puberun Sangha Playground Ph II |
262400 |
Construction of Open Stage at Puberun Sangha Playground Ph II1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_22082023145901512.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_22082023145901512.png)
latitude : 27.45019861
Longitude : 95.25379129
file name : Image_22082023145901512.png
|
2023-08-22 14:59:01.61487 |
69 |
66110523 |
Construction of Open Stage at Puberun Sangha Playground Ph II |
262400 |
Construction of Open Stage at Puberun Sangha Playground Ph II1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_22082023145816842.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_22082023145816842.png)
latitude : 27.45019403
Longitude : 95.25379791
file name : Image_22082023145816842.png
|
2023-08-22 14:58:16.952656 |
70 |
66110312 |
Construction of toilets in public institutions |
113400 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_21082023160130268.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_21082023160130268.png)
latitude : 27.48155497
Longitude : 95.22437047
file name : Image_21082023160130268.png
|
2023-08-21 16:01:30.387101 |
71 |
66110312 |
Construction of toilets in public institutions |
113400 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_21082023160122207.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_21082023160122207.png)
latitude : 27.48159417
Longitude : 95.22437702
file name : Image_21082023160122207.png
|
2023-08-21 16:01:22.31237 |
72 |
66110221 |
Operation & maintenance of drinking water supply system |
226800 |
Operation & maintenance of drinking water supply system1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_28122023224333474.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_28122023224333474.png)
latitude : 27.442819999999998
Longitude : 95.26175833333333
file name : Image_28122023224333474.png
|
2023-12-28 22:43:33.558382 |
73 |
66110221 |
Operation & maintenance of drinking water supply system |
226800 |
Operation & maintenance of drinking water supply system1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_28122023224329214.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_28122023224329214.png)
latitude : 27.44288166666667
Longitude : 95.26178333333334
file name : Image_28122023224329214.png
|
2023-12-28 22:43:29.318241 |
74 |
66110263 |
Construction of toilets in public institutions |
113400 |
Construction of toilets in public institutions1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_28122023224325343.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_28122023224325343.png)
latitude : 27.442701666666668
Longitude : 95.262735
file name : Image_28122023224325343.png
|
2023-12-28 22:43:25.424225 |
75 |
66110263 |
Construction of toilets in public institutions |
113400 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_21082023162720539.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_21082023162720539.png)
latitude : 27.44276102
Longitude : 95.26272161
file name : Image_21082023162720539.png
|
2023-08-21 16:27:20.636302 |
76 |
66110263 |
Construction of toilets in public institutions |
113400 |
Construction of toilets in public institutions1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_21082023162611552.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2021/Image_21082023162611552.png)
latitude : 27.44278338
Longitude : 95.26272874
file name : Image_21082023162611552.png
|
2023-08-21 16:26:11.706642 |
77 |
87174723 |
Construction of Meeting Auditorium at Baruahola Gaon 2223 1st |
312000 |
Construction of Meeting Auditorium at Baruahola Gaon 2223 1st1 |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_01072024132425272.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_01072024132425272.png)
latitude : 27.46344333333333
Longitude : 95.25356500000001
file name : Image_01072024132425272.png
|
2024-07-01 13:24:25.375231 |
78 |
87174723 |
Construction of Meeting Auditorium at Baruahola Gaon 2223 1st |
312000 |
Construction of Meeting Auditorium at Baruahola Gaon 2223 1st1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_10012024124406203.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_10012024124406203.png)
latitude : 27.463351666666668
Longitude : 95.25357000000001
file name : Image_10012024124406203.png
|
2024-01-10 12:44:06.293293 |
79 |
54023190 |
SANITIZATION AT GP AREA DURING COVID 19 PHASE II |
57571 |
SANITIZATION AT GP AREA DURING COVID 19 PHASE II1 |
Roof laid |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04072022154448614.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04072022154448614.png)
latitude : 27.44885583
Longitude : 95.24489256
file name : Image_04072022154448614.png
|
2022-07-04 15:44:48.759659 |
80 |
54023190 |
SANITIZATION AT GP AREA DURING COVID 19 PHASE II |
57571 |
SANITIZATION AT GP AREA DURING COVID 19 PHASE II1 |
Roof laid |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04072022154453485.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_04072022154453485.png)
latitude : 27.44891118
Longitude : 95.24487
file name : Image_04072022154453485.png
|
2022-07-04 15:44:53.605343 |
81 |
66103055 |
Operation & maintenance of drinking water supply system |
284000 |
Operation & maintenance of drinking water supply system1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_12012023101441548.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_12012023101441548.png)
latitude : 27.44903488
Longitude : 95.25376749
file name : Image_12012023101441548.png
|
2023-01-12 10:14:41.634437 |
82 |
98038530 |
INSTALLATION OF SHILAPHALAM AT BARUAHOLA HIGH SCHOOL CAMPUS 2122 2nd |
30000 |
INSTALLATION OF SHILAPHALAM AT BARUAHOLA HIGH SCHOOL CAMPUS 2122 2nd1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_08062024002717159.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_08062024002717159.png)
latitude : 27.44966
Longitude : 95.25206000000001
file name : Image_08062024002717159.png
|
2024-06-08 00:27:17.228032 |
83 |
98038485 |
CONSTRUCTION OF ADDITIONAL CLASSROOM AT BARUAHOLA HIGH SCHOOL 2122 2nd |
303000 |
CONSTRUCTION OF ADDITIONAL CLASSROOM AT BARUAHOLA HIGH SCHOOL 2122 2nd1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_08062024002713688.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_08062024002713688.png)
latitude : 27.449454999999997
Longitude : 95.25182333333332
file name : Image_08062024002713688.png
|
2024-06-08 00:27:13.765991 |
84 |
87174785 |
Construction of Cultural Centre at Gandhia Naharani |
312000 |
Construction of Cultural Centre at Gandhia Naharani1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_01022024134043865.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2022/Image_01022024134043865.png)
latitude : 27.465598333333332
Longitude : 95.23916333333334
file name : Image_01022024134043865.png
|
2024-02-01 13:40:43.990512 |
85 |
66103130 |
CONSTRUCTION OF OPEN STAGE AT DHARIYA GAON 2020-21_2nd |
360000 |
CONSTRUCTION OF OPEN STAGE AT DHARIYA GAON 2020-21_2nd1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_10012024124419022.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/18/2020/Image_10012024124419022.png)
latitude : 27.448990000000002
Longitude : 95.26990166666668
file name : Image_10012024124419022.png
|
2024-01-10 12:44:19.114326 |