1 |
34576063 |
CONSTRUCTION OF CONCRETE ROAD FROM SUBHAS BAGDI HOUSE TO TOWARDS KUYE RIVER AT RAMCHANDRAPUR |
123750 |
CONSTRUCTION OF CONCRETE ROAD FROM SUBHAS BAGDI HOUSE TO TOWARDS KUYE RIVER AT RAMCHANDRAPUR1 |
Roof laid |
-
latitude : 23.78277666666667,23.783051666666665,23.78313166666667
Longitude : 87.80266833333332,87.8031,87.80317166666667
file name : Image_08012021084605319.png
|
2021-01-08 08:46:05.442293 |
2 |
34576063 |
CONSTRUCTION OF CONCRETE ROAD FROM SUBHAS BAGDI HOUSE TO TOWARDS KUYE RIVER AT RAMCHANDRAPUR |
123750 |
CONSTRUCTION OF CONCRETE ROAD FROM SUBHAS BAGDI HOUSE TO TOWARDS KUYE RIVER AT RAMCHANDRAPUR1 |
Plinth level |
-
latitude : 23.790956666666663,23.78305833333333,23.783128333333334
Longitude : 87.81809999999999,87.80304666666667,87.80312333333335
file name : Image_03012021095611987.png
|
2021-01-03 09:56:12.079307 |
3 |
46551911 |
REPAIRING & MAINTANANCE OF TUBEWELL UNDER GP AREA |
842423 |
REPAIRING & MAINTANANCE OF TUBEWELL UNDER GP AREA1 |
Completion of work |
-
latitude : 23.814205
Longitude : 87.797835
file name : Image_10102021081722185.png
|
2021-10-10 08:17:22.284042 |
4 |
34675867 |
CONSTRUCTION OF CONCRETE ROAD FROM CHAND SK HOUSE TO POLICE STATION MORE AT THAKURPARA |
124868 |
CONSTRUCTION OF CONCRETE ROAD FROM CHAND SK HOUSE TO POLICE STATION MORE AT THAKURPARA1 |
Roof laid |
-
latitude : 23.818358333333336,23.8185861,23.8186463,23.8186507
Longitude : 87.80313833333334,87.8028295,87.8028643,87.8028721
file name : Image_08012021102110550.png
|
2021-01-08 10:21:10.617666 |
5 |
34675867 |
CONSTRUCTION OF CONCRETE ROAD FROM CHAND SK HOUSE TO POLICE STATION MORE AT THAKURPARA |
124868 |
CONSTRUCTION OF CONCRETE ROAD FROM CHAND SK HOUSE TO POLICE STATION MORE AT THAKURPARA1 |
Plinth level |
-
latitude : 23.8184991,23.8184719,23.8185923,23.8185923
Longitude : 87.802746,87.8026989,87.8028417,87.8028417
file name : Image_31122020150833678.png
|
2020-12-31 15:08:33.73225 |
6 |
34583657 |
CONCRETE ROAD FROM SALEK SK HOUSE TO MAIN ROAD AT PASCHIMPARA |
108790 |
CONCRETE ROAD FROM SALEK SK HOUSE TO MAIN ROAD AT PASCHIMPARA1 |
Roof laid |
-
latitude : 23.81824,23.81829,23.818410000000004
Longitude : 87.79719500000002,87.79767166666667,87.79769333333334
file name : Image_08012021101431464.png
|
2021-01-08 10:14:31.527387 |
7 |
34559573 |
INSTALATION OF STREET LIGHT FROM UDASHI SANKO TO KAJI PUKUR AT MASTOLI |
149250 |
INSTALATION OF STREET LIGHT FROM UDASHI SANKO TO KAJI PUKUR AT MASTOLI1 |
Plinth level |
-
latitude : 23.803890000000003
Longitude : 87.79934999999999
file name : Image_29052021162710863.png
|
2021-05-29 16:27:10.932826 |
8 |
34559573 |
INSTALATION OF STREET LIGHT FROM UDASHI SANKO TO KAJI PUKUR AT MASTOLI |
149250 |
INSTALATION OF STREET LIGHT FROM UDASHI SANKO TO KAJI PUKUR AT MASTOLI1 |
Plinth level |
-
latitude : 23.803928333333335
Longitude : 87.79936666666666
file name : Image_29052021162714134.png
|
2021-05-29 16:27:14.204438 |
9 |
34559573 |
INSTALATION OF STREET LIGHT FROM UDASHI SANKO TO KAJI PUKUR AT MASTOLI |
149250 |
INSTALATION OF STREET LIGHT FROM UDASHI SANKO TO KAJI PUKUR AT MASTOLI1 |
Plinth level |
-
latitude : 23.803908333333332
Longitude : 87.79934999999999
file name : Image_29052021162717884.png
|
2021-05-29 16:27:17.949805 |
10 |
34559573 |
INSTALATION OF STREET LIGHT FROM UDASHI SANKO TO KAJI PUKUR AT MASTOLI |
149250 |
INSTALATION OF STREET LIGHT FROM UDASHI SANKO TO KAJI PUKUR AT MASTOLI1 |
Plinth level |
-
latitude : 23.803908333333332
Longitude : 87.79934999999999
file name : Image_29052021162724269.png
|
2021-05-29 16:27:24.334146 |
11 |
34650685 |
CONCRETE DARIN WITH COVER SLABE FROM BHAGYABATI BAGDI HOUSE TO JAGANNATH BAGDI HOUSE AT LAGHATA |
49500 |
CONCRETE DARIN WITH COVER SLABE FROM BHAGYABATI BAGDI HOUSE TO JAGANNATH BAGDI HOUSE AT LAGHATA1 |
Roof laid |
-
latitude : 23.81496666666667,23.815008333333335,23.815043333333332,23.815061666666665,23.815103333333333
Longitude : 87.82346666666666,87.82370833333334,87.82383666666668,87.82402333333333,87.82417833333332
file name : Image_08012021104718089.png
|
2021-01-08 10:47:18.168651 |
12 |
34650685 |
CONCRETE DARIN WITH COVER SLABE FROM BHAGYABATI BAGDI HOUSE TO JAGANNATH BAGDI HOUSE AT LAGHATA |
49500 |
CONCRETE DARIN WITH COVER SLABE FROM BHAGYABATI BAGDI HOUSE TO JAGANNATH BAGDI HOUSE AT LAGHATA1 |
Plinth level |
-
latitude : 23.814763333333335,23.815013333333333,23.815063333333335,23.815109999999997
Longitude : 87.82261833333332,87.82371333333334,87.82396166666668,87.82420333333333
file name : Image_31122020145004544.png
|
2020-12-31 14:50:04.608867 |
13 |
34658926 |
CONSTRUCTION OF CONCRETE ROAD WITH DRAIN FROM AMULYA DAS HOUSE TO SUSHANTA MONDAL HOUSE AT BAKUL |
349899 |
CONSTRUCTION OF CONCRETE ROAD WITH DRAIN FROM AMULYA DAS HOUSE TO SUSHANTA MONDAL HOUSE AT BAKUL1 |
Roof laid |
-
latitude : 23.81764333333333,23.817890000000002,23.817948333333334,23.818261666666665,23.81867333333333,23.81878166666667,23.818744999999996
Longitude : 87.82465333333333,87.82456166666667,87.82452666666669,87.82446499999999,87.82452833333333,87.82492500000002,87.825125
file name : Image_08012021104714849.png
|
2021-01-08 10:47:14.935518 |
14 |
34658926 |
CONSTRUCTION OF CONCRETE ROAD WITH DRAIN FROM AMULYA DAS HOUSE TO SUSHANTA MONDAL HOUSE AT BAKUL |
349899 |
CONSTRUCTION OF CONCRETE ROAD WITH DRAIN FROM AMULYA DAS HOUSE TO SUSHANTA MONDAL HOUSE AT BAKUL1 |
Plinth level |
-
latitude : 23.81763,23.817878333333336,23.817943333333332,23.818155,23.818531666666665,23.818740000000002,23.81873
Longitude : 87.82467166666666,87.82458666666668,87.82454333333332,87.82449333333334,87.82454833333334,87.82455499999999,87.82514
file name : Image_31122020145859403.png
|
2020-12-31 14:58:59.488038 |
15 |
34676893 |
CONCRETE ROAD FROM RAM DULAL MUKHERJEE HOUSE TO MADAN MOHON MUKHERJEE HOUSE |
99000 |
CONCRETE ROAD FROM RAM DULAL MUKHERJEE HOUSE TO MADAN MOHON MUKHERJEE HOUSE1 |
Roof laid |
-
latitude : 23.814720000000005,23.8150874,23.814991666666668
Longitude : 87.80397666666667,87.8038088,87.80336666666666
file name : Image_08012021114433741.png
|
2021-01-08 11:44:33.822823 |
16 |
34676893 |
CONCRETE ROAD FROM RAM DULAL MUKHERJEE HOUSE TO MADAN MOHON MUKHERJEE HOUSE |
99000 |
CONCRETE ROAD FROM RAM DULAL MUKHERJEE HOUSE TO MADAN MOHON MUKHERJEE HOUSE1 |
Plinth level |
-
latitude : 23.818231666666666,23.814828333333335,23.814988333333336
Longitude : 87.80312666666666,87.80337833333333,87.80337333333334
file name : Image_31122020151410099.png
|
2020-12-31 15:14:10.157556 |
17 |
34648734 |
CONSTRUCTION OF CONCRETE ROAD FROM PARBATI SHANKAR SCHOOL TO TARASANKAR BHAVAN |
197900 |
CONSTRUCTION OF CONCRETE ROAD FROM PARBATI SHANKAR SCHOOL TO TARASANKAR BHAVAN1 |
Roof laid |
-
latitude : 23.80773,23.807556666666663,23.807438333333334
Longitude : 87.80397666666667,87.80400666666668,87.80464333333333
file name : Image_08012021115125608.png
|
2021-01-08 11:51:25.687647 |
18 |
34648734 |
CONSTRUCTION OF CONCRETE ROAD FROM PARBATI SHANKAR SCHOOL TO TARASANKAR BHAVAN |
197900 |
CONSTRUCTION OF CONCRETE ROAD FROM PARBATI SHANKAR SCHOOL TO TARASANKAR BHAVAN1 |
Plinth level |
-
latitude : 23.816769999999998,23.80753666666667,23.80743166666667
Longitude : 87.81158166666667,87.80396,87.80467500000002
file name : Image_31122020142354125.png
|
2020-12-31 14:23:54.185461 |
19 |
34660042 |
INSTALATION OF TANK FOR DRINKING WATER SUPPLY TO VILLAGERS AT BAKUL |
80000 |
INSTALATION OF TANK FOR DRINKING WATER SUPPLY TO VILLAGERS AT BAKUL1 |
Plinth level |
-
latitude : 23.8147062
Longitude : 87.821145
file name : Image_01122021155135933.png
|
2021-12-01 15:51:36.05017 |
20 |
39064251 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT P KADIPUR SHIBTALA |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT P KADIPUR SHIBTALA1 |
Roof laid |
-
latitude : 23.79333166666667,23.793308333333336
Longitude : 87.80385499999998,87.80387166666667
file name : Image_29052021162721066.png
|
2021-05-29 16:27:21.12431 |
21 |
39064251 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT P KADIPUR SHIBTALA |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT P KADIPUR SHIBTALA1 |
Roof laid |
-
latitude : 23.79333166666667,23.793308333333336
Longitude : 87.80385499999998,87.80387166666667
file name : Image_29052021162727655.png
|
2021-05-29 16:27:27.720625 |
22 |
39064251 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT P KADIPUR SHIBTALA |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT P KADIPUR SHIBTALA1 |
Completion of work |
-
latitude : 23.793323333333333,23.79332
Longitude : 87.80382499999999,87.80382
file name : Image_30012021112830465.png
|
2021-01-30 11:28:30.542392 |
23 |
39064312 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MASTOLI FOOTBALL GOUND |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MASTOLI FOOTBALL GOUND1 |
Roof laid |
-
latitude : 23.800144999999997,23.800155000000004
Longitude : 87.79041666666666,87.79042333333334
file name : Image_29052021170916071.png
|
2021-05-29 17:09:16.126089 |
24 |
39064312 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MASTOLI FOOTBALL GOUND |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MASTOLI FOOTBALL GOUND1 |
Roof laid |
-
latitude : 23.80021,23.80021
Longitude : 87.79038833333334,87.79038833333334
file name : Image_15032021105448287.png
|
2021-03-15 10:54:48.356669 |
25 |
39064312 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MASTOLI FOOTBALL GOUND |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MASTOLI FOOTBALL GOUND1 |
Plinth level |
-
latitude : 23.800285,23.80029833333333
Longitude : 87.79044166666667,87.79043333333333
file name : Image_30012021111713324.png
|
2021-01-30 11:17:13.405899 |
26 |
39063384 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MONA |
300000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MONA1 |
Roof laid |
-
latitude : 23.809624999999997,23.809624999999997
Longitude : 87.83266166666665,87.83265833333334
file name : Image_30052021081155674.png
|
2021-05-30 08:11:55.73753 |
27 |
39063516 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA B SK |
300000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA B SK1 |
Roof laid |
-
latitude : 23.821224999999995,23.821224999999995
Longitude : 87.80062666666666,87.80062666666666
file name : Image_29052021171019288.png
|
2021-05-29 17:10:19.348267 |
28 |
39063516 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA B SK |
300000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA B SK1 |
Roof laid |
-
latitude : 23.821224999999995,23.821224999999995
Longitude : 87.80062666666666,87.80062666666666
file name : Image_29052021171036664.png
|
2021-05-29 17:10:36.727316 |
29 |
39064333 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT H KUNDU HOUSE AT MAHUGRAM |
290000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT H KUNDU HOUSE AT MAHUGRAM1 |
Roof laid |
-
latitude : 23.822751666666665,23.822751666666665
Longitude : 87.80661,87.80661
file name : Image_29052021171028893.png
|
2021-05-29 17:10:28.947262 |
30 |
39064333 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT H KUNDU HOUSE AT MAHUGRAM |
290000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT H KUNDU HOUSE AT MAHUGRAM1 |
Roof laid |
-
latitude : 23.822751666666665,23.822751666666665
Longitude : 87.80661,87.80661
file name : Image_29052021171042676.png
|
2021-05-29 17:10:42.75059 |
31 |
39064333 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT H KUNDU HOUSE AT MAHUGRAM |
290000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT H KUNDU HOUSE AT MAHUGRAM1 |
Roof laid |
-
latitude : 23.822734999999998,23.822734999999998,23.822734999999998
Longitude : 87.80659666666666,87.80659666666666,87.80659666666666
file name : Image_15032021104205119.png
|
2021-03-15 10:42:05.191325 |
32 |
39064333 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT H KUNDU HOUSE AT MAHUGRAM |
290000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT H KUNDU HOUSE AT MAHUGRAM1 |
Plinth level |
-
latitude : 23.82129166666667,23.82129166666667
Longitude : 87.80576666666666,87.80576666666666
file name : Image_20022021084607639.png
|
2021-02-20 08:46:07.728146 |
33 |
53882300 |
SINKING OF TUBE WELL AT TANIMA SADHI HOUSE UNDER TARAMADANGA SANSAD |
90000 |
SINKING OF TUBE WELL AT TANIMA SADHI HOUSE UNDER TARAMADANGA SANSAD1 |
Completion of work |
-
latitude : 23.80865833333333
Longitude : 87.80490999999999
file name : Image_23102021101059267.png
|
2021-10-23 10:10:59.359003 |
34 |
53882289 |
SINKING OF TUBE WELL AT TAMAL GHOSH HOUSE AT TARAMADANGA |
90000 |
SINKING OF TUBE WELL AT TAMAL GHOSH HOUSE AT TARAMADANGA1 |
Plinth level |
-
latitude : 23.815151666666665
Longitude : 87.80778333333335
file name : Image_01112021094210246.png
|
2021-11-01 09:42:10.36669 |
35 |
53882289 |
SINKING OF TUBE WELL AT TAMAL GHOSH HOUSE AT TARAMADANGA |
90000 |
SINKING OF TUBE WELL AT TAMAL GHOSH HOUSE AT TARAMADANGA1 |
Plinth level |
-
latitude : 23.815154999999997
Longitude : 87.80776166666668
file name : Image_01112021094408925.png
|
2021-11-01 09:44:09.028128 |
36 |
53882289 |
SINKING OF TUBE WELL AT TAMAL GHOSH HOUSE AT TARAMADANGA |
90000 |
SINKING OF TUBE WELL AT TAMAL GHOSH HOUSE AT TARAMADANGA1 |
Completion of work |
-
latitude : 23.81302333333333
Longitude : 87.80522333333332
file name : Image_23102021105106740.png
|
2021-10-23 10:51:06.858624 |
37 |
53882271 |
SINKING OF TUBE WELL AT LAGHATA HEMANTA MURMU HOUSE |
55000 |
SINKING OF TUBE WELL AT LAGHATA HEMANTA MURMU HOUSE 1 |
Plinth level |
-
latitude : 23.82268
Longitude : 87.80754666666665
file name : Image_01112021091318935.png
|
2021-11-01 09:13:19.017109 |
38 |
53882271 |
SINKING OF TUBE WELL AT LAGHATA HEMANTA MURMU HOUSE |
55000 |
SINKING OF TUBE WELL AT LAGHATA HEMANTA MURMU HOUSE 1 |
Completion of work |
-
latitude : 23.8147668
Longitude : 87.7970341
file name : Image_26102021124031052.png
|
2021-10-26 12:40:31.166647 |
39 |
53882249 |
SINKING OF TUBE WELL AT MASTOLI PURBA PARA DURGATALA |
65000 |
SINKING OF TUBE WELL AT MASTOLI PURBA PARA DURGATALA1 |
Plinth level |
-
latitude : 23.82269833333333
Longitude : 87.80684500000001
file name : Image_01112021091309265.png
|
2021-11-01 09:13:09.354173 |
40 |
53882249 |
SINKING OF TUBE WELL AT MASTOLI PURBA PARA DURGATALA |
65000 |
SINKING OF TUBE WELL AT MASTOLI PURBA PARA DURGATALA1 |
Completion of work |
-
latitude : 23.80327333333333
Longitude : 87.79885666666665
file name : Image_23102021093912920.png
|
2021-10-23 09:39:13.039447 |
41 |
53882230 |
SINKING OF TUBE WELL AT MASTOLI BAGDI PARA FARING BAGDI HOUSE |
65000 |
SINKING OF TUBE WELL AT MASTOLI BAGDI PARA FARING BAGDI HOUSE1 |
Plinth level |
-
latitude : 23.819475000000004
Longitude : 87.80502499999999
file name : Image_01112021090250347.png
|
2021-11-01 09:02:50.434511 |
42 |
53882230 |
SINKING OF TUBE WELL AT MASTOLI BAGDI PARA FARING BAGDI HOUSE |
65000 |
SINKING OF TUBE WELL AT MASTOLI BAGDI PARA FARING BAGDI HOUSE1 |
Completion of work |
-
latitude : 23.803896666666667
Longitude : 87.79492
file name : Image_23102021092912859.png
|
2021-10-23 09:29:12.986084 |
43 |
53882215 |
SINKING OF TUBE WELL AT MASTOLI ADIBASI PARA SASWAN |
65000 |
SINKING OF TUBE WELL AT MASTOLI ADIBASI PARA SASWAN1 |
Plinth level |
-
latitude : 23.818075
Longitude : 87.80149333333333
file name : Image_01112021085930764.png
|
2021-11-01 08:59:30.861328 |
44 |
53882215 |
SINKING OF TUBE WELL AT MASTOLI ADIBASI PARA SASWAN |
65000 |
SINKING OF TUBE WELL AT MASTOLI ADIBASI PARA SASWAN1 |
Completion of work |
-
latitude : 23.80315166666667
Longitude : 87.79506166666667
file name : Image_23102021093122057.png
|
2021-10-23 09:31:22.185927 |
45 |
53882197 |
SINKING OF TUBE WELL AT LAGHATA AADIBASI PARA RANI BASKI HOUSE |
50000 |
SINKING OF TUBE WELL AT LAGHATA AADIBASI PARA RANI BASKI HOUSE 1 |
Plinth level |
-
latitude : 23.81547666666667
Longitude : 87.79732333333335
file name : Image_01112021085623727.png
|
2021-11-01 08:56:23.856905 |
46 |
53882197 |
SINKING OF TUBE WELL AT LAGHATA AADIBASI PARA RANI BASKI HOUSE |
50000 |
SINKING OF TUBE WELL AT LAGHATA AADIBASI PARA RANI BASKI HOUSE 1 |
Completion of work |
-
latitude : 23.8147553
Longitude : 87.7970964
file name : Image_26102021124126404.png
|
2021-10-26 12:41:26.525339 |
47 |
53882176 |
SINKING OF TUBE WELL AT SONACHITURA KALI TALA |
50000 |
SINKING OF TUBE WELL AT SONACHITURA KALI TALA1 |
Plinth level |
-
latitude : 23.814276666666668
Longitude : 87.79864833333335
file name : Image_01112021082631300.png
|
2021-11-01 08:26:31.428439 |
48 |
53882176 |
SINKING OF TUBE WELL AT SONACHITURA KALI TALA |
50000 |
SINKING OF TUBE WELL AT SONACHITURA KALI TALA1 |
Completion of work |
-
latitude : 23.8146592
Longitude : 87.797084
file name : Image_26102021124351060.png
|
2021-10-26 12:43:51.19106 |
49 |
53882153 |
SINKING OF TUBE WELL AT TARAMADNAGA BIRBHUM SANSKRITBAHINI |
50000 |
SINKING OF TUBE WELL AT TARAMADNAGA BIRBHUM SANSKRITBAHINI1 |
Plinth level |
-
latitude : 23.8139294
Longitude : 87.7978541
file name : Image_01112021082458788.png
|
2021-11-01 08:24:58.886252 |
50 |
53882153 |
SINKING OF TUBE WELL AT TARAMADNAGA BIRBHUM SANSKRITBAHINI |
50000 |
SINKING OF TUBE WELL AT TARAMADNAGA BIRBHUM SANSKRITBAHINI1 |
Completion of work |
-
latitude : 23.8130768
Longitude : 87.8030994
file name : Image_23102021103225614.png
|
2021-10-23 10:32:25.712488 |
51 |
53882314 |
SINKING OF TUBE WELL AT KALYANI BAGDI HOUSE AT TARAMADANGA |
90000 |
SINKING OF TUBE WELL AT KALYANI BAGDI HOUSE AT TARAMADANGA1 |
Plinth level |
-
latitude : 23.814558333333334
Longitude : 87.798565
file name : Image_01112021082813879.png
|
2021-11-01 08:28:13.960651 |
52 |
53882314 |
SINKING OF TUBE WELL AT KALYANI BAGDI HOUSE AT TARAMADANGA |
90000 |
SINKING OF TUBE WELL AT KALYANI BAGDI HOUSE AT TARAMADANGA1 |
Completion of work |
-
latitude : 23.807358333333333
Longitude : 87.80460833333333
file name : Image_23102021100831384.png
|
2021-10-23 10:08:31.483743 |
53 |
34575139 |
CONSTRUCTION OF CONCRETE ROAD FROM TARULAL BAURI HOUSE TO KAJOL BAURI HOUSE AT PASCHIMKADIPUR |
100000 |
CONSTRUCTION OF CONCRETE ROAD FROM TARULAL BAURI HOUSE TO KAJOL BAURI HOUSE AT PASCHIMKADIPUR1 |
Plinth level |
-
latitude : 23.79310666666667,23.79318333333333,23.793345,23.793456666666664
Longitude : 87.80522833333335,87.80529499999999,87.80532166666666,87.80535
file name : Image_23092021123830103.png
|
2021-09-23 12:38:30.228877 |
54 |
34575139 |
CONSTRUCTION OF CONCRETE ROAD FROM TARULAL BAURI HOUSE TO KAJOL BAURI HOUSE AT PASCHIMKADIPUR |
100000 |
CONSTRUCTION OF CONCRETE ROAD FROM TARULAL BAURI HOUSE TO KAJOL BAURI HOUSE AT PASCHIMKADIPUR1 |
Completion of work |
-
latitude : 23.79327166666667,23.793248333333334
Longitude : 87.80522833333335,87.80524333333332
file name : Image_09092021095434835.png
|
2021-09-09 09:54:34.955943 |
55 |
34659643 |
CONSTRUCTION OF CONCRETE ROAD FROM BUSSTAND TO MANTU BAGDI HOUSE AT SONCHITURA |
150000 |
CONSTRUCTION OF CONCRETE ROAD FROM BUSSTAND TO MANTU BAGDI HOUSE AT SONCHITURA1 |
Plinth level |
-
latitude : 23.809966666666664,23.809966666666664
Longitude : 87.845705,87.845705
file name : Image_02112021103534329.png
|
2021-11-02 10:35:34.453127 |
56 |
34659643 |
CONSTRUCTION OF CONCRETE ROAD FROM BUSSTAND TO MANTU BAGDI HOUSE AT SONCHITURA |
150000 |
CONSTRUCTION OF CONCRETE ROAD FROM BUSSTAND TO MANTU BAGDI HOUSE AT SONCHITURA1 |
Completion of work |
-
latitude : 23.809978333333333,23.810028333333335
Longitude : 87.84570333333335,87.84570666666666
file name : Image_16092021080839818.png
|
2021-09-16 08:08:39.936241 |
57 |
53964506 |
Remuneration of SWM Staff |
194150 |
Remuneration of SWM Staff1 |
Plinth level |
-
latitude : 23.8153606,23.8153606
Longitude : 87.7968363,87.7968363
file name : Image_21092021150305840.png
|
2021-09-21 15:03:05.913022 |
58 |
46046921 |
INSTALATION MINI SUBMERSIBLE IN FRONT OF PASCHIMKADIPUR FOOTBALL GROUND |
80000 |
INSTALATION MINI SUBMERSIBLE IN FRONT OF PASCHIMKADIPUR FOOTBALL GROUND1 |
Plinth level |
-
latitude : 23.8147341
Longitude : 87.7971079
file name : Image_09022022150651879.png
|
2022-02-09 15:06:51.957817 |
59 |
46046921 |
INSTALATION MINI SUBMERSIBLE IN FRONT OF PASCHIMKADIPUR FOOTBALL GROUND |
80000 |
INSTALATION MINI SUBMERSIBLE IN FRONT OF PASCHIMKADIPUR FOOTBALL GROUND1 |
Completion of work |
-
latitude : 23.814735
Longitude : 87.7971083
file name : Image_09022022150306529.png
|
2022-02-09 15:03:06.610263 |
60 |
46046771 |
INSTALATION OF STREET LIGHT FROM HANUMANTALA TO ADIBASIPARA AT MASTOLI |
100000 |
INSTALATION OF STREET LIGHT FROM HANUMANTALA TO ADIBASIPARA AT MASTOLI1 |
Roof laid |
-
latitude : 23.814843333333336
Longitude : 87.79710833333333
file name : Image_23032022144008943.png
|
2022-03-23 14:40:09.051432 |
61 |
46046771 |
INSTALATION OF STREET LIGHT FROM HANUMANTALA TO ADIBASIPARA AT MASTOLI |
100000 |
INSTALATION OF STREET LIGHT FROM HANUMANTALA TO ADIBASIPARA AT MASTOLI1 |
Plinth level |
-
latitude : 23.814791666666665
Longitude : 87.797165
file name : Image_23032022142909683.png
|
2022-03-23 14:29:09.780111 |
62 |
46046771 |
INSTALATION OF STREET LIGHT FROM HANUMANTALA TO ADIBASIPARA AT MASTOLI |
100000 |
INSTALATION OF STREET LIGHT FROM HANUMANTALA TO ADIBASIPARA AT MASTOLI1 |
Completion of work |
-
latitude : 23.8148518
Longitude : 87.797209
file name : Image_23032022140534717.png
|
2022-03-23 14:05:34.820546 |
63 |
46071420 |
INST OF STREET LIGHT AT CHILD PARK CINEMATALA SREE PALLY ADIBASI PARA GHOSH PARA PURBA TARASHANKAR |
300000 |
INST OF STREET LIGHT AT CHILD PARK CINEMATALA SREE PALLY ADIBASI PARA GHOSH PARA PURBA TARASHANKAR1 |
Roof laid |
-
latitude : 23.8148506
Longitude : 87.7972089
file name : Image_23032022144322121.png
|
2022-03-23 14:43:22.224657 |
64 |
46071420 |
INST OF STREET LIGHT AT CHILD PARK CINEMATALA SREE PALLY ADIBASI PARA GHOSH PARA PURBA TARASHANKAR |
300000 |
INST OF STREET LIGHT AT CHILD PARK CINEMATALA SREE PALLY ADIBASI PARA GHOSH PARA PURBA TARASHANKAR1 |
Plinth level |
-
latitude : 23.814823333333333
Longitude : 87.79706499999999
file name : Image_23032022142919472.png
|
2022-03-23 14:29:19.598051 |
65 |
46071420 |
INST OF STREET LIGHT AT CHILD PARK CINEMATALA SREE PALLY ADIBASI PARA GHOSH PARA PURBA TARASHANKAR |
300000 |
INST OF STREET LIGHT AT CHILD PARK CINEMATALA SREE PALLY ADIBASI PARA GHOSH PARA PURBA TARASHANKAR1 |
Completion of work |
-
latitude : 23.8148352
Longitude : 87.7971944
file name : Image_23032022140813062.png
|
2022-03-23 14:08:13.171817 |
66 |
46073200 |
INST OF STREET LIGHT FROM BABU THANDAR HOUSE TO CHANDAN DAS BAIRGAYA HOUSE AT GOBINDOPUR |
200000 |
INST OF STREET LIGHT FROM BABU THANDAR HOUSE TO CHANDAN DAS BAIRGAYA HOUSE AT GOBINDOPUR1 |
Roof laid |
-
latitude : 23.814753333333336
Longitude : 87.79720166666667
file name : Image_23032022144005673.png
|
2022-03-23 14:40:05.772734 |
67 |
46073200 |
INST OF STREET LIGHT FROM BABU THANDAR HOUSE TO CHANDAN DAS BAIRGAYA HOUSE AT GOBINDOPUR |
200000 |
INST OF STREET LIGHT FROM BABU THANDAR HOUSE TO CHANDAN DAS BAIRGAYA HOUSE AT GOBINDOPUR1 |
Plinth level |
-
latitude : 23.81483166666667
Longitude : 87.79703833333333
file name : Image_23032022142906311.png
|
2022-03-23 14:29:06.405502 |
68 |
46073200 |
INST OF STREET LIGHT FROM BABU THANDAR HOUSE TO CHANDAN DAS BAIRGAYA HOUSE AT GOBINDOPUR |
200000 |
INST OF STREET LIGHT FROM BABU THANDAR HOUSE TO CHANDAN DAS BAIRGAYA HOUSE AT GOBINDOPUR1 |
Completion of work |
-
latitude : 23.8148338
Longitude : 87.7971887
file name : Image_23032022113918022.png
|
2022-03-23 11:39:18.135553 |
69 |
46046853 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN |
250000 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN1 |
Roof laid |
-
latitude : 23.814828333333335
Longitude : 87.79711833333334
file name : Image_23032022144012130.png
|
2022-03-23 14:40:12.22926 |
70 |
46046853 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN |
250000 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN1 |
Roof laid |
-
latitude : 23.814878
Longitude : 87.7972181
file name : Image_23032022144314598.png
|
2022-03-23 14:43:14.705968 |
71 |
46046853 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN |
250000 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN1 |
Roof laid |
-
latitude : 23.8148522
Longitude : 87.7972098
file name : Image_23032022144318313.png
|
2022-03-23 14:43:18.414156 |
72 |
46046853 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN |
250000 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN1 |
Plinth level |
-
latitude : 23.81489
Longitude : 87.797115
file name : Image_23032022142913086.png
|
2022-03-23 14:29:13.180819 |
73 |
46046853 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN |
250000 |
INST OF STREET LIGHT FROM KAJIPARA VIA BAGDI PARA VIA DAS PARA VIA BAURI PARA VIA HAZRA PARA TO DAN1 |
Completion of work |
-
latitude : 23.8148528
Longitude : 87.7972117
file name : Image_23032022140634812.png
|
2022-03-23 14:06:34.892597 |
74 |
46047156 |
INSTALATION OF STREET LIGHT AT MUSLIM PARA AREA |
200000 |
INSTALATION OF STREET LIGHT AT MUSLIM PARA AREA1 |
Plinth level |
-
latitude : 23.814869999999996
Longitude : 87.79714333333335
file name : Image_23032022142916268.png
|
2022-03-23 14:29:16.361001 |
75 |
46047156 |
INSTALATION OF STREET LIGHT AT MUSLIM PARA AREA |
200000 |
INSTALATION OF STREET LIGHT AT MUSLIM PARA AREA1 |
Completion of work |
-
latitude : 23.8148497
Longitude : 87.7972068
file name : Image_23032022140729804.png
|
2022-03-23 14:07:29.902396 |
76 |
46071111 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT TARAMADANGA SANSAD |
220000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT TARAMADANGA SANSAD1 |
Completion of work |
-
latitude : 23.8148276,23.814828
Longitude : 87.7971908,87.7971889
file name : Image_28032022163956165.png
|
2022-03-28 16:39:56.25877 |
77 |
34604866 |
CONSTRUCTION OF CONCRETE ROAD FROM RAKKHAKAR MONDAL TO SANTOSH HAZRA VIA KALTALA |
60000 |
CONSTRUCTION OF CONCRETE ROAD FROM RAKKHAKAR MONDAL TO SANTOSH HAZRA VIA KALTALA 1 |
Plinth level |
-
latitude : 23.80942333333333,23.809425
Longitude : 87.804965,87.80496333333333
file name : Image_28092021104240687.png
|
2021-09-28 10:42:40.785817 |
78 |
46072881 |
INST OF SUB-MERSIBLE WITH TANK AND PIPE LINE FOR DRINKING WATER NEAR KUSH MONDAL HOUSE AT BAKUL |
270000 |
INST OF SUB-MERSIBLE WITH TANK AND PIPE LINE FOR DRINKING WATER NEAR KUSH MONDAL HOUSE AT BAKUL1 |
Completion of work |
-
latitude : 23.814661666666666,23.814653333333332
Longitude : 87.79762666666666,87.79763499999999
file name : Image_13042022131828109.png
|
2022-04-13 13:18:28.170216 |
79 |
46047078 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT MIRZA PARA UNDER T PARA |
250000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT MIRZA PARA UNDER T PARA1 |
Roof laid |
-
latitude : 23.814805,23.8148045
Longitude : 87.7971495,87.7971497
file name : Image_28042022123059942.png
|
2022-04-28 12:31:00.024858 |
80 |
46047078 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT MIRZA PARA UNDER T PARA |
250000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT MIRZA PARA UNDER T PARA1 |
Plinth level |
-
latitude : 23.8148102,23.8148102
Longitude : 87.797151,87.797151
file name : Image_28042022122920499.png
|
2022-04-28 12:29:20.622219 |
81 |
46047078 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT MIRZA PARA UNDER T PARA |
250000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT MIRZA PARA UNDER T PARA1 |
Completion of work |
-
latitude : 23.8148029,23.8148029
Longitude : 87.7971515,87.7971515
file name : Image_28042022122657692.png
|
2022-04-28 12:26:57.776586 |
82 |
46047078 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT MIRZA PARA UNDER T PARA |
250000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT MIRZA PARA UNDER T PARA1 |
Completion of work |
-
latitude : 23.8147348,23.8148153
Longitude : 87.79667,87.7971528
file name : Image_28042022122653911.png
|
2022-04-28 12:26:54.046148 |
83 |
39064402 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MAHUGRAM KALITALA |
290000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MAHUGRAM KALITALA1 |
Plinth level |
-
latitude : 23.822733333333336,23.822733333333336
Longitude : 87.80659833333333,87.80659833333333
file name : Image_26092021093941112.png
|
2021-09-26 09:39:41.228845 |
84 |
39064402 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MAHUGRAM KALITALA |
290000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT MAHUGRAM KALITALA1 |
Completion of work |
-
latitude : 23.82277333333333,23.822748333333333
Longitude : 87.80662333333333,87.80659666666666
file name : Image_13082021150526671.png
|
2021-08-13 15:05:26.759458 |
85 |
46047102 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT ASHLA PARA UNDER T PARA |
250000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT ASHLA PARA UNDER T PARA1 |
Roof laid |
-
latitude : 23.814807,23.8148056
Longitude : 87.7971586,87.7971499
file name : Image_29042022140136889.png
|
2022-04-29 14:01:36.980794 |
86 |
46047102 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT ASHLA PARA UNDER T PARA |
250000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT ASHLA PARA UNDER T PARA1 |
Plinth level |
-
latitude : 23.8148059,23.8143588
Longitude : 87.7971587,87.7971586
file name : Image_29042022135823001.png
|
2022-04-29 13:58:23.109895 |
87 |
46047102 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT ASHLA PARA UNDER T PARA |
250000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT ASHLA PARA UNDER T PARA1 |
Completion of work |
-
latitude : 23.814808,23.8148126
Longitude : 87.7971593,87.7971542
file name : Image_29042022135555866.png
|
2022-04-29 13:55:55.96239 |
88 |
34675968 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT THAKURPARA |
200000 |
INSTALATION OF PIPE LINE FOR DRINKING WATER SUPPLY TO VILLAGERS AT THAKURPARA1 |
Completion of work |
-
latitude : 23.82129166666667,23.821318333333338
Longitude : 87.80060499999999,87.80061499999998
file name : Image_13082021151045694.png
|
2021-08-13 15:10:45.802296 |
89 |
34581577 |
CONCRETE DRAIN WITH COVER SLABE FROM SABUJ HOUSE TO KUDU HOUSE AT PASCHIMPARA |
170000 |
CONCRETE DRAIN WITH COVER SLABE FROM SABUJ HOUSE TO KUDU HOUSE AT PASCHIMPARA1 |
Completion of work |
-
latitude : 23.82241333333333,23.822420000000005
Longitude : 87.79847999999998,87.79848166666667
file name : Image_16092021110319973.png
|
2021-09-16 11:03:20.055567 |
90 |
46046831 |
CONSTRUCTION OF CONCRETE ROAD FROM DALIM MASTER HOUSE TO JAHANGIR BABU HOUSE AT MASTOLI |
200000 |
CONSTRUCTION OF CONCRETE ROAD FROM DALIM MASTER HOUSE TO JAHANGIR BABU HOUSE AT MASTOLI1 |
Completion of work |
-
latitude : 23.8112271,23.8111931,23.8111918
Longitude : 87.7974081,87.797397,87.7973944
file name : Image_25072022100028037.png
|
2022-07-25 10:00:28.12766 |
91 |
46047048 |
CONSTRUCTION OF CONCRETE ROAD FROM AJIJUL MALLIK HOUSE TO HIRA CHOUDHURY HOUSE AT P PARA |
220000 |
CONSTRUCTION OF CONCRETE ROAD FROM AJIJUL MALLIK HOUSE TO HIRA CHOUDHURY HOUSE AT P PARA1 |
Completion of work |
-
latitude : 23.818095000000003,23.818111666666663,23.81811,23.81806,23.817901666666664
Longitude : 87.79817333333334,87.79798666666666,87.79788666666667,87.79775833333333,87.79774166666667
file name : Image_06072022073012893.png
|
2022-07-06 07:30:12.999806 |
92 |
46073344 |
CONSTRUCTION OF CONCRETE ROAD FROM GOPAL MONDAL HOUSE TO SABITRI MURMU HOUSE AT LAGHATA |
210000 |
CONSTRUCTION OF CONCRETE ROAD FROM GOPAL MONDAL HOUSE TO SABITRI MURMU HOUSE AT LAGHATA1 |
Completion of work |
-
latitude : 23.814028333333333,23.814148333333332,23.814085
Longitude : 87.81988333333332,87.81962166666666,87.81937666666666
file name : Image_17072022084850665.png
|
2022-07-17 08:48:50.745192 |
93 |
56118265 |
Repairing & Maintanace Of Tube Well Under GP Area |
802490 |
Repairing & Maintanace Of Tube Well Under GP Area1 |
Completion of work |
-
latitude : 23.814225000000004
Longitude : 87.797755
file name : Image_08072022123657566.png
|
2022-07-08 12:36:57.65288 |
94 |
46071619 |
CONSTRUCTION OF CONCRETE DRAIN FROM GAYETRI DAS HOUSE TO INFRONT OF PRY SCHOOL AT SANDIPAN |
350000 |
CONSTRUCTION OF CONCRETE DRAIN FROM GAYETRI DAS HOUSE TO INFRONT OF PRY SCHOOL AT SANDIPAN1 |
Completion of work |
-
latitude : 23.8147853,23.8147515
Longitude : 87.7971265,87.7971274
file name : Image_03082022142019061.png
|
2022-08-03 14:20:19.127845 |
95 |
46559886 |
CONSTRUCTION OF CONCRETE DRAIN FROM MURALI TEA STALL TO SIBU TEA STALL AT T DANGA |
80000 |
CONSTRUCTION OF CONCRETE DRAIN FROM MURALI TEA STALL TO SIBU TEA STALL AT T DANGA1 |
Completion of work |
-
latitude : 23.813190000000002,23.81312833333333,23.8126128,23.8126128
Longitude : 87.80531,87.80551666666666,87.8060571,87.8060571
file name : Image_04082022104449055.png
|
2022-08-04 10:44:49.145133 |
96 |
47212355 |
RENOVATION OF ICDS CENTRE AT PASCHIMKADIPUR |
100000 |
RENOVATION OF ICDS CENTRE AT PASCHIMKADIPUR1 |
Completion of work |
-
latitude : 23.794643333333337
Longitude : 87.80301
file name : Image_04082022101725774.png
|
2022-08-04 10:17:25.841324 |
97 |
46073027 |
CONSTRUCTION OF BOTH SIDE CONCRETE DRAIN FROM SUBOL MONDAL HOUSE TO FULLARA MONDAL HOUSE AT BAKUL |
310000 |
CONSTRUCTION OF BOTH SIDE CONCRETE DRAIN FROM SUBOL MONDAL HOUSE TO FULLARA MONDAL HOUSE AT BAKUL1 |
Plinth level |
-
latitude : 23.814923333333333,23.814923333333333
Longitude : 87.79714333333335,87.79714333333335
file name : Image_03082022143502602.png
|
2022-08-03 14:35:02.679867 |
98 |
46073027 |
CONSTRUCTION OF BOTH SIDE CONCRETE DRAIN FROM SUBOL MONDAL HOUSE TO FULLARA MONDAL HOUSE AT BAKUL |
310000 |
CONSTRUCTION OF BOTH SIDE CONCRETE DRAIN FROM SUBOL MONDAL HOUSE TO FULLARA MONDAL HOUSE AT BAKUL1 |
Completion of work |
-
latitude : 23.814914999999996,23.8147713
Longitude : 87.79717166666666,87.7971312
file name : Image_03082022143230104.png
|
2022-08-03 14:32:30.17662 |
99 |
46552236 |
RENOVATION OF GRAM PANCHAYAT BHAVAN |
250000 |
RENOVATION OF GRAM PANCHAYAT BHAVAN1 |
Plinth level |
-
latitude : 23.8148753
Longitude : 87.7972252
file name : Image_18022022141414294.png
|
2022-02-18 14:14:14.386448 |
100 |
46552236 |
RENOVATION OF GRAM PANCHAYAT BHAVAN |
250000 |
RENOVATION OF GRAM PANCHAYAT BHAVAN1 |
Completion of work |
-
latitude : 23.814922
Longitude : 87.7972228
file name : Image_18022022140918143.png
|
2022-02-18 14:09:18.236707 |
101 |
66071170 |
Creation of a new source of drinking water |
60000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 23.8151489
Longitude : 87.7964716
file name : Image_08022023150852995.png
|
2023-02-08 15:08:53.063046 |
102 |
66071170 |
Creation of a new source of drinking water |
60000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 23.81568333333333
Longitude : 87.79595499999999
file name : Image_08022023150709061.png
|
2023-02-08 15:07:09.140268 |
103 |
66071170 |
Creation of a new source of drinking water |
60000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 23.81566666666667
Longitude : 87.79595166666668
file name : Image_08022023150338271.png
|
2023-02-08 15:03:38.371259 |
104 |
66071197 |
Creation of a new source of drinking water |
60000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 23.817656666666668
Longitude : 87.82149333333334
file name : Image_08022023153715492.png
|
2023-02-08 15:37:15.586485 |
105 |
66071197 |
Creation of a new source of drinking water |
60000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 23.8181299
Longitude : 87.8216928
file name : Image_08022023154320537.png
|
2023-02-08 15:43:20.631347 |
106 |
66071197 |
Creation of a new source of drinking water |
60000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 23.81765833333333
Longitude : 87.82150000000001
file name : Image_08022023153307627.png
|
2023-02-08 15:33:07.708522 |
107 |
56118569 |
Construction Of PCC Road From Sajal Hazra House to Morol Pukur Ghat at Mahugram |
150000 |
Construction Of PCC Road From Sajal Hazra House to Morol Pukur Ghat at Mahugram1 |
Completion of work |
-
latitude : 23.822501666666668,23.822596666666662
Longitude : 87.80894000000002,87.80854
file name : Image_21032023073924900.png
|
2023-03-21 07:39:24.954432 |
108 |
56120323 |
Construction Of Concrete Platform of Mahugram Thakurpara Iddgaon |
170000 |
Construction Of Concrete Platform of Mahugram Thakurpara Iddgaon 1 |
Completion of work |
-
latitude : 23.810623333333336
Longitude : 87.79855166666667
file name : Image_16032023101627253.png
|
2023-03-16 10:16:27.328532 |
109 |
56118736 |
Instalation Of Street Light at Thakurpara Area |
80000 |
Instalation Of Street Light at Thakurpara Area1 |
Completion of work |
-
latitude : 23.8187275
Longitude : 87.8016425
file name : Image_21032023072332918.png
|
2023-03-21 07:23:32.967427 |
110 |
56118594 |
Instalation Of Street Light at Hazra Para and Debipur |
50000 |
Instalation Of Street Light at Hazra Para and Debipur1 |
Completion of work |
-
latitude : 23.822673333333334
Longitude : 87.80748
file name : Image_21032023073115158.png
|
2023-03-21 07:31:15.210613 |
111 |
56168907 |
Instalation Of Street Light From Sandipan Pry School to Champa Jwellers at Sandipan |
20000 |
Instalation Of Street Light From Sandipan Pry School to Champa Jwellers at Sandipan1 |
Completion of work |
-
latitude : 23.816063333333332
Longitude : 87.80588166666666
file name : Image_21032023074838849.png
|
2023-03-21 07:48:38.935144 |
112 |
66071243 |
Creation of a new source of drinking water |
130000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 23.8148411
Longitude : 87.7970297
file name : Image_08022023144749294.png
|
2023-02-08 14:47:49.380367 |
113 |
66071243 |
Creation of a new source of drinking water |
130000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 23.8148908
Longitude : 87.7969574
file name : Image_08022023145251915.png
|
2023-02-08 14:52:52.00377 |
114 |
66071243 |
Creation of a new source of drinking water |
130000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 23.8148349
Longitude : 87.7970318
file name : Image_08022023143856038.png
|
2023-02-08 14:38:56.139102 |
115 |
56118672 |
Providing Water Facility to Community through Pipeline From Durgatala to Hazra Para Via Natun Para |
130000 |
Providing Water Facility to Community through Pipeline From Durgatala to Hazra Para Via Natun Para 1 |
Completion of work |
-
latitude : 23.822678333333336,23.822678333333336,23.822663333333335
Longitude : 87.80758666666667,87.80758666666667,87.80768000000002
file name : Image_21032023073426151.png
|
2023-03-21 07:34:26.201817 |
116 |
56155191 |
Instalation of Dustbin for Community beside at Baneswar Ghosh House at Taramadanga |
10000 |
Instalation of Dustbin for Community beside at Baneswar Ghosh House at Taramadanga1 |
Completion of work |
-
latitude : 23.811136666666666
Longitude : 87.80478
file name : Image_27022023133541107.png
|
2023-02-27 13:35:41.167173 |
117 |
56155191 |
Instalation of Dustbin for Community beside at Baneswar Ghosh House at Taramadanga |
10000 |
Instalation of Dustbin for Community beside at Baneswar Ghosh House at Taramadanga1 |
Completion of work |
-
latitude : 23.811136666666666
Longitude : 87.80478
file name : Image_27022023133605833.png
|
2023-02-27 13:36:05.894326 |
118 |
56168771 |
Instalation of Dustbin For Community Beside of Basudeb Das Sweet Shoap at Gobindopur |
7000 |
Instalation of Dustbin For Community Beside of Basudeb Das Sweet Shoap at Gobindopur1 |
Plinth level |
-
latitude : 23.81448833333333
Longitude : 87.82074333333334
file name : Image_09032023130413676.png
|
2023-03-09 13:04:13.741954 |
119 |
56168771 |
Instalation of Dustbin For Community Beside of Basudeb Das Sweet Shoap at Gobindopur |
7000 |
Instalation of Dustbin For Community Beside of Basudeb Das Sweet Shoap at Gobindopur1 |
Completion of work |
-
latitude : 23.812306666666668
Longitude : 87.83692500000001
file name : Image_27022023135006791.png
|
2023-02-27 13:50:06.854964 |
120 |
56155186 |
Instalation of Dustbin for Community beside at Fish Market at Taramadanga |
7000 |
Instalation of Dustbin for Community beside at Fish Market at Taramadanga1 |
Completion of work |
-
latitude : 23.8122035
Longitude : 87.8057861
file name : Image_27022023133530502.png
|
2023-02-27 13:35:30.58358 |
121 |
56118284 |
Maintenance and Upgradation of SLWM Unit |
269490 |
Maintenance and Upgradation of SLWM Unit1 |
Completion of work |
-
latitude : 23.810688333333328
Longitude : 87.83011
file name : Image_27022023140942280.png
|
2023-02-27 14:09:42.345748 |
122 |
56155176 |
Providing Water Facility to Community through Pipeline at Ghoshpara and Nichupara at Taramadanga |
230000 |
Providing Water Facility to Community through Pipeline at Ghoshpara and Nichupara at Taramadanga1 |
Completion of work |
-
latitude : 23.808625,23.80844833333333,23.808303333333335
Longitude : 87.806135,87.80627666666666,87.806425
file name : Image_27022023133544813.png
|
2023-02-27 13:35:44.876479 |
123 |
56155176 |
Providing Water Facility to Community through Pipeline at Ghoshpara and Nichupara at Taramadanga |
230000 |
Providing Water Facility to Community through Pipeline at Ghoshpara and Nichupara at Taramadanga1 |
Completion of work |
-
latitude : 23.808625,23.80844833333333,23.808303333333335
Longitude : 87.806135,87.80627666666666,87.806425
file name : Image_27022023133609555.png
|
2023-02-27 13:36:09.617189 |
124 |
56155183 |
Instalation of Dustbin for Community beside at Chumki Sweet at Taramadanga |
7000 |
Instalation of Dustbin for Community beside at Chumki Sweet at Taramadanga1 |
Plinth level |
-
latitude : 23.8109445
Longitude : 87.8060696
file name : Image_09032023132417776.png
|
2023-03-09 13:24:17.82844 |
125 |
56155183 |
Instalation of Dustbin for Community beside at Chumki Sweet at Taramadanga |
7000 |
Instalation of Dustbin for Community beside at Chumki Sweet at Taramadanga1 |
Completion of work |
-
latitude : 23.8112631
Longitude : 87.8057896
file name : Image_27022023133534108.png
|
2023-02-27 13:35:34.174516 |
126 |
56169938 |
Installation Of Dustbin Beside at Karmatirtha at Bakul |
10000 |
Installation Of Dustbin Beside at Karmatirtha at Bakul1 |
Plinth level |
-
latitude : 23.814428333333332
Longitude : 87.82070166666666
file name : Image_09032023125853745.png
|
2023-03-09 12:58:53.806658 |
127 |
56169938 |
Installation Of Dustbin Beside at Karmatirtha at Bakul |
10000 |
Installation Of Dustbin Beside at Karmatirtha at Bakul1 |
Completion of work |
-
latitude : 23.8146323
Longitude : 87.8209826
file name : Image_27022023133548262.png
|
2023-02-27 13:35:48.330178 |
128 |
56169938 |
Installation Of Dustbin Beside at Karmatirtha at Bakul |
10000 |
Installation Of Dustbin Beside at Karmatirtha at Bakul1 |
Completion of work |
-
latitude : 23.8146323
Longitude : 87.8209826
file name : Image_27022023133613001.png
|
2023-02-27 13:36:13.062343 |
129 |
66071284 |
Operation & maintenance of community sanitary complex |
260000 |
Operation & maintenance of community sanitary complex1 |
Roof laid |
-
latitude : 23.819785000000003,23.81949666666667,23.8187162,23.819238333333335,23.819125,23.819014999999997
Longitude : 87.80285166666665,87.80268833333334,87.8028816,87.80252,87.80251166666667,87.80247833333333
file name : Image_09032023123454646.png
|
2023-03-09 12:34:54.706803 |
130 |
66071284 |
Operation & maintenance of community sanitary complex |
260000 |
Operation & maintenance of community sanitary complex1 |
Plinth level |
-
latitude : 23.818725,23.8187199,23.8187199
Longitude : 87.8028853,87.8028856,87.8028856
file name : Image_17022023125031959.png
|
2023-02-17 12:50:32.043781 |
131 |
66071284 |
Operation & maintenance of community sanitary complex |
260000 |
Operation & maintenance of community sanitary complex1 |
Completion of work |
-
latitude : 23.819194999999997,23.819209999999998,23.819636666666664
Longitude : 87.80252833333334,87.80253833333333,87.80269666666666
file name : Image_08022023151824883.png
|
2023-02-08 15:18:24.954394 |
132 |
56168785 |
Instalation of Submersible With Overhead Tank and Pipeline for Community of Moni Thander House at G |
150000 |
Instalation of Submersible With Overhead Tank and Pipeline for Community of Moni Thander House at G1 |
Plinth level |
-
latitude : 23.81385833333333,23.81385833333333
Longitude : 87.83382000000002,87.83389166666666
file name : Image_09032023130845166.png
|
2023-03-09 13:08:45.223896 |
133 |
56168785 |
Instalation of Submersible With Overhead Tank and Pipeline for Community of Moni Thander House at G |
150000 |
Instalation of Submersible With Overhead Tank and Pipeline for Community of Moni Thander House at G1 |
Completion of work |
-
latitude : 23.817008333333334,23.81382833333333
Longitude : 87.82381666666667,87.83374833333333
file name : Image_27022023134228259.png
|
2023-02-27 13:42:28.319704 |
134 |
56118350 |
Sinking Of Tube Well of Providing Safe Drinking Water Khairul Islam House at Mastali Muslimpara |
60000 |
Sinking Of Tube Well of Providing Safe Drinking Water Khairul Islam House at Mastali Muslimpara1 |
Completion of work |
-
latitude : 23.804583333333333
Longitude : 87.79766666666667
file name : Image_09032023133118094.png
|
2023-03-09 13:31:18.166566 |
135 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area1 |
Completion of work |
-
latitude : 23.8182872
Longitude : 87.8033319
file name : Image_09032023122915463.png
|
2023-03-09 12:29:15.524294 |
136 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area2 |
Completion of work |
-
latitude : 23.81816666666667
Longitude : 87.80349333333334
file name : Image_09032023122922053.png
|
2023-03-09 12:29:22.125724 |
137 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area3 |
Completion of work |
-
latitude : 23.8182878
Longitude : 87.8033248
file name : Image_09032023122930100.png
|
2023-03-09 12:29:30.161055 |
138 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area4 |
Completion of work |
-
latitude : 23.818234
Longitude : 87.8034983
file name : Image_09032023122936109.png
|
2023-03-09 12:29:36.171734 |
139 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area5 |
Completion of work |
-
latitude : 23.818268333333336
Longitude : 87.80396
file name : Image_09032023122943223.png
|
2023-03-09 12:29:43.30133 |
140 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area6 |
Completion of work |
-
latitude : 23.818348333333333
Longitude : 87.80408666666666
file name : Image_09032023122954073.png
|
2023-03-09 12:29:54.138556 |
141 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area7 |
Completion of work |
-
latitude : 23.818309999999997
Longitude : 87.80396333333334
file name : Image_09032023123005396.png
|
2023-03-09 12:30:05.460804 |
142 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area8 |
Completion of work |
-
latitude : 23.8181754
Longitude : 87.8035894
file name : Image_09032023123011969.png
|
2023-03-09 12:30:12.040194 |
143 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area9 |
Completion of work |
-
latitude : 23.8182765
Longitude : 87.803385
file name : Image_09032023123018107.png
|
2023-03-09 12:30:18.165929 |
144 |
56155170 |
Instalation Of Street Light at Babupara Area |
50000 |
Instalation Of Street Light at Babupara Area10 |
Completion of work |
-
latitude : 23.818336666666664
Longitude : 87.80366166666666
file name : Image_09032023123029077.png
|
2023-03-09 12:30:29.136929 |
145 |
56027714 |
Construction and Maintenance Of Gram Panchayat Office |
150000 |
Construction and Maintenance Of Gram Panchayat Office1 |
Plinth level |
-
latitude : 23.8149014
Longitude : 87.796956
file name : Image_13122023123508153.png
|
2023-12-13 12:35:08.220217 |
146 |
56027714 |
Construction and Maintenance Of Gram Panchayat Office |
150000 |
Construction and Maintenance Of Gram Panchayat Office1 |
Completion of work |
-
latitude : 23.8148176
Longitude : 87.7971133
file name : Image_09032023120356518.png
|
2023-03-09 12:03:56.585732 |
147 |
56155182 |
Instalation of Dustbin for Community in front of PBG Bank |
7000 |
Instalation of Dustbin for Community in front of PBG Bank1 |
Plinth level |
-
latitude : 23.8111475
Longitude : 87.8049715
file name : Image_09032023132421115.png
|
2023-03-09 13:24:21.166659 |
148 |
56155182 |
Instalation of Dustbin for Community in front of PBG Bank |
7000 |
Instalation of Dustbin for Community in front of PBG Bank1 |
Completion of work |
-
latitude : 23.8111157
Longitude : 87.8047135
file name : Image_27022023133537600.png
|
2023-02-27 13:35:37.662 |
149 |
56155182 |
Instalation of Dustbin for Community in front of PBG Bank |
7000 |
Instalation of Dustbin for Community in front of PBG Bank1 |
Completion of work |
-
latitude : 23.8111157
Longitude : 87.8047135
file name : Image_27022023133602280.png
|
2023-02-27 13:36:02.342314 |
150 |
56169955 |
Installation Of Dustbin In Front Of Raghunath Dutta House at Bakul Chowrasta |
10000 |
Installation Of Dustbin In Front Of Raghunath Dutta House at Bakul Chowrasta1 |
Plinth level |
-
latitude : 23.815046666666664
Longitude : 87.82069333333332
file name : Image_09032023125850279.png
|
2023-03-09 12:58:50.337016 |
151 |
56169955 |
Installation Of Dustbin In Front Of Raghunath Dutta House at Bakul Chowrasta |
10000 |
Installation Of Dustbin In Front Of Raghunath Dutta House at Bakul Chowrasta1 |
Completion of work |
-
latitude : 23.8147542
Longitude : 87.8210186
file name : Image_27022023133551674.png
|
2023-02-27 13:35:51.743099 |
152 |
56169955 |
Installation Of Dustbin In Front Of Raghunath Dutta House at Bakul Chowrasta |
10000 |
Installation Of Dustbin In Front Of Raghunath Dutta House at Bakul Chowrasta1 |
Completion of work |
-
latitude : 23.8147542
Longitude : 87.8210186
file name : Image_27022023133616462.png
|
2023-02-27 13:36:16.52682 |
153 |
56169926 |
Installation Of Dustbin In Front Of Laha Mishthanna Bhandar at Bakul Bazar |
10000 |
Installation Of Dustbin In Front Of Laha Mishthanna Bhandar at Bakul Bazar 1 |
Plinth level |
-
latitude : 23.8151176
Longitude : 87.8209375
file name : Image_09032023125846874.png
|
2023-03-09 12:58:46.947097 |
154 |
56169926 |
Installation Of Dustbin In Front Of Laha Mishthanna Bhandar at Bakul Bazar |
10000 |
Installation Of Dustbin In Front Of Laha Mishthanna Bhandar at Bakul Bazar 1 |
Completion of work |
-
latitude : 23.8150993
Longitude : 87.8209491
file name : Image_27022023133555140.png
|
2023-02-27 13:35:55.20674 |
155 |
56169926 |
Installation Of Dustbin In Front Of Laha Mishthanna Bhandar at Bakul Bazar |
10000 |
Installation Of Dustbin In Front Of Laha Mishthanna Bhandar at Bakul Bazar 1 |
Completion of work |
-
latitude : 23.8150993
Longitude : 87.8209491
file name : Image_27022023133619854.png
|
2023-02-27 13:36:19.920677 |
156 |
66071348 |
Installation of Street light at Labpur-I |
150000 |
Installation of Street light at Labpur-I1 |
Plinth level |
-
latitude : 23.814876
Longitude : 87.7969888
file name : Image_09032023121610752.png
|
2023-03-09 12:16:10.850352 |
157 |
66071348 |
Installation of Street light at Labpur-I |
150000 |
Installation of Street light at Labpur-I1 |
Plinth level |
-
latitude : 23.809053333333335
Longitude : 87.84446666666666
file name : Image_17022023133112733.png
|
2023-02-17 13:31:12.828199 |
158 |
66071348 |
Installation of Street light at Labpur-I |
150000 |
Installation of Street light at Labpur-I1 |
Completion of work |
-
latitude : 23.8148716
Longitude : 87.7969542
file name : Image_08022023145826068.png
|
2023-02-08 14:58:26.173194 |
159 |
67027961 |
Grey water management — collection infrastructure |
12500 |
Grey water management — collection infrastructure1 |
Completion of work |
-
latitude : 23.791563333333336
Longitude : 87.80415999999998
file name : Image_24032023115047623.png
|
2023-03-24 11:50:47.696297 |
160 |
67027951 |
Grey water management — collection infrastructure |
12500 |
Grey water management — collection infrastructure1 |
Completion of work |
-
latitude : 23.791604999999997
Longitude : 87.80414166666667
file name : Image_24032023115324415.png
|
2023-03-24 11:53:24.475001 |
161 |
67027968 |
Grey water management — collection infrastructure |
12500 |
Grey water management — collection infrastructure1 |
Completion of work |
-
latitude : 23.814963333333335
Longitude : 87.806675
file name : Image_19042023100832700.png
|
2023-04-19 10:08:32.761858 |
162 |
67027968 |
Grey water management — collection infrastructure |
12500 |
Grey water management — collection infrastructure1 |
Completion of work |
-
latitude : 23.815618333333337
Longitude : 87.79953833333333
file name : Image_10042023125145980.png
|
2023-04-10 12:51:46.049445 |
163 |
67027760 |
Grey water management — collection infrastructure |
12500 |
Grey water management — collection infrastructure1 |
Completion of work |
-
latitude : 23.815585000000002
Longitude : 87.79941166666667
file name : Image_10042023125142925.png
|
2023-04-10 12:51:42.995736 |
164 |
67027760 |
Grey water management — collection infrastructure |
12500 |
Grey water management — collection infrastructure1 |
Plinth level |
-
latitude : 23.814976666666666
Longitude : 87.80664166666665
file name : Image_19042023100722749.png
|
2023-04-19 10:07:22.809412 |
165 |
67027789 |
Grey water management — collection infrastructure |
12500 |
Grey water management — collection infrastructure1 |
Completion of work |
-
latitude : 23.82274166666667
Longitude : 87.80755666666667
file name : Image_21032023074227427.png
|
2023-03-21 07:42:27.484209 |
166 |
67027941 |
Grey water management — collection infrastructure |
12500 |
Grey water management — collection infrastructure1 |
Completion of work |
-
latitude : 23.82262166666667
Longitude : 87.80756000000001
file name : Image_21032023073611255.png
|
2023-03-21 07:36:11.308707 |
167 |
34652052 |
INSTALATION OF STREET LIGHT FROM SOM TUDU HOUSE TO SOM SOREN |
20000 |
INSTALATION OF STREET LIGHT FROM SOM TUDU HOUSE TO SOM SOREN 1 |
Completion of work |
-
latitude : 23.8147816
Longitude : 87.7970001
file name : Image_26102021134543396.png
|
2021-10-26 13:45:43.5402 |
168 |
56103839 |
Mother and Child Friendly Room at GP office |
300000 |
Mother and Child Friendly Room at GP office1 |
Roof laid |
-
latitude : 23.8148293
Longitude : 87.7971129
file name : Image_18042023145106415.png
|
2023-04-18 14:51:06.469269 |
169 |
56103839 |
Mother and Child Friendly Room at GP office |
300000 |
Mother and Child Friendly Room at GP office1 |
Plinth level |
-
latitude : 23.8148308
Longitude : 87.7971125
file name : Image_18042023144900425.png
|
2023-04-18 14:49:00.482008 |
170 |
56103839 |
Mother and Child Friendly Room at GP office |
300000 |
Mother and Child Friendly Room at GP office1 |
Completion of work |
-
latitude : 23.8148398
Longitude : 87.7971094
file name : Image_18042023144710738.png
|
2023-04-18 14:47:10.790967 |
171 |
34651584 |
INSTALATION OF STREET LIGHT FROM RABILAL MARDI HOUSE TO MALIN MURMU |
20000 |
INSTALATION OF STREET LIGHT FROM RABILAL MARDI HOUSE TO MALIN MURMU1 |
Completion of work |
-
latitude : 23.8147458
Longitude : 87.7969764
file name : Image_26102021134546975.png
|
2021-10-26 13:45:47.13778 |
172 |
34651195 |
INSTALATION OF STREET LIGHT FROM CHAND MURMU HOUSE TO RAMESWAR MARDI |
20000 |
INSTALATION OF STREET LIGHT FROM CHAND MURMU HOUSE TO RAMESWAR MARDI1 |
Completion of work |
-
latitude : 23.8142084
Longitude : 87.7969981
file name : Image_26102021134550291.png
|
2021-10-26 13:45:50.435796 |
173 |
34592388 |
CONSTRUCTION OF CONCRETE ROAD ASHOK MONDAL HOUSE TO SHANTI MURMU HOUSE |
150000 |
CONSTRUCTION OF CONCRETE ROAD ASHOK MONDAL HOUSE TO SHANTI MURMU HOUSE1 |
Completion of work |
-
latitude : 23.814183333333336,23.81406833333333,23.81401166666667,23.81403833333333,23.814048333333336
Longitude : 87.81886333333333,87.81888499999998,87.81903166666667,87.81918666666667,87.81931000000002
file name : Image_06082021134240009.png
|
2021-08-06 13:42:40.111603 |
174 |
34584881 |
CONSTRUCTION OF CONCRETE ROAD FROM SAILA THAPA TO SOMNATH BAURI HOUSE AT HATTALA |
200000 |
CONSTRUCTION OF CONCRETE ROAD FROM SAILA THAPA TO SOMNATH BAURI HOUSE AT HATTALA1 |
Completion of work |
-
latitude : 23.819446666666668,23.819463333333335
Longitude : 87.80712,87.80712166666666
file name : Image_12012022110304633.png
|
2022-01-12 11:03:04.733066 |
175 |
34584881 |
CONSTRUCTION OF CONCRETE ROAD FROM SAILA THAPA TO SOMNATH BAURI HOUSE AT HATTALA |
200000 |
CONSTRUCTION OF CONCRETE ROAD FROM SAILA THAPA TO SOMNATH BAURI HOUSE AT HATTALA1 |
Completion of work |
-
latitude : 23.819396666666663,23.819291666666665,23.81919833333333
Longitude : 87.80710833333333,87.80729333333332,87.80757
file name : Image_06082021131307007.png
|
2021-08-06 13:13:07.102867 |
176 |
56168799 |
Construction Of PCC Road From Raham Sk House to Mayna Sk House at Paschimpara |
190000 |
Construction Of PCC Road From Raham Sk House to Mayna Sk House at Paschimpara1 |
Plinth level |
-
latitude : 23.819045,23.81909166666667,23.819291666666665
Longitude : 87.79765833333335,87.79796499999999,87.79803333333332
file name : Image_14052023122112265.png
|
2023-05-14 12:21:12.337127 |
177 |
34659215 |
CONSTRUCTION OF CONCRETE ROAD FROM ABAICHONA PAR TO NIMAI BAIRAGYA HOUSE AT MONACHITURA |
200000 |
CONSTRUCTION OF CONCRETE ROAD FROM ABAICHONA PAR TO NIMAI BAIRAGYA HOUSE AT MONACHITURA1 |
Completion of work |
-
latitude : 23.810365,23.810365
Longitude : 87.83361333333332,87.83361333333332
file name : Image_02112021105327020.png
|
2021-11-02 10:53:27.150747 |
178 |
34659215 |
CONSTRUCTION OF CONCRETE ROAD FROM ABAICHONA PAR TO NIMAI BAIRAGYA HOUSE AT MONACHITURA |
200000 |
CONSTRUCTION OF CONCRETE ROAD FROM ABAICHONA PAR TO NIMAI BAIRAGYA HOUSE AT MONACHITURA1 |
Completion of work |
-
latitude : 23.810816666666664,23.81054,23.810221666666667,23.810100000000002
Longitude : 87.83374333333335,87.83366,87.83345499999999,87.83342666666667
file name : Image_06082021134244702.png
|
2021-08-06 13:42:44.801383 |
179 |
34548423 |
REPAIRING AND MAINTANANCE OF TUBEWELL UNDER GP AREA |
870000 |
REPAIRING AND MAINTANANCE OF TUBEWELL UNDER GP AREA1 |
Plinth level |
-
latitude : 23.8146876
Longitude : 87.7970293
file name : Image_29052021160529591.png
|
2021-05-29 16:05:29.642827 |
180 |
34548423 |
REPAIRING AND MAINTANANCE OF TUBEWELL UNDER GP AREA |
870000 |
REPAIRING AND MAINTANANCE OF TUBEWELL UNDER GP AREA1 |
Completion of work |
-
latitude : 23.8146687
Longitude : 87.7970212
file name : Image_29052021103049474.png
|
2021-05-29 10:30:49.541704 |
181 |
34548423 |
REPAIRING AND MAINTANANCE OF TUBEWELL UNDER GP AREA |
870000 |
REPAIRING AND MAINTANANCE OF TUBEWELL UNDER GP AREA1 |
Completion of work |
-
latitude : 23.8146687
Longitude : 87.7970212
file name : Image_29052021103107575.png
|
2021-05-29 10:31:07.635156 |
182 |
56120345 |
Instalation Of Solar Lamp at Crematorium Gate at Laghata |
65000 |
Instalation Of Solar Lamp at Crematorium Gate at Laghata1 |
Completion of work |
-
latitude : 23.8096911
Longitude : 87.8044474
file name : Image_13092023122218268.png
|
2023-09-13 12:22:19.657783 |
183 |
34650110 |
CONSTRUCTION OF CONCRETE ROAD FROM BHAGIRATH SAHA HOUSE TO SUBHAS CHNADRA SAHA |
99000 |
CONSTRUCTION OF CONCRETE ROAD FROM BHAGIRATH SAHA HOUSE TO SUBHAS CHNADRA SAHA1 |
Roof laid |
-
latitude : 23.814815,23.81516166666667
Longitude : 87.82265000000001,87.82275166666668
file name : Image_08012021105031967.png
|
2021-01-08 10:50:32.050942 |
184 |
34650110 |
CONSTRUCTION OF CONCRETE ROAD FROM BHAGIRATH SAHA HOUSE TO SUBHAS CHNADRA SAHA |
99000 |
CONSTRUCTION OF CONCRETE ROAD FROM BHAGIRATH SAHA HOUSE TO SUBHAS CHNADRA SAHA1 |
Plinth level |
-
latitude : 23.814815,23.815150000000003
Longitude : 87.82263833333333,87.82278333333333
file name : Image_31122020144606259.png
|
2020-12-31 14:46:06.334425 |
185 |
34649432 |
CONSTRUCTION OF CONCRETE ROAD FROM GITA MONDAL HOUSE TO JAHARLAL MONDAL HOUSE AT LAGHATA |
69300 |
CONSTRUCTION OF CONCRETE ROAD FROM GITA MONDAL HOUSE TO JAHARLAL MONDAL HOUSE AT LAGHATA1 |
Plinth level |
-
latitude : 23.8144432,23.81415,23.814108333333333
Longitude : 87.821844,87.82159500000002,87.82161666666667
file name : Image_08012021110039787.png
|
2021-01-08 11:00:39.856312 |
186 |
34649432 |
CONSTRUCTION OF CONCRETE ROAD FROM GITA MONDAL HOUSE TO JAHARLAL MONDAL HOUSE AT LAGHATA |
69300 |
CONSTRUCTION OF CONCRETE ROAD FROM GITA MONDAL HOUSE TO JAHARLAL MONDAL HOUSE AT LAGHATA1 |
Completion of work |
-
latitude : 23.8144144,23.814151666666664,23.814121666666665
Longitude : 87.8218625,87.82161833333333,87.82164499999999
file name : Image_31122020144230731.png
|
2020-12-31 14:42:30.814156 |
187 |
34675749 |
CONSTRUCTION OF CONCRETE DRAIN WITH COVER SLABE FROM SOMNATH BAURI HOUSE TO DIGHI PUKUR AT HATTALA |
140000 |
CONSTRUCTION OF CONCRETE DRAIN WITH COVER SLABE FROM SOMNATH BAURI HOUSE TO DIGHI PUKUR AT HATTALA1 |
Plinth level |
-
latitude : 23.8147664,23.8147664
Longitude : 87.7970896,87.7970896
file name : Image_17122021142723757.png
|
2021-12-17 14:27:23.864086 |
188 |
34676932 |
INSTALATION OF STREET LIGHT FROM SASTHI HEMRAM HOUSE TO SOM CHORE |
20000 |
INSTALATION OF STREET LIGHT FROM SASTHI HEMRAM HOUSE TO SOM CHORE1 |
Completion of work |
-
latitude : 23.814253333333333
Longitude : 87.79750333333335
file name : Image_26102021124454735.png
|
2021-10-26 12:44:54.885663 |
189 |
39063449 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA |
300000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA1 |
Plinth level |
-
latitude : 23.8153606,23.816841666666665
Longitude : 87.7968215,87.80707666666667
file name : Image_28092021121758961.png
|
2021-09-28 12:17:59.05098 |
190 |
39063449 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA |
300000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA1 |
Plinth level |
-
latitude : 23.816828333333333,23.81927333333333
Longitude : 87.80087833333333,87.80000166666666
file name : Image_25092021093317945.png
|
2021-09-25 09:33:18.065677 |
191 |
39063449 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA |
300000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT T PARA1 |
Completion of work |
-
latitude : 23.819291666666665,23.819290000000002
Longitude : 87.80005666666666,87.80005333333332
file name : Image_09092021095431456.png
|
2021-09-09 09:54:31.597674 |
192 |
34605923 |
CONSTRUCTION OF CONCRETE ROAD FROM JITEN SARDAR TO SUBHAS JHA |
70000 |
CONSTRUCTION OF CONCRETE ROAD FROM JITEN SARDAR TO SUBHAS JHA 1 |
Plinth level |
-
latitude : 23.8148468,23.8148488
Longitude : 87.7972088,87.7972113
file name : Image_07032022115318498.png
|
2022-03-07 11:53:18.634443 |
193 |
34605923 |
CONSTRUCTION OF CONCRETE ROAD FROM JITEN SARDAR TO SUBHAS JHA |
70000 |
CONSTRUCTION OF CONCRETE ROAD FROM JITEN SARDAR TO SUBHAS JHA 1 |
Completion of work |
-
latitude : 23.817870000000003,23.817921666666667,23.817864999999998,23.81788166666667
Longitude : 87.80375666666666,87.80394166666669,87.80420666666666,87.80419333333333
file name : Image_06082021130738135.png
|
2021-08-06 13:07:38.240844 |
194 |
34596256 |
CONSTRUCTION OF CONCRETE ROAD FROM ASISH ROOJ HOUSE TO MANAS KR CHAKRABORTY HOUSE AT BABUPARA |
120000 |
CONSTRUCTION OF CONCRETE ROAD FROM ASISH ROOJ HOUSE TO MANAS KR CHAKRABORTY HOUSE AT BABUPARA1 |
Completion of work |
-
latitude : 23.817933333333333,23.817943333333332,23.817978333333333,23.817921666666667
Longitude : 87.80377833333333,87.80382166666668,87.80391999999999,87.80417666666666
file name : Image_25092021095313532.png
|
2021-09-25 09:53:13.649355 |
195 |
34676101 |
STREET LIGT FROM PURBA DAS PARA TO PASCHIM DAS PARA |
100000 |
STREET LIGT FROM PURBA DAS PARA TO PASCHIM DAS PARA1 |
Completion of work |
-
latitude : 23.8144232
Longitude : 87.7972263
file name : Image_26102021124354893.png
|
2021-10-26 12:43:55.019649 |
196 |
34676101 |
STREET LIGT FROM PURBA DAS PARA TO PASCHIM DAS PARA |
100000 |
STREET LIGT FROM PURBA DAS PARA TO PASCHIM DAS PARA1 |
Completion of work |
-
latitude : 23.8145876
Longitude : 87.7971789
file name : Image_10102021081946331.png
|
2021-10-10 08:19:46.528298 |
197 |
34676101 |
STREET LIGT FROM PURBA DAS PARA TO PASCHIM DAS PARA |
100000 |
STREET LIGT FROM PURBA DAS PARA TO PASCHIM DAS PARA1 |
Completion of work |
-
latitude : 23.8144232
Longitude : 87.7972263
file name : Image_26102021124358569.png
|
2021-10-26 12:43:58.686934 |
198 |
34554700 |
MAINTANANCE OF STREET LIGHT UNDER GP AREA |
200000 |
MAINTANANCE OF STREET LIGHT UNDER GP AREA1 |
Completion of work |
-
latitude : 23.8147516
Longitude : 87.7969674
file name : Image_29052021103036493.png
|
2021-05-29 10:30:36.569749 |
199 |
34554700 |
MAINTANANCE OF STREET LIGHT UNDER GP AREA |
200000 |
MAINTANANCE OF STREET LIGHT UNDER GP AREA1 |
Plinth level |
-
latitude : 23.814739
Longitude : 87.7969738
file name : Image_29052021160753484.png
|
2021-05-29 16:07:53.538125 |
200 |
34554700 |
MAINTANANCE OF STREET LIGHT UNDER GP AREA |
200000 |
MAINTANANCE OF STREET LIGHT UNDER GP AREA1 |
Completion of work |
-
latitude : 23.8147418
Longitude : 87.7969635
file name : Image_29052021103045975.png
|
2021-05-29 10:30:46.040582 |
201 |
34554700 |
MAINTANANCE OF STREET LIGHT UNDER GP AREA |
200000 |
MAINTANANCE OF STREET LIGHT UNDER GP AREA1 |
Completion of work |
-
latitude : 23.8147418
Longitude : 87.7969635
file name : Image_29052021103103590.png
|
2021-05-29 10:31:03.653263 |
202 |
34649071 |
CONSTRUCTION OF CONCRETE ROAD FROM SOM MURMU HOUSE TO CHAMPA MURMU HOUSE AT LAGHATA |
200000 |
CONSTRUCTION OF CONCRETE ROAD FROM SOM MURMU HOUSE TO CHAMPA MURMU HOUSE AT LAGHATA1 |
Completion of work |
-
latitude : 23.807241666666663,23.807565,23.80777666666667,23.807891666666666,23.808203333333335,23.808228333333332,23.808651666666666
Longitude : 87.81702333333332,87.81678666666667,87.81656333333333,87.81648500000001,87.81663333333333,87.81664166666665,87.81682500000001
file name : Image_15072021123700203.png
|
2021-07-15 12:37:00.296648 |
203 |
39063569 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT GOB P.DAS PARA |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT GOB P.DAS PARA1 |
Roof laid |
-
latitude : 23.8147626,23.8147609
Longitude : 87.7971158,87.7971191
file name : Image_08102021124654363.png
|
2021-10-08 12:46:54.481965 |
204 |
39063569 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT GOB P.DAS PARA |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT GOB P.DAS PARA1 |
Plinth level |
-
latitude : 23.8147627,23.8147627
Longitude : 87.7971135,87.7971135
file name : Image_08102021124103360.png
|
2021-10-08 12:41:03.467699 |
205 |
39063569 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT GOB P.DAS PARA |
250000 |
INST OF MINI SUB MERSIBLE WITH TANK AND PIPELINE FOR DRINKING WATER AT GOB P.DAS PARA1 |
Completion of work |
-
latitude : 23.8147607,23.8147607
Longitude : 87.7971106,87.7971106
file name : Image_08102021123132250.png
|
2021-10-08 12:31:32.356777 |
206 |
34572343 |
CONSTRUCTION OF SARBAJANIN BATHING GHAT AT BAJE PUKUR UNDER PASCHIMKADIPUR |
150000 |
CONSTRUCTION OF SARBAJANIN BATHING GHAT AT BAJE PUKUR UNDER PASCHIMKADIPUR1 |
Plinth level |
-
latitude : 23.792756666666666
Longitude : 87.80382499999999
file name : Image_30052021120836109.png
|
2021-05-30 12:08:36.180905 |
207 |
34572343 |
CONSTRUCTION OF SARBAJANIN BATHING GHAT AT BAJE PUKUR UNDER PASCHIMKADIPUR |
150000 |
CONSTRUCTION OF SARBAJANIN BATHING GHAT AT BAJE PUKUR UNDER PASCHIMKADIPUR1 |
Roof laid |
-
latitude : 23.792768333333335
Longitude : 87.80384333333335
file name : Image_30052021121342921.png
|
2021-05-30 12:13:42.967317 |
208 |
34572343 |
CONSTRUCTION OF SARBAJANIN BATHING GHAT AT BAJE PUKUR UNDER PASCHIMKADIPUR |
150000 |
CONSTRUCTION OF SARBAJANIN BATHING GHAT AT BAJE PUKUR UNDER PASCHIMKADIPUR1 |
Completion of work |
-
latitude : 23.792728333333336
Longitude : 87.80390333333335
file name : Image_29052021162916694.png
|
2021-05-29 16:29:16.769903 |
209 |
56120427 |
Instalation Of Overhead Tank with Pipeline at Natun Para Area |
150000 |
Instalation Of Overhead Tank with Pipeline at Natun Para Area1 |
Completion of work |
-
latitude : 23.812589,23.812589
Longitude : 87.8060007,87.8060007
file name : Image_09062023083730932.png
|
2023-06-09 08:37:30.998013 |
210 |
56118688 |
Instalation of Submiersible With Pipe Line for Community at Srilikhari Par at Thakurpara |
150000 |
Instalation of Submiersible With Pipe Line for Community at Srilikhari Par at Thakurpara1 |
Plinth level |
-
latitude : 23.81936166666667,23.819340000000004
Longitude : 87.80009999999999,87.80007333333333
file name : Image_30112023115438362.png
|
2023-11-30 11:54:38.431585 |
211 |
56118688 |
Instalation of Submiersible With Pipe Line for Community at Srilikhari Par at Thakurpara |
150000 |
Instalation of Submiersible With Pipe Line for Community at Srilikhari Par at Thakurpara1 |
Completion of work |
-
latitude : 23.79067,23.790646666666664
Longitude : 87.80447000000001,87.80449500000002
file name : Image_09062023091143447.png
|
2023-06-09 09:11:43.513219 |
212 |
56155172 |
Repairing Of PCC Road From Rabi Prasad Sarkar House to Kali Tala at Babupara |
150000 |
Repairing Of PCC Road From Rabi Prasad Sarkar House to Kali Tala at Babupara1 |
Completion of work |
-
latitude : 23.8113268,23.8113268
Longitude : 87.7973567,87.7973567
file name : Image_09062023093612037.png
|
2023-06-09 09:36:12.10798 |
213 |
56169881 |
Construction Of PCC Road From Sub Centre to Mukhgnitala at Monachitura |
140000 |
Construction Of PCC Road From Sub Centre to Mukhgnitala at Monachitura1 |
Completion of work |
-
latitude : 23.806570000000004,23.80656333333333,23.80655
Longitude : 87.80015,87.80014833333334,87.80013666666667
file name : Image_09062023093001295.png
|
2023-06-09 09:30:01.359374 |
214 |
56118392 |
Construction & Maintenance Of Creametorium Shed with Floor at Paschimkadipur |
75000 |
Construction & Maintenance Of Creametorium Shed with Floor at Paschimkadipur 1 |
Completion of work |
-
latitude : 23.790574999999997
Longitude : 87.80467333333333
file name : Image_09062023090548456.png
|
2023-06-09 09:05:48.521281 |
215 |
56168836 |
Construction Of PCC Road From Tutul Das House to Ramu Dhibar House at Sandipan |
70000 |
Construction Of PCC Road From Tutul Das House to Ramu Dhibar House at Sandipan1 |
Plinth level |
-
latitude : 23.816141666666667,23.816263333333335
Longitude : 87.80613333333334,87.80598499999999
file name : Image_27122023144604375.png
|
2023-12-27 14:46:04.462922 |
216 |
56168836 |
Construction Of PCC Road From Tutul Das House to Ramu Dhibar House at Sandipan |
70000 |
Construction Of PCC Road From Tutul Das House to Ramu Dhibar House at Sandipan1 |
Plinth level |
-
latitude : 23.8163279,23.8165087,23.81621
Longitude : 87.8058673,87.8058714,87.80628166666665
file name : Image_31082023083439806.png
|
2023-08-31 08:34:39.891504 |
217 |
56168836 |
Construction Of PCC Road From Tutul Das House to Ramu Dhibar House at Sandipan |
70000 |
Construction Of PCC Road From Tutul Das House to Ramu Dhibar House at Sandipan1 |
Completion of work |
-
latitude : 23.816108333333332,23.816118333333332
Longitude : 87.80654333333332,87.80641833333333
file name : Image_08062023123316535.png
|
2023-06-08 12:33:16.606825 |
218 |
56168776 |
Construction Of PCC Drain With Cover and Soak Pith From Arun Das House to Sastitala at Gobindopur |
150000 |
Construction Of PCC Drain With Cover and Soak Pith From Arun Das House to Sastitala at Gobindopur 1 |
Plinth level |
-
latitude : 23.816305000000003,23.816300000000002,23.81638666666667,23.816435000000002,23.816489999999998,23.816486666666666
Longitude : 87.834045,87.83405333333333,87.83405166666668,87.83385166666667,87.83370500000001,87.83369666666667
file name : Image_29082023114302191.png
|
2023-08-29 11:43:02.273889 |
219 |
56168776 |
Construction Of PCC Drain With Cover and Soak Pith From Arun Das House to Sastitala at Gobindopur |
150000 |
Construction Of PCC Drain With Cover and Soak Pith From Arun Das House to Sastitala at Gobindopur 1 |
Completion of work |
-
latitude : 23.816458333333337,23.816465
Longitude : 87.834095,87.83408333333334
file name : Image_05062023115057088.png
|
2023-06-05 11:50:57.149122 |
220 |
56155194 |
Installation Of Street Light From Tarun Chakraborty House to Parbati Shankar School Via Kundu Steel |
150000 |
Installation Of Street Light From Tarun Chakraborty House to Parbati Shankar School Via Kundu Steel 1 |
Completion of work |
-
latitude : 23.8101797
Longitude : 87.8041716
file name : Image_09062023085620144.png
|
2023-06-09 08:56:20.216516 |
221 |
56155181 |
Construction Of PCC Drain With Cover From Apu Sarkar House to Cannel Office at Taramadanga |
250000 |
Construction Of PCC Drain With Cover From Apu Sarkar House to Cannel Office at Taramadanga1 |
Plinth level |
-
latitude : 23.8133462,23.813326666666665,23.81326333333333,23.8132454,23.8132454
Longitude : 87.806313,87.80660833333334,87.80707166666667,87.8080571,87.8080571
file name : Image_29082023114305241.png
|
2023-08-29 11:43:05.326548 |
222 |
56155181 |
Construction Of PCC Drain With Cover From Apu Sarkar House to Cannel Office at Taramadanga |
250000 |
Construction Of PCC Drain With Cover From Apu Sarkar House to Cannel Office at Taramadanga1 |
Plinth level |
-
latitude : 23.813375,23.8133672,23.8133672,23.813382
Longitude : 87.8063438,87.8063393,87.8063393,87.8063464
file name : Image_14062023085406760.png
|
2023-06-14 08:54:07.305503 |
223 |
56155181 |
Construction Of PCC Drain With Cover From Apu Sarkar House to Cannel Office at Taramadanga |
250000 |
Construction Of PCC Drain With Cover From Apu Sarkar House to Cannel Office at Taramadanga1 |
Completion of work |
-
latitude : 23.813343333333332,23.81333833333333
Longitude : 87.80643666666668,87.80646666666668
file name : Image_09062023083525053.png
|
2023-06-09 08:35:25.112569 |
224 |
56168761 |
Construction Of PCC Road From Sagar Das House to Basudeb Das Poultry Farm at Gobindopur |
190000 |
Construction Of PCC Road From Sagar Das House to Basudeb Das Poultry Farm at Gobindopur1 |
Plinth level |
-
latitude : 23.81722666666667,23.817551666666667,23.817828333333335
Longitude : 87.83369333333333,87.83384166666669,87.83396666666667
file name : Image_22062023121647378.png
|
2023-06-22 12:16:47.486469 |
225 |
56168761 |
Construction Of PCC Road From Sagar Das House to Basudeb Das Poultry Farm at Gobindopur |
190000 |
Construction Of PCC Road From Sagar Das House to Basudeb Das Poultry Farm at Gobindopur1 |
Completion of work |
-
latitude : 23.817330000000002,23.817380000000004
Longitude : 87.833775,87.83378666666667
file name : Image_05062023114844235.png
|
2023-06-05 11:48:44.324744 |
226 |
56168942 |
Installation Of Submersible Providing Safe Drinking Water of Dhibar Para Manashatala at Sandipan |
100000 |
Installation Of Submersible Providing Safe Drinking Water of Dhibar Para Manashatala at Sandipan1 |
Roof laid |
-
latitude : 23.81623833333333,23.816231666666667
Longitude : 87.804745,87.80475999999999
file name : Image_22062023100039590.png
|
2023-06-22 10:00:39.659632 |
227 |
56168942 |
Installation Of Submersible Providing Safe Drinking Water of Dhibar Para Manashatala at Sandipan |
100000 |
Installation Of Submersible Providing Safe Drinking Water of Dhibar Para Manashatala at Sandipan1 |
Plinth level |
-
latitude : 23.816264999999998,23.816255
Longitude : 87.80476166666668,87.80481333333334
file name : Image_16062023120132054.png
|
2023-06-16 12:01:32.132731 |
228 |
56168942 |
Installation Of Submersible Providing Safe Drinking Water of Dhibar Para Manashatala at Sandipan |
100000 |
Installation Of Submersible Providing Safe Drinking Water of Dhibar Para Manashatala at Sandipan1 |
Completion of work |
-
latitude : 23.81629666666667,23.816300000000002
Longitude : 87.80489333333335,87.80477666666665
file name : Image_09062023082912084.png
|
2023-06-09 08:29:12.161588 |
229 |
56118643 |
Construction Of PCC Drain With Cover From Bikash Rajak Shoap to Back Side of Dharmarajtala at Mahugr |
150000 |
Construction Of PCC Drain With Cover From Bikash Rajak Shoap to Back Side of Dharmarajtala at Mahugr1 |
Plinth level |
-
latitude : 23.8212505,23.82082833333333
Longitude : 87.8059077,87.80562833333333
file name : Image_22062023101506983.png
|
2023-06-22 10:15:07.052425 |
230 |
56118643 |
Construction Of PCC Drain With Cover From Bikash Rajak Shoap to Back Side of Dharmarajtala at Mahugr |
150000 |
Construction Of PCC Drain With Cover From Bikash Rajak Shoap to Back Side of Dharmarajtala at Mahugr1 |
Completion of work |
-
latitude : 23.821239999999996,23.821199999999997
Longitude : 87.80575833333333,87.80575166666668
file name : Image_05062023121657028.png
|
2023-06-05 12:16:57.102721 |
231 |
56118715 |
Instalation of Submiersible With Pipe Line for Community at Phultala Para at Thakurpara |
150000 |
Instalation of Submiersible With Pipe Line for Community at Phultala Para at Thakurpara1 |
Plinth level |
-
latitude : 23.821543333333338,23.821553333333334
Longitude : 87.80940166666666,87.80938499999999
file name : Image_22062023100941940.png
|
2023-06-22 10:09:42.010468 |
232 |
56118715 |
Instalation of Submiersible With Pipe Line for Community at Phultala Para at Thakurpara |
150000 |
Instalation of Submiersible With Pipe Line for Community at Phultala Para at Thakurpara1 |
Completion of work |
-
latitude : 23.790694999999996,23.79069833333333
Longitude : 87.80447000000001,87.80444833333334
file name : Image_09062023091332983.png
|
2023-06-09 09:13:33.050871 |
233 |
56169854 |
Sinking Of Tube Well Providing Safe Drinking Water Of Pradip Thander House at Sandipan |
50000 |
Sinking Of Tube Well Providing Safe Drinking Water Of Pradip Thander House at Sandipan1 |
Plinth level |
-
latitude : 23.81727
Longitude : 87.80794666666667
file name : Image_22062023100456360.png
|
2023-06-22 10:04:56.479517 |
234 |
56169854 |
Sinking Of Tube Well Providing Safe Drinking Water Of Pradip Thander House at Sandipan |
50000 |
Sinking Of Tube Well Providing Safe Drinking Water Of Pradip Thander House at Sandipan1 |
Completion of work |
-
latitude : 23.81628
Longitude : 87.80484499999999
file name : Image_09062023082925327.png
|
2023-06-09 08:29:25.411838 |
235 |
56169907 |
Installation Of Sub Mersible With Tank and Pipeline Providing Safe Drinking Water at Bagdipara Area |
200000 |
Installation Of Sub Mersible With Tank and Pipeline Providing Safe Drinking Water at Bagdipara Area1 |
Plinth level |
-
latitude : 23.813181666666665,23.819073333333336
Longitude : 87.806435,87.82311499999999
file name : Image_14062023090616308.png
|
2023-06-14 09:06:16.647754 |
236 |
56169907 |
Installation Of Sub Mersible With Tank and Pipeline Providing Safe Drinking Water at Bagdipara Area |
200000 |
Installation Of Sub Mersible With Tank and Pipeline Providing Safe Drinking Water at Bagdipara Area1 |
Completion of work |
-
latitude : 23.8132233,23.8132233
Longitude : 87.8061918,87.8061918
file name : Image_09062023083400927.png
|
2023-06-09 08:34:00.985938 |
237 |
56120464 |
Construction of PCC Drain With Cover and Soak Pith From Santwana Hazra House to Likhara Pukur Via S |
200000 |
Construction of PCC Drain With Cover and Soak Pith From Santwana Hazra House to Likhara Pukur Via S1 |
Roof laid |
-
latitude : 23.814483,23.8135367,23.8143209,23.8144177
Longitude : 87.8044574,87.8042897,87.8052421,87.8054576
file name : Image_22062023095608076.png
|
2023-06-22 09:56:08.144725 |
238 |
56120464 |
Construction of PCC Drain With Cover and Soak Pith From Santwana Hazra House to Likhara Pukur Via S |
200000 |
Construction of PCC Drain With Cover and Soak Pith From Santwana Hazra House to Likhara Pukur Via S1 |
Plinth level |
-
latitude : 23.8144787,23.8145004,23.81459166666667,23.8144787,23.8144787
Longitude : 87.8041502,87.8056865,87.80486,87.8041502,87.8041502
file name : Image_08062023123313466.png
|
2023-06-08 12:33:13.534683 |
239 |
56120464 |
Construction of PCC Drain With Cover and Soak Pith From Santwana Hazra House to Likhara Pukur Via S |
200000 |
Construction of PCC Drain With Cover and Soak Pith From Santwana Hazra House to Likhara Pukur Via S1 |
Completion of work |
-
latitude : 23.8136112,23.8144178
Longitude : 87.8042885,87.8054588
file name : Image_05062023114603835.png
|
2023-06-05 11:46:03.909768 |
240 |
56118474 |
Construction Of Community Bathing Ghat Of Dighir Pukur at Hattala |
200000 |
Construction Of Community Bathing Ghat Of Dighir Pukur at Hattala1 |
Plinth level |
-
latitude : 23.8180605
Longitude : 87.8069791
file name : Image_22062023115950736.png
|
2023-06-22 11:59:50.810534 |
241 |
56118474 |
Construction Of Community Bathing Ghat Of Dighir Pukur at Hattala |
200000 |
Construction Of Community Bathing Ghat Of Dighir Pukur at Hattala1 |
Completion of work |
-
latitude : 23.818246666666663
Longitude : 87.806975
file name : Image_09032023123858840.png
|
2023-03-09 12:38:58.90352 |
242 |
56169868 |
Construction of PCC Road From Buri Kalitala to Mada bagdi House at Bakul |
140000 |
Construction of PCC Road From Buri Kalitala to Mada bagdi House at Bakul1 |
Completion of work |
-
latitude : 23.816946666666663,23.816865,23.816766666666663,23.81660833333334,23.816514999999995
Longitude : 87.82392666666668,87.82389166666665,87.82387166666668,87.82374999999999,87.82365999999999
file name : Image_06092023110752424.png
|
2023-09-06 11:07:52.494515 |
243 |
56169868 |
Construction of PCC Road From Buri Kalitala to Mada bagdi House at Bakul |
140000 |
Construction of PCC Road From Buri Kalitala to Mada bagdi House at Bakul1 |
Completion of work |
-
latitude : 23.817005,23.81679,23.816496666666662
Longitude : 87.82375833333332,87.82382000000001,87.82362333333334
file name : Image_27022023133558760.png
|
2023-02-27 13:35:58.827505 |
244 |
56169868 |
Construction of PCC Road From Buri Kalitala to Mada bagdi House at Bakul |
140000 |
Construction of PCC Road From Buri Kalitala to Mada bagdi House at Bakul1 |
Completion of work |
-
latitude : 23.817005,23.81679,23.816496666666662
Longitude : 87.82375833333332,87.82382000000001,87.82362333333334
file name : Image_27022023133623355.png
|
2023-02-27 13:36:23.421366 |
245 |
67991175 |
Construction of new Piped Water Supply schemes |
190000 |
Construction of new Piped Water Supply schemes1 |
Roof laid |
-
latitude : 23.821408333333338
Longitude : 87.79796
file name : Image_23042024102654555.png
|
2024-04-23 10:26:54.62182 |
246 |
67991175 |
Construction of new Piped Water Supply schemes |
190000 |
Construction of new Piped Water Supply schemes1 |
Plinth level |
-
latitude : 23.821506666666664
Longitude : 87.79776333333332
file name : Image_21042024082741697.png
|
2024-04-21 08:27:41.779814 |
247 |
67991175 |
Construction of new Piped Water Supply schemes |
190000 |
Construction of new Piped Water Supply schemes1 |
Completion of work |
-
latitude : 23.82142666666667
Longitude : 87.79787666666668
file name : Image_16042024101407863.png
|
2024-04-16 10:14:07.934981 |
248 |
67998696 |
Drainage Construction |
160000 |
Drainage Construction1 |
Roof laid |
-
latitude : 23.818463333333337
Longitude : 87.82619500000001
file name : Image_11062024121318812.png
|
2024-06-11 12:13:18.89181 |
249 |
67998696 |
Drainage Construction |
160000 |
Drainage Construction1 |
Roof laid |
-
latitude : 23.818513333333332
Longitude : 87.82626
file name : Image_21042024093157893.png
|
2024-04-21 09:31:57.989248 |
250 |
67998696 |
Drainage Construction |
160000 |
Drainage Construction1 |
Plinth level |
-
latitude : 23.818416666666668
Longitude : 87.82621166666668
file name : Image_21042024092937861.png
|
2024-04-21 09:29:37.943334 |
251 |
67998696 |
Drainage Construction |
160000 |
Drainage Construction1 |
Plinth level |
-
latitude : 23.818503333333336
Longitude : 87.82625666666667
file name : Image_18042024100532168.png
|
2024-04-18 10:05:32.244474 |
252 |
67998696 |
Drainage Construction |
160000 |
Drainage Construction1 |
Completion of work |
-
latitude : 23.818446666666667
Longitude : 87.82621666666667
file name : Image_18042024091823187.png
|
2024-04-18 09:18:23.25877 |
253 |
67797500 |
Construction of roads |
130000 |
Construction of roads1 |
Roof laid |
-
latitude : 23.805511666666668,23.805521666666664,23.805616666666666
Longitude : 87.79513666666665,87.79523833333333,87.79484333333333
file name : Image_25062024071406239.png
|
2024-06-25 07:14:06.306908 |
254 |
67797500 |
Construction of roads |
130000 |
Construction of roads1 |
Plinth level |
-
latitude : 23.8105856,23.8105856
Longitude : 87.7984738,87.7984738
file name : Image_08012024102326148.png
|
2024-01-08 10:23:26.214488 |
255 |
67797500 |
Construction of roads |
130000 |
Construction of roads1 |
Completion of work |
-
latitude : 23.805586666666667,23.80559
Longitude : 87.79505666666667,87.79507
file name : Image_03012024121339093.png
|
2024-01-03 12:13:39.176044 |
256 |
67807670 |
Construction of roads |
250000 |
Construction of roads1 |
Roof laid |
-
latitude : 23.8133983,23.8133983
Longitude : 87.806353,87.806353
file name : Image_11012024144717356.png
|
2024-01-11 14:47:17.436568 |
257 |
67807670 |
Construction of roads |
250000 |
Construction of roads1 |
Plinth level |
-
latitude : 23.814145,23.81411166666667
Longitude : 87.83445166666667,87.83448833333333
file name : Image_09012024130800310.png
|
2024-01-09 13:08:00.402707 |
258 |
67807670 |
Construction of roads |
250000 |
Construction of roads1 |
Completion of work |
-
latitude : 23.814289999999996,23.81428
Longitude : 87.83442333333332,87.83448833333333
file name : Image_02012024131629602.png
|
2024-01-02 13:16:29.709437 |
259 |
67808141 |
Construction of roads |
180000 |
Construction of roads1 |
Roof laid |
-
latitude : 23.8143343,23.8143343
Longitude : 87.8222904,87.8222904
file name : Image_25062024121328834.png
|
2024-06-25 12:13:28.901844 |
260 |
67808141 |
Construction of roads |
180000 |
Construction of roads1 |
Plinth level |
-
latitude : 23.81408666666667,23.81404166666667
Longitude : 87.82232666666665,87.82227833333333
file name : Image_09012024132159008.png
|
2024-01-09 13:21:59.084563 |
261 |
67808141 |
Construction of roads |
180000 |
Construction of roads1 |
Completion of work |
-
latitude : 23.8141,23.81399333333333
Longitude : 87.82221499999999,87.82221166666668
file name : Image_02012024132829942.png
|
2024-01-02 13:28:30.028528 |
262 |
56120375 |
Instalation Of Solar Lamp at Laghata Natun Para |
35000 |
Instalation Of Solar Lamp at Laghata Natun Para 1 |
Roof laid |
-
latitude : 23.811941666666666
Longitude : 87.83901333333333
file name : Image_20122023161538348.png
|
2023-12-20 16:15:38.501966 |
263 |
56120375 |
Instalation Of Solar Lamp at Laghata Natun Para |
35000 |
Instalation Of Solar Lamp at Laghata Natun Para 1 |
Plinth level |
-
latitude : 23.8148161
Longitude : 87.7971312
file name : Image_20122023150806556.png
|
2023-12-20 15:08:06.543043 |
264 |
56120375 |
Instalation Of Solar Lamp at Laghata Natun Para |
35000 |
Instalation Of Solar Lamp at Laghata Natun Para 1 |
Completion of work |
-
latitude : 23.8148166
Longitude : 87.7971186
file name : Image_20122023145418086.png
|
2023-12-20 14:54:18.156989 |
265 |
56120375 |
Instalation Of Solar Lamp at Laghata Natun Para |
35000 |
Instalation Of Solar Lamp at Laghata Natun Para 1 |
Completion of work |
-
latitude : 23.8148133
Longitude : 87.7971283
file name : Image_20122023134706986.png
|
2023-12-20 13:47:07.18982 |
266 |
56120402 |
Instalation Of Solar Lamp at Laghata Football Ground |
65000 |
Instalation Of Solar Lamp at Laghata Football Ground 1 |
Roof laid |
-
latitude : 23.80895666666667
Longitude : 87.84538666666667
file name : Image_20122023161415442.png
|
2023-12-20 16:14:15.53111 |
267 |
56120402 |
Instalation Of Solar Lamp at Laghata Football Ground |
65000 |
Instalation Of Solar Lamp at Laghata Football Ground 1 |
Plinth level |
-
latitude : 23.8148129
Longitude : 87.7971272
file name : Image_20122023150924655.png
|
2023-12-20 15:09:24.7456 |
268 |
56120402 |
Instalation Of Solar Lamp at Laghata Football Ground |
65000 |
Instalation Of Solar Lamp at Laghata Football Ground 1 |
Completion of work |
-
latitude : 23.8148133
Longitude : 87.7971283
file name : Image_20122023135000364.png
|
2023-12-20 13:50:00.608749 |
269 |
56116551 |
Construction and Maintenance of LED Street Light and Solar Lighting under GP Area |
99918 |
Construction and Maintenance of LED Street Light and Solar Lighting under GP Area1 |
Completion of work |
-
latitude : 23.8147591
Longitude : 87.7971084
file name : Image_12122023142806678.png
|
2023-12-12 14:28:06.754079 |
270 |
67807269 |
Installation of Solar lights |
175000 |
Installation of Solar lights1 |
Roof laid |
-
latitude : 23.812464999999996
Longitude : 87.83581833333334
file name : Image_20122023164958432.png
|
2023-12-20 16:49:58.578756 |
271 |
67807269 |
Installation of Solar lights |
175000 |
Installation of Solar lights1 |
Plinth level |
-
latitude : 23.814243333333334
Longitude : 87.837075
file name : Image_20122023163756148.png
|
2023-12-20 16:37:56.268265 |
272 |
67807269 |
Installation of Solar lights |
175000 |
Installation of Solar lights1 |
Plinth level |
-
latitude : 23.8148162
Longitude : 87.7971313
file name : Image_20122023145059931.png
|
2023-12-20 14:51:00.023781 |
273 |
67807269 |
Installation of Solar lights |
175000 |
Installation of Solar lights1 |
Completion of work |
-
latitude : 23.8148145
Longitude : 87.7971249
file name : Image_20122023144441028.png
|
2023-12-20 14:44:41.142935 |
274 |
67807269 |
Installation of Solar lights |
175000 |
Installation of Solar lights1 |
Completion of work |
-
latitude : 23.8148145
Longitude : 87.7971314
file name : Image_20122023142701804.png
|
2023-12-20 14:27:01.87409 |
275 |
67807269 |
Installation of Solar lights |
175000 |
Installation of Solar lights1 |
Completion of work |
-
latitude : 23.8148133
Longitude : 87.7971283
file name : Image_20122023142658344.png
|
2023-12-20 14:26:58.483441 |
276 |
56116551 |
Construction and Maintenance of LED Street Light and Solar Lighting under GP Area |
99918 |
Construction and Maintenance of LED Street Light and Solar Lighting under GP Area1 |
Completion of work |
-
latitude : 23.8148133
Longitude : 87.7971283
file name : Image_20122023134957122.png
|
2023-12-20 13:49:57.207656 |
277 |
56116551 |
Construction and Maintenance of LED Street Light and Solar Lighting under GP Area |
99918 |
Construction and Maintenance of LED Street Light and Solar Lighting under GP Area1 |
Completion of work |
-
latitude : 23.814483333333335
Longitude : 87.79694333333333
file name : Image_12122023142628519.png
|
2023-12-12 14:26:28.613472 |
278 |
67795350 |
Repairing and maintenance of roads |
150000 |
Repairing and maintenance of roads1 |
Roof laid |
-
latitude : 23.801851666666668,23.801849999999998,23.801843333333334,23.801846666666666
Longitude : 87.79975833333334,87.79976166666665,87.79977500000001,87.79979333333334
file name : Image_25062024070548582.png
|
2024-06-25 07:05:48.653291 |
279 |
67795350 |
Repairing and maintenance of roads |
150000 |
Repairing and maintenance of roads1 |
Roof laid |
-
latitude : 23.801941666666668,23.801918333333333
Longitude : 87.79971333333333,87.79974666666666
file name : Image_11012024143016934.png
|
2024-01-11 14:30:17.003749 |
280 |
67795350 |
Repairing and maintenance of roads |
150000 |
Repairing and maintenance of roads1 |
Roof laid |
-
latitude : 23.801941666666668,23.801918333333333
Longitude : 87.79971333333333,87.79974666666666
file name : Image_11012024143012037.png
|
2024-01-11 14:30:12.099241 |
281 |
67795350 |
Repairing and maintenance of roads |
150000 |
Repairing and maintenance of roads1 |
Roof laid |
-
latitude : 23.801879999999997,23.801879999999997
Longitude : 87.79971833333333,87.79971833333333
file name : Image_11012024143007581.png
|
2024-01-11 14:30:07.64495 |
282 |
67795350 |
Repairing and maintenance of roads |
150000 |
Repairing and maintenance of roads1 |
Plinth level |
-
latitude : 23.801876666666665,23.801876666666665
Longitude : 87.79973999999999,87.79973999999999
file name : Image_11012024142414616.png
|
2024-01-11 14:24:14.692638 |
283 |
67795350 |
Repairing and maintenance of roads |
150000 |
Repairing and maintenance of roads1 |
Completion of work |
-
latitude : 23.801951666666664,23.801945
Longitude : 87.79956833333333,87.79957
file name : Image_10012024103119175.png
|
2024-01-10 10:31:19.447016 |
284 |
67791724 |
Procurement of Computer |
80000 |
Procurement of Computer1 |
|
-
latitude : 23.8148185
Longitude : 87.797123
file name : Image_08022024153600171.png
|
2024-02-08 15:36:00.255633 |
285 |
67794067 |
Functional Electricity Connection |
250000 |
Functional Electricity Connection1 |
Plinth level |
-
latitude : 23.8148085,23.8148085
Longitude : 87.7971212,87.7971212
file name : Image_08022024153901490.png
|
2024-02-08 15:39:01.564438 |
286 |
67794067 |
Functional Electricity Connection |
250000 |
Functional Electricity Connection1 |
Plinth level |
-
latitude : 23.8148171,23.814341666666664
Longitude : 87.7971228,87.79778499999999
file name : Image_08022024153747062.png
|
2024-02-08 15:37:47.160287 |
287 |
67794067 |
Functional Electricity Connection |
250000 |
Functional Electricity Connection1 |
Completion of work |
-
latitude : 23.8148221,23.8148221
Longitude : 87.7971355,87.7971355
file name : Image_08022024153427605.png
|
2024-02-08 15:34:27.676716 |
288 |
67792251 |
Installation of Web Cam |
30000 |
Installation of Web Cam1 |
|
-
latitude : 23.8148125
Longitude : 87.7971176
file name : Image_08022024153018639.png
|
2024-02-08 15:30:18.708111 |
289 |
67792251 |
Installation of Web Cam |
30000 |
Installation of Web Cam2 |
|
-
latitude : 23.8148196
Longitude : 87.7971115
file name : Image_08022024153100872.png
|
2024-02-08 15:31:00.951476 |
290 |
67792251 |
Installation of Web Cam |
30000 |
Installation of Web Cam3 |
|
-
latitude : 23.8148181
Longitude : 87.7971178
file name : Image_08022024153222660.png
|
2024-02-08 15:32:22.728442 |
291 |
67997134 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste |
70000 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste1 |
|
-
latitude : 23.8148215
Longitude : 87.7971377
file name : Image_08022024152838401.png
|
2024-02-08 15:28:38.483062 |
292 |
67997660 |
Drainage Construction |
60000 |
Drainage Construction1 |
Roof laid |
-
latitude : 23.8135926
Longitude : 87.8041102
file name : Image_21062024115035370.png
|
2024-06-21 11:50:35.434393 |
293 |
67997660 |
Drainage Construction |
60000 |
Drainage Construction1 |
Plinth level |
-
latitude : 23.8134699
Longitude : 87.8041739
file name : Image_02012024121138112.png
|
2024-01-02 12:11:38.180691 |
294 |
67997660 |
Drainage Construction |
60000 |
Drainage Construction1 |
Completion of work |
-
latitude : 23.8135292
Longitude : 87.8040984
file name : Image_12122023115320529.png
|
2023-12-12 11:53:20.607822 |
295 |
67997593 |
Drainage Construction |
123000 |
Drainage Construction1 |
Plinth level |
-
latitude : 23.8147892
Longitude : 87.7971296
file name : Image_16012024134943728.png
|
2024-01-16 13:49:43.809539 |
296 |
67997593 |
Drainage Construction |
123000 |
Drainage Construction1 |
Completion of work |
-
latitude : 23.8142815
Longitude : 87.8052775
file name : Image_12122023115939949.png
|
2023-12-12 11:59:40.024022 |
297 |
67997718 |
Drainage Construction |
60000 |
Drainage Construction1 |
Plinth level |
-
latitude : 23.8182095
Longitude : 87.8032326
file name : Image_02012024124310094.png
|
2024-01-02 12:43:10.156704 |
298 |
67997718 |
Drainage Construction |
60000 |
Drainage Construction1 |
Completion of work |
-
latitude : 23.8182242
Longitude : 87.8032725
file name : Image_12122023122521739.png
|
2023-12-12 12:25:21.803582 |
299 |
67998058 |
Drainage Construction |
280000 |
Drainage Construction1 |
Roof laid |
-
latitude : 23.8149276
Longitude : 87.7971333
file name : Image_26062024110816397.png
|
2024-06-26 11:08:16.484247 |
300 |
67998058 |
Drainage Construction |
280000 |
Drainage Construction1 |
Roof laid |
-
latitude : 23.811306666666663
Longitude : 87.80940333333335
file name : Image_25062024072831178.png
|
2024-06-25 07:28:31.247005 |
301 |
67998058 |
Drainage Construction |
280000 |
Drainage Construction1 |
Plinth level |
-
latitude : 23.8111553
Longitude : 87.8055622
file name : Image_02012024114631883.png
|
2024-01-02 11:46:31.9601 |
302 |
67998058 |
Drainage Construction |
280000 |
Drainage Construction1 |
Completion of work |
-
latitude : 23.811351666666663
Longitude : 87.80938499999999
file name : Image_17122023112640782.png
|
2023-12-17 11:26:40.857065 |
303 |
67997911 |
Drainage Construction |
230000 |
Drainage Construction1 |
Completion of work |
-
latitude : 23.8133021
Longitude : 87.8082025
file name : Image_12122023121423715.png
|
2023-12-12 12:14:23.805843 |
304 |
88626953 |
Constuction of CC Road from Anowar Mirdhya House to Bitumin Road at Mahugram |
150000 |
Constuction of CC Road from Anowar Mirdhya House to Bitumin Road at Mahugram1 |
Completion of work |
-
latitude : 23.8213115,23.8213115,23.8213115,23.82096166666667
Longitude : 87.7989004,87.7989004,87.7989004,87.79867166666666
file name : Image_27122023142151244.png
|
2023-12-27 14:21:51.328724 |
305 |
88626886 |
Creation of drainage channel for management of grey water |
115000 |
Creation of drainage channel for management of grey water1 |
Plinth level |
-
latitude : 23.8133847
Longitude : 87.8063307
file name : Image_16012024134123158.png
|
2024-01-16 13:41:23.224209 |
306 |
88626886 |
Creation of drainage channel for management of grey water |
115000 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 23.8133819
Longitude : 87.8063471
file name : Image_27122023144615056.png
|
2023-12-27 14:46:15.133428 |
307 |
88626886 |
Creation of drainage channel for management of grey water |
115000 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 23.8133819
Longitude : 87.8063471
file name : Image_27122023144608303.png
|
2023-12-27 14:46:08.377788 |
308 |
88626227 |
Constuction of CC Road from Suman Das House to Kanthal Dhibar House at Sandipan |
95000 |
Constuction of CC Road from Suman Das House to Kanthal Dhibar House at Sandipan1 |
Roof laid |
-
latitude : 23.8133983,23.8133983
Longitude : 87.806353,87.806353
file name : Image_11012024144512909.png
|
2024-01-11 14:45:12.982849 |
309 |
88626227 |
Constuction of CC Road from Suman Das House to Kanthal Dhibar House at Sandipan |
95000 |
Constuction of CC Road from Suman Das House to Kanthal Dhibar House at Sandipan1 |
Plinth level |
-
latitude : 23.8145048,23.8145048
Longitude : 87.8059938,87.8059938
file name : Image_11012024074552210.png
|
2024-01-11 07:45:52.274236 |
310 |
88626227 |
Constuction of CC Road from Suman Das House to Kanthal Dhibar House at Sandipan |
95000 |
Constuction of CC Road from Suman Das House to Kanthal Dhibar House at Sandipan1 |
Completion of work |
-
latitude : 23.816035000000003,23.81604666666666
Longitude : 87.80660333333331,87.80660666666667
file name : Image_11012024073953880.png
|
2024-01-11 07:39:53.943024 |
311 |
88626112 |
Upgradation of Gram Panchayat Market Complex Up Stair Mouza- Mahugram, JL.No-94, Plot-1115 |
190000 |
Upgradation of Gram Panchayat Market Complex Up Stair Mouza- Mahugram, JL.No-94, Plot-11151 |
Plinth level |
-
latitude : 23.8149406
Longitude : 87.796938
file name : Image_27122023124551178.png
|
2023-12-27 12:45:51.240799 |
312 |
88626112 |
Upgradation of Gram Panchayat Market Complex Up Stair Mouza- Mahugram, JL.No-94, Plot-1115 |
190000 |
Upgradation of Gram Panchayat Market Complex Up Stair Mouza- Mahugram, JL.No-94, Plot-11151 |
Completion of work |
-
latitude : 23.8147751
Longitude : 87.7971348
file name : Image_27122023123658636.png
|
2023-12-27 12:36:58.700863 |
313 |
67982825 |
Creation of a new source of drinking water |
150000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 23.808709999999998
Longitude : 87.83411
file name : Image_20012024091523272.png
|
2024-01-20 09:15:23.34197 |
314 |
67982825 |
Creation of a new source of drinking water |
150000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 23.808736666666665
Longitude : 87.83409000000002
file name : Image_02012024132152178.png
|
2024-01-02 13:21:52.25616 |
315 |
56168813 |
Construction Of PCC Drain With Cover From Sanu Sk House to Dalim Sk House at Paschimpara |
150000 |
Construction Of PCC Drain With Cover From Sanu Sk House to Dalim Sk House at Paschimpara1 |
Completion of work |
-
latitude : 23.818013333333337,23.817953333333335,23.817968333333337,23.817979999999995,23.8183,23.818309999999997
Longitude : 87.79719666666666,87.79691499999998,87.79683833333333,87.796765,87.79680000000002,87.79657
file name : Image_07092023095824611.png
|
2023-09-07 09:58:24.702044 |
316 |
67790906 |
Repairing/Construction of Building |
150000 |
Repairing/Construction of Building1 |
Plinth level |
-
latitude : 23.8147744
Longitude : 87.7971312
file name : Image_27122023125426332.png
|
2023-12-27 12:54:26.403018 |
317 |
67790906 |
Repairing/Construction of Building |
150000 |
Repairing/Construction of Building1 |
Completion of work |
-
latitude : 23.815105000000003
Longitude : 87.79707666666667
file name : Image_27122023090356922.png
|
2023-12-27 09:03:56.991199 |
318 |
56168845 |
Construction Of PCC Road From Asish Dutta House to Bivas Patra House at Sandipan |
50000 |
Construction Of PCC Road From Asish Dutta House to Bivas Patra House at Sandipan1 |
Completion of work |
-
latitude : 23.81733166666667,23.817326666666666
Longitude : 87.80822666666667,87.80824166666667
file name : Image_04012024104638477.png
|
2024-01-04 10:46:38.552937 |
319 |
56168928 |
Construction Of PCC Drain With Cover From Bapi Saha House to Deb Kumar Chandra House at Sandipan |
120000 |
Construction Of PCC Drain With Cover From Bapi Saha House to Deb Kumar Chandra House at Sandipan1 |
Completion of work |
-
latitude : 23.8164766,23.8164495
Longitude : 87.8058126,87.805835
file name : Image_17122023102616069.png
|
2023-12-17 10:26:16.135897 |
320 |
67882116 |
Installation of Tubewell |
822490 |
Installation of Tubewell1 |
Plinth level |
-
latitude : 23.814959999999996
Longitude : 87.79708333333335
file name : Image_29122023123725484.png
|
2023-12-29 12:37:25.561873 |
321 |
67882116 |
Installation of Tubewell |
822490 |
Installation of Tubewell1 |
Plinth level |
-
latitude : 23.8148173
Longitude : 87.7971219
file name : Image_18122023125905130.png
|
2023-12-18 12:59:05.201802 |
322 |
67882116 |
Installation of Tubewell |
822490 |
Installation of Tubewell1 |
Completion of work |
-
latitude : 23.8149411
Longitude : 87.7969487
file name : Image_15122023131520170.png
|
2023-12-15 13:15:20.250996 |
323 |
67882116 |
Installation of Tubewell |
822490 |
Installation of Tubewell1 |
Completion of work |
-
latitude : 23.8147817
Longitude : 87.7971315
file name : Image_16102023142307308.png
|
2023-10-16 14:23:07.370805 |
324 |
67817139 |
Construction of RAMS |
200000 |
Construction of RAMS1 |
Roof laid |
-
latitude : 23.821119999999997,23.821126666666668
Longitude : 87.80298166666668,87.80287166666668
file name : Image_21042024083558435.png
|
2024-04-21 08:35:58.506656 |
325 |
67817139 |
Construction of RAMS |
200000 |
Construction of RAMS1 |
Plinth level |
-
latitude : 23.821206666666665,23.8204655
Longitude : 87.80294333333335,87.8023874
file name : Image_04042024120252702.png
|
2024-04-04 12:02:52.778555 |
326 |
67817139 |
Construction of RAMS |
200000 |
Construction of RAMS1 |
Completion of work |
-
latitude : 23.821095,23.821123333333336,23.821123333333336
Longitude : 87.80298333333333,87.80295833333334,87.80295833333334
file name : Image_13032024123257169.png
|
2024-03-13 12:32:57.235964 |
327 |
67982710 |
Creation of a new source of drinking water |
220000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 23.818876666666664
Longitude : 87.81004166666668
file name : Image_21042024084610744.png
|
2024-04-21 08:46:10.821403 |
328 |
67982710 |
Creation of a new source of drinking water |
220000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 23.81897666666667
Longitude : 87.81002833333332
file name : Image_10042024144851992.png
|
2024-04-10 14:48:52.051499 |
329 |
67982710 |
Creation of a new source of drinking water |
220000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 23.818875000000002
Longitude : 87.81001833333333
file name : Image_10042024142922896.png
|
2024-04-10 14:29:22.96913 |
330 |
67997523 |
Drainage Construction |
130000 |
Drainage Construction1 |
Plinth level |
-
latitude : 23.81415666666667
Longitude : 87.79611666666666
file name : Image_05062024084906425.png
|
2024-06-05 08:49:06.497668 |
331 |
67997523 |
Drainage Construction |
130000 |
Drainage Construction1 |
Completion of work |
-
latitude : 23.821635
Longitude : 87.802615
file name : Image_21042024083300873.png
|
2024-04-21 08:33:00.948969 |
332 |
67998766 |
Drainage Construction |
190000 |
Drainage Construction1 |
Roof laid |
-
latitude : 23.813448333333334
Longitude : 87.83680166666666
file name : Image_25062024121325121.png
|
2024-06-25 12:13:25.197963 |
333 |
67998766 |
Drainage Construction |
190000 |
Drainage Construction1 |
Plinth level |
-
latitude : 23.813543333333335
Longitude : 87.83685500000001
file name : Image_03062024085710724.png
|
2024-06-03 08:57:10.796199 |
334 |
67998766 |
Drainage Construction |
190000 |
Drainage Construction1 |
Completion of work |
-
latitude : 23.813528333333338
Longitude : 87.83686666666667
file name : Image_20042024111438322.png
|
2024-04-20 11:14:38.39276 |
335 |
95445469 |
Construction of roads |
300000 |
Construction of roads1 |
Roof laid |
-
latitude : 23.810975,23.811493333333335,23.811591666666665
Longitude : 87.80202666666668,87.80209333333332,87.80198333333334
file name : Image_25062024072136556.png
|
2024-06-25 07:21:36.620827 |
336 |
95445469 |
Construction of roads |
300000 |
Construction of roads1 |
Roof laid |
-
latitude : 23.8109269,23.8109269
Longitude : 87.8017829,87.8017829
file name : Image_07032024130243536.png
|
2024-03-07 13:02:43.596213 |
337 |
95445469 |
Construction of roads |
300000 |
Construction of roads1 |
Plinth level |
-
latitude : 23.8109357,23.8109495,23.810971,23.810971,23.810971,23.810971,23.811535000000003,23.81157
Longitude : 87.8018136,87.801709,87.8019777,87.8019777,87.8019777,87.8019777,87.80203333333333,87.80204
file name : Image_06032024130033214.png
|
2024-03-06 13:00:33.286036 |
338 |
95445469 |
Construction of roads |
300000 |
Construction of roads1 |
Completion of work |
-
latitude : 23.8103261,23.8103261
Longitude : 87.7970221,87.7970221
file name : Image_06032024125022930.png
|
2024-03-06 12:50:23.028905 |
339 |
67800138 |
Construction of roads |
150000 |
Construction of roads1 |
Plinth level |
-
latitude : 23.823736666666665,23.823736666666665
Longitude : 87.80899333333333,87.80899333333333
file name : Image_09042024104447569.png
|
2024-04-09 10:44:47.638929 |
340 |
67800138 |
Construction of roads |
150000 |
Construction of roads1 |
Completion of work |
-
latitude : 23.823535,23.823525000000004,23.82363,23.823649999999997,23.823600000000003,23.82359,23.823559999999997,23.82354666666667
Longitude : 87.80914666666668,87.80915000000002,87.80916166666665,87.80900500000001,87.80884333333333,87.80873500000001,87.80871833333335,87.80857166666668
file name : Image_13032024114215292.png
|
2024-03-13 11:42:15.357937 |
341 |
67805495 |
Construction of roads |
150000 |
Construction of roads1 |
Plinth level |
-
latitude : 23.81577333333333,23.81574333333333
Longitude : 87.80745666666665,87.80745333333334
file name : Image_28032024094643341.png
|
2024-03-28 09:46:43.411037 |
342 |
67805495 |
Construction of roads |
150000 |
Construction of roads1 |
Completion of work |
-
latitude : 23.815306666666668,23.815475,23.815501666666666,23.815648333333336,23.815753333333337,23.815823333333334,23.81601333333333
Longitude : 87.807395,87.80744000000001,87.80744166666666,87.80746666666667,87.80747000000001,87.80750666666667,87.80754166666665
file name : Image_13032024120918046.png
|
2024-03-13 12:09:18.116083 |
343 |
67817988 |
Construction of RAMPS |
200000 |
Construction of RAMPS1 |
Roof laid |
-
latitude : 23.8144795,23.8144795
Longitude : 87.820701,87.820701
file name : Image_21042024104312327.png
|
2024-04-21 10:43:12.400778 |
344 |
67817988 |
Construction of RAMPS |
200000 |
Construction of RAMPS1 |
Plinth level |
-
latitude : 23.795718333333337,23.79568
Longitude : 87.79912166666666,87.79922833333333
file name : Image_08042024093625360.png
|
2024-04-08 09:36:25.428495 |
345 |
67817988 |
Construction of RAMPS |
200000 |
Construction of RAMPS1 |
Completion of work |
-
latitude : 23.795626666666667,23.795621666666662,23.795613333333336
Longitude : 87.79909166666667,87.79908833333333,87.79908833333333
file name : Image_13032024130116013.png
|
2024-03-13 13:01:16.077274 |
346 |
67805243 |
Electricity/Solar Power Installation |
150000 |
Electricity/Solar Power Installation1 |
Roof laid |
-
latitude : 23.814513333333334
Longitude : 87.79765
file name : Image_30062024105608238.png
|
2024-06-30 10:56:08.297012 |
347 |
67805243 |
Electricity/Solar Power Installation |
150000 |
Electricity/Solar Power Installation1 |
Plinth level |
-
latitude : 23.814498333333336
Longitude : 87.79775833333333
file name : Image_25062024075858932.png
|
2024-06-25 07:58:59.006475 |
348 |
67805243 |
Electricity/Solar Power Installation |
150000 |
Electricity/Solar Power Installation1 |
Completion of work |
-
latitude : 23.814611666666664
Longitude : 87.79768833333334
file name : Image_21062024112835717.png
|
2024-06-21 11:28:35.789043 |
349 |
67804524 |
Electricity connection /Installation of Solar Energy |
100000 |
Electricity connection /Installation of Solar Energy1 |
Roof laid |
-
latitude : 23.8143602
Longitude : 87.7981134
file name : Image_30062024105748685.png
|
2024-06-30 10:57:48.751059 |
350 |
67804524 |
Electricity connection /Installation of Solar Energy |
100000 |
Electricity connection /Installation of Solar Energy1 |
Plinth level |
-
latitude : 23.8143852
Longitude : 87.7981365
file name : Image_25062024075537042.png
|
2024-06-25 07:55:37.115501 |
351 |
67804524 |
Electricity connection /Installation of Solar Energy |
100000 |
Electricity connection /Installation of Solar Energy1 |
Completion of work |
-
latitude : 23.8151401
Longitude : 87.7983278
file name : Image_21062024113143992.png
|
2024-06-21 11:31:44.092946 |
352 |
67804095 |
Electricity connection /Installation of Solar Energy |
60000 |
Electricity connection /Installation of Solar Energy1 |
Roof laid |
-
latitude : 23.814810000000005
Longitude : 87.797845
file name : Image_30062024105855075.png
|
2024-06-30 10:58:55.154947 |
353 |
67804095 |
Electricity connection /Installation of Solar Energy |
60000 |
Electricity connection /Installation of Solar Energy1 |
Plinth level |
-
latitude : 23.814423333333334
Longitude : 87.79911166666668
file name : Image_25062024075413211.png
|
2024-06-25 07:54:13.306376 |
354 |
67804095 |
Electricity connection /Installation of Solar Energy |
60000 |
Electricity connection /Installation of Solar Energy1 |
Completion of work |
-
latitude : 23.814715
Longitude : 87.79817666666668
file name : Image_21062024113321574.png
|
2024-06-21 11:33:21.694436 |
355 |
67804831 |
Electricity/Solar Power Installation |
120000 |
Electricity/Solar Power Installation1 |
Roof laid |
-
latitude : 23.8149293
Longitude : 87.7971365
file name : Image_01072024110445747.png
|
2024-07-01 11:04:45.856681 |
356 |
67804831 |
Electricity/Solar Power Installation |
120000 |
Electricity/Solar Power Installation1 |
Roof laid |
-
latitude : 23.81494
Longitude : 87.79757333333333
file name : Image_30062024110034975.png
|
2024-06-30 11:00:35.036042 |
357 |
67804831 |
Electricity/Solar Power Installation |
120000 |
Electricity/Solar Power Installation1 |
Plinth level |
-
latitude : 23.8134837
Longitude : 87.8050699
file name : Image_25062024074622722.png
|
2024-06-25 07:46:22.798253 |
358 |
67804831 |
Electricity/Solar Power Installation |
120000 |
Electricity/Solar Power Installation1 |
Completion of work |
-
latitude : 23.8134528
Longitude : 87.8050447
file name : Image_21062024113700941.png
|
2024-06-21 11:37:01.076223 |
359 |
67802807 |
Electricity |
190000 |
Electricity1 |
Roof laid |
-
latitude : 23.814912
Longitude : 87.7969421
file name : Image_01072024111005334.png
|
2024-07-01 11:10:05.419302 |
360 |
67802807 |
Electricity |
190000 |
Electricity1 |
Roof laid |
-
latitude : 23.8148448
Longitude : 87.7969375
file name : Image_01072024110924845.png
|
2024-07-01 11:09:24.926785 |
361 |
67802807 |
Electricity |
190000 |
Electricity1 |
Roof laid |
-
latitude : 23.8149954
Longitude : 87.7968444
file name : Image_30062024110200453.png
|
2024-06-30 11:02:00.518447 |
362 |
67802807 |
Electricity |
190000 |
Electricity1 |
Plinth level |
-
latitude : 23.8130843
Longitude : 87.8058655
file name : Image_25062024074517834.png
|
2024-06-25 07:45:17.898636 |
363 |
67802807 |
Electricity |
190000 |
Electricity1 |
Completion of work |
-
latitude : 23.8126944
Longitude : 87.8059237
file name : Image_21062024114651772.png
|
2024-06-21 11:46:51.857088 |
364 |
67798256 |
Electricity |
100000 |
Electricity1 |
Roof laid |
-
latitude : 23.8148408,23.8148408
Longitude : 87.7969657,87.7969657
file name : Image_01072024110333258.png
|
2024-07-01 11:03:33.354039 |
365 |
67798256 |
Electricity |
100000 |
Electricity1 |
Roof laid |
-
latitude : 23.8149282,23.8149282
Longitude : 87.7971084,87.7971084
file name : Image_01072024104720599.png
|
2024-07-01 10:47:20.685508 |
366 |
67798256 |
Electricity |
100000 |
Electricity1 |
Plinth level |
-
latitude : 23.8147192,23.8147612
Longitude : 87.797088,87.7970498
file name : Image_01072024104222000.png
|
2024-07-01 10:42:22.088189 |
367 |
67798256 |
Electricity |
100000 |
Electricity1 |
Plinth level |
-
latitude : 23.814743333333332,23.814761666666662
Longitude : 87.79778166666668,87.79784333333333
file name : Image_25062024075743381.png
|
2024-06-25 07:57:43.459137 |
368 |
67798256 |
Electricity |
100000 |
Electricity1 |
Completion of work |
-
latitude : 23.8143954,23.814653333333332
Longitude : 87.7979518,87.79769499999999
file name : Image_21062024113026455.png
|
2024-06-21 11:30:26.558616 |
369 |
67818972 |
Electricity/Solar Power Installation |
165000 |
Electricity/Solar Power Installation1 |
Roof laid |
-
latitude : 23.8148432
Longitude : 87.7969593
file name : Image_01072024104814006.png
|
2024-07-01 10:48:14.09034 |
370 |
67818972 |
Electricity/Solar Power Installation |
165000 |
Electricity/Solar Power Installation1 |
Plinth level |
-
latitude : 23.813265
Longitude : 87.805325
file name : Image_01072024104140796.png
|
2024-07-01 10:41:40.929156 |
371 |
67818972 |
Electricity/Solar Power Installation |
165000 |
Electricity/Solar Power Installation1 |
Plinth level |
-
latitude : 23.815096666666665
Longitude : 87.79706499999999
file name : Image_01072024082309100.png
|
2024-07-01 08:23:09.163593 |
372 |
67818972 |
Electricity/Solar Power Installation |
165000 |
Electricity/Solar Power Installation1 |
Plinth level |
-
latitude : 23.8143883
Longitude : 87.7980687
file name : Image_30062024105656733.png
|
2024-06-30 10:56:56.799971 |
373 |
67818972 |
Electricity/Solar Power Installation |
165000 |
Electricity/Solar Power Installation1 |
Plinth level |
-
latitude : 23.81398
Longitude : 87.79952833333333
file name : Image_26062024071119996.png
|
2024-06-26 07:11:20.094686 |
374 |
67818972 |
Electricity/Solar Power Installation |
165000 |
Electricity/Solar Power Installation1 |
Completion of work |
-
latitude : 23.8136561
Longitude : 87.8013368
file name : Image_25062024075041711.png
|
2024-06-25 07:50:41.771721 |
375 |
56168826 |
Construction Of PCC Drain With Cover From Tasebar Sk House to Ibrahim Sk House at Paschimpara |
150000 |
Construction Of PCC Drain With Cover From Tasebar Sk House to Ibrahim Sk House at Paschimpara1 |
Completion of work |
-
latitude : 23.81837666666667,23.818428333333333
Longitude : 87.79816000000001,87.79813666666665
file name : Image_28042024091509677.png
|
2024-04-28 09:15:09.751872 |
376 |
56168826 |
Construction Of PCC Drain With Cover From Tasebar Sk House to Ibrahim Sk House at Paschimpara |
150000 |
Construction Of PCC Drain With Cover From Tasebar Sk House to Ibrahim Sk House at Paschimpara1 |
Completion of work |
-
latitude : 23.818668333333335,23.818548333333336,23.818399999999997,23.818170000000002
Longitude : 87.79815500000001,87.79814999999999,87.79814833333333,87.79814999999999
file name : Image_29082023115429602.png
|
2023-08-29 11:54:29.694111 |
377 |
88627012 |
Creation of drainage channel for management of grey water |
300000 |
Creation of drainage channel for management of grey water1 |
Plinth level |
-
latitude : 23.81794
Longitude : 87.79832833333333
file name : Image_28042024084023859.png
|
2024-04-28 08:40:23.921494 |
378 |
88627012 |
Creation of drainage channel for management of grey water |
300000 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 23.818665000000003
Longitude : 87.79811166666666
file name : Image_27122023141443224.png
|
2023-12-27 14:14:43.294332 |