1 |
39040839 |
Construction of Drain With Cover From Madhu to Bandha Pukur |
200000 |
Construction of Drain With Cover From Madhu to Bandha Pukur1 |
Roof laid |
-
latitude : 24.07892529387027
Longitude : 87.7077429369092
file name : Image_09022021122232808.png
|
2021-02-09 12:22:32.913369 |
2 |
39040839 |
Construction of Drain With Cover From Madhu to Bandha Pukur |
200000 |
Construction of Drain With Cover From Madhu to Bandha Pukur1 |
Plinth level |
-
latitude : 24.07894939184189
Longitude : 87.70771309733391
file name : Image_09022021121618190.png
|
2021-02-09 12:16:18.284478 |
3 |
39040647 |
Construction of Drain With Cover From Natun Pukur to Swapan |
250000 |
Construction of Drain With Cover From Natun Pukur to Swapan 1 |
Plinth level |
-
latitude : 24.04874608386308
Longitude : 87.71272120065987
file name : Image_27012021130254709.png
|
2021-01-27 13:02:54.783204 |
4 |
39040647 |
Construction of Drain With Cover From Natun Pukur to Swapan |
250000 |
Construction of Drain With Cover From Natun Pukur to Swapan 1 |
Completion of work |
-
latitude : 24.04867140110582
Longitude : 87.71270644851029
file name : Image_15012021104744639.png
|
2021-01-15 10:47:44.772555 |
5 |
39040647 |
Construction of Drain With Cover From Natun Pukur to Swapan |
250000 |
Construction of Drain With Cover From Natun Pukur to Swapan 1 |
Completion of work |
-
latitude : 24.048779234290123
Longitude : 87.71271315403283
file name : Image_15012021105153115.png
|
2021-01-15 10:51:53.23525 |
6 |
46549069 |
Cons of Pucca drain with slab from Nur alam house to Bayen Para at Prachandrapur |
225000 |
Cons of Pucca drain with slab from Nur alam house to Bayen Para at Prachandrapur1 |
Roof laid |
-
latitude : 24.049032870680094,24.049099129624665
Longitude : 87.71435131318867,87.71436447277665
file name : Image_21092021131916670.png
|
2021-09-21 13:19:16.764742 |
7 |
46549069 |
Cons of Pucca drain with slab from Nur alam house to Bayen Para at Prachandrapur |
225000 |
Cons of Pucca drain with slab from Nur alam house to Bayen Para at Prachandrapur1 |
Plinth level |
-
latitude : 24.049044814892113,24.049071301706135
Longitude : 87.71434754133224,87.71435868926346
file name : Image_21092021131419734.png
|
2021-09-21 13:14:19.821573 |
8 |
46549069 |
Cons of Pucca drain with slab from Nur alam house to Bayen Para at Prachandrapur |
225000 |
Cons of Pucca drain with slab from Nur alam house to Bayen Para at Prachandrapur1 |
Completion of work |
-
latitude : 24.049062207341194,24.049096405506134
Longitude : 87.71434050053358,87.71437813527882
file name : Image_21092021130143759.png
|
2021-09-21 13:01:43.840395 |
9 |
46549772 |
Cons of drain with slab for all sansad under gp area |
350000 |
Cons of drain with slab for all sansad under gp area1 |
Roof laid |
-
latitude : 24.076232356019318,24.07617913093418
Longitude : 87.70982583984733,87.70982516929507
file name : Image_08102021133855475.png
|
2021-10-08 13:38:55.569648 |
10 |
46549772 |
Cons of drain with slab for all sansad under gp area |
350000 |
Cons of drain with slab for all sansad under gp area1 |
Plinth level |
-
latitude : 24.07629576511681,24.076209808699787
Longitude : 87.70983103662729,87.70980739966035
file name : Image_08102021133334828.png
|
2021-10-08 13:33:34.94073 |
11 |
46549772 |
Cons of drain with slab for all sansad under gp area |
350000 |
Cons of drain with slab for all sansad under gp area1 |
Completion of work |
-
latitude : 24.07625469379127,24.076211024075747
Longitude : 87.70982173271477,87.70981184206903
file name : Image_08102021132325315.png
|
2021-10-08 13:23:25.414429 |
12 |
46505638 |
Cons of pucca drain with slab from Ali sk to Idgha VI |
120000 |
Cons of pucca drain with slab from Ali sk to Idgha VI1 |
Roof laid |
-
latitude : 24.082761774770916,24.082714961841702
Longitude : 87.71201871335506,87.71187462843955
file name : Image_03092021172055125.png
|
2021-09-03 17:20:55.250468 |
13 |
46505638 |
Cons of pucca drain with slab from Ali sk to Idgha VI |
120000 |
Cons of pucca drain with slab from Ali sk to Idgha VI1 |
Plinth level |
-
latitude : 24.082770072855055,24.08270507119596
Longitude : 87.71196297369897,87.71187412552536
file name : Image_03092021171503544.png
|
2021-09-03 17:15:03.665776 |
14 |
46505638 |
Cons of pucca drain with slab from Ali sk to Idgha VI |
120000 |
Cons of pucca drain with slab from Ali sk to Idgha VI1 |
Completion of work |
-
latitude : 24.082839768379927,24.082750333473086
Longitude : 87.71185040473938,87.71184956654906
file name : Image_03092021170217271.png
|
2021-09-03 17:02:17.385757 |
15 |
46928238 |
Cons of pcc road from ICDS center to Arjun tudu house |
150000 |
Cons of pcc road from ICDS center to Arjun tudu house1 |
Roof laid |
-
latitude : 24.094440364278853,24.094538264907897
Longitude : 87.68997472710907,87.68999291583896
file name : Image_10082021165920102.png
|
2021-08-10 16:59:20.246262 |
16 |
46928238 |
Cons of pcc road from ICDS center to Arjun tudu house |
150000 |
Cons of pcc road from ICDS center to Arjun tudu house1 |
Plinth level |
-
latitude : 24.09443797543645,24.094506497494876
Longitude : 87.68998361192644,87.68998017534614
file name : Image_10082021164028893.png
|
2021-08-10 16:40:32.696027 |
17 |
46928238 |
Cons of pcc road from ICDS center to Arjun tudu house |
150000 |
Cons of pcc road from ICDS center to Arjun tudu house1 |
Completion of work |
-
latitude : 24.094387348741293,24.094507126137614
Longitude : 87.68996324390173,87.68999517895281
file name : Image_10082021163345244.png
|
2021-08-10 16:33:45.3861 |
18 |
46928761 |
Cons of Pcc road of all Sansad under mollarpur 2 gp |
200000 |
Cons of Pcc road of all Sansad under mollarpur 2 gp1 |
Roof laid |
-
latitude : 24.076920342631638,24.07688450999558,24.076773575507104
Longitude : 87.71209188736975,87.71211359649897,87.71208308637142
file name : Image_24082021120622508.png
|
2021-08-24 12:06:22.606646 |
19 |
46928761 |
Cons of Pcc road of all Sansad under mollarpur 2 gp |
200000 |
Cons of Pcc road of all Sansad under mollarpur 2 gp1 |
Plinth level |
-
latitude : 24.0769033273682,24.076782376505435
Longitude : 87.71214636974037,87.71209021098912
file name : Image_24082021120034205.png
|
2021-08-24 12:00:34.30585 |
20 |
46928761 |
Cons of Pcc road of all Sansad under mollarpur 2 gp |
200000 |
Cons of Pcc road of all Sansad under mollarpur 2 gp1 |
Completion of work |
-
latitude : 24.07687629573047,24.076891257427633
Longitude : 87.71207369863987,87.71209666505456
file name : Image_24082021115538280.png
|
2021-08-24 11:55:38.377674 |
21 |
46491024 |
Cons of pucca drain with slab from Asim Pal house to Durgamindir |
120000 |
Cons of pucca drain with slab from Asim Pal house to Durgamindir1 |
Roof laid |
-
latitude : 24.08070980105549,24.080656827427447
Longitude : 87.70753146149218,87.70758644677699
file name : Image_27092021123853445.png
|
2021-09-27 12:38:53.546649 |
22 |
46491024 |
Cons of pucca drain with slab from Asim Pal house to Durgamindir |
120000 |
Cons of pucca drain with slab from Asim Pal house to Durgamindir1 |
Plinth level |
-
latitude : 24.080690355040133,24.08063453156501
Longitude : 87.70751779899001,87.70761067047715
file name : Image_27092021123404401.png
|
2021-09-27 12:34:04.509159 |
23 |
46491024 |
Cons of pucca drain with slab from Asim Pal house to Durgamindir |
120000 |
Cons of pucca drain with slab from Asim Pal house to Durgamindir1 |
Completion of work |
-
latitude : 24.08071143552661,24.08069735392928
Longitude : 87.70752525888383,87.70757940597832
file name : Image_27092021122016367.png
|
2021-09-27 12:20:16.459704 |
24 |
46922300 |
Installation and Maintance of Street light all sansad |
300000 |
Installation and Maintance of Street light all sansad4 |
Roof laid |
-
latitude : 24.057980426587164
Longitude : 87.71592576988041
file name : Image_29012022135755835.png
|
2022-01-29 13:57:55.94124 |
25 |
46922300 |
Installation and Maintance of Street light all sansad |
300000 |
Installation and Maintance of Street light all sansad4 |
Plinth level |
-
latitude : 24.057949790731072
Longitude : 87.71590665914118
file name : Image_29012022135409670.png
|
2022-01-29 13:54:09.77008 |
26 |
46922300 |
Installation and Maintance of Street light all sansad |
300000 |
Installation and Maintance of Street light all sansad4 |
Completion of work |
-
latitude : 24.057936295866966
Longitude : 87.71593675017357
file name : Image_29012022134601621.png
|
2022-01-29 13:46:01.752645 |
27 |
46548874 |
Cons of Pucca drain with slab from Rathtala pukur to Sanjib Roy house at Mollarpur. |
300000 |
Cons of Pucca drain with slab from Rathtala pukur to Sanjib Roy house at Mollarpur.1 |
Roof laid |
-
latitude : 24.0742624,24.0742624
Longitude : 87.7119584,87.7119584
file name : Image_07032022163610806.png
|
2022-03-07 16:36:10.896271 |
28 |
46548874 |
Cons of Pucca drain with slab from Rathtala pukur to Sanjib Roy house at Mollarpur. |
300000 |
Cons of Pucca drain with slab from Rathtala pukur to Sanjib Roy house at Mollarpur.1 |
Plinth level |
-
latitude : 24.075754922814667,24.07574670854956
Longitude : 87.70966406911612,87.7095546014607
file name : Image_07032022163208777.png
|
2022-03-07 16:32:08.851219 |
29 |
46548874 |
Cons of Pucca drain with slab from Rathtala pukur to Sanjib Roy house at Mollarpur. |
300000 |
Cons of Pucca drain with slab from Rathtala pukur to Sanjib Roy house at Mollarpur.1 |
Completion of work |
-
latitude : 24.075790252536535,24.0757679566741
Longitude : 87.70945158787072,87.70957329310477
file name : Image_07032022162251463.png
|
2022-03-07 16:22:51.552971 |
30 |
46547318 |
Resinking and Maintainance of tubewell of sansad one to five |
300000 |
Resinking and Maintainance of tubewell of sansad one to five1 |
Completion of work |
-
latitude : 24.0768476
Longitude : 87.7029434
file name : Image_09032022204455630.png
|
2022-03-09 20:44:55.726668 |
31 |
46547556 |
Resinking and Maintainance of tubewell of sansad six to ten |
300000 |
Resinking and Maintainance of tubewell of sansad six to ten1 |
Completion of work |
-
latitude : 24.076858
Longitude : 87.7029981
file name : Image_09032022204549996.png
|
2022-03-09 20:45:50.099401 |
32 |
46548664 |
Sanitary Napkin Machine and Disposal Machine |
100000 |
Sanitary Napkin Machine and Disposal Machine1 |
Roof laid |
-
latitude : 24.0770845
Longitude : 87.7002407
file name : Image_05072022124549569.png
|
2022-07-05 12:45:49.675126 |
33 |
46548664 |
Sanitary Napkin Machine and Disposal Machine |
100000 |
Sanitary Napkin Machine and Disposal Machine1 |
Plinth level |
-
latitude : 24.0770853
Longitude : 87.7002445
file name : Image_05072022123408250.png
|
2022-07-05 12:34:08.34587 |
34 |
46548664 |
Sanitary Napkin Machine and Disposal Machine |
100000 |
Sanitary Napkin Machine and Disposal Machine1 |
Completion of work |
-
latitude : 24.0770847
Longitude : 87.7002383
file name : Image_05072022121701011.png
|
2022-07-05 12:17:01.107052 |
35 |
57178471 |
Drinking Water Testing |
40000 |
Drinking Water Testing1 |
Roof laid |
-
latitude : 24.0768588
Longitude : 87.7029447
file name : Image_13072022164523880.png
|
2022-07-13 16:45:24.013534 |
36 |
57178471 |
Drinking Water Testing |
40000 |
Drinking Water Testing1 |
Completion of work |
-
latitude : 24.076827
Longitude : 87.7027539
file name : Image_13072022164128695.png
|
2022-07-13 16:41:28.823362 |
37 |
57178471 |
Drinking Water Testing |
40000 |
Drinking Water Testing1 |
Completion of work |
-
latitude : 24.0768286
Longitude : 87.7027545
file name : Image_13072022163511879.png
|
2022-07-13 16:35:11.990267 |
38 |
57178471 |
Drinking Water Testing |
40000 |
Drinking Water Testing1 |
Completion of work |
-
latitude : 24.0768308
Longitude : 87.7028612
file name : Image_13072022162845014.png
|
2022-07-13 16:28:45.120473 |
39 |
57166705 |
Tubewell Materials |
480000 |
Tubewell Materials1 |
Roof laid |
-
latitude : 24.0768452
Longitude : 87.7029388
file name : Image_19072022172717959.png
|
2022-07-19 17:27:18.059531 |
40 |
57166705 |
Tubewell Materials |
480000 |
Tubewell Materials1 |
Plinth level |
-
latitude : 24.0768409
Longitude : 87.7028339
file name : Image_19072022172323140.png
|
2022-07-19 17:23:23.244119 |
41 |
57166705 |
Tubewell Materials |
480000 |
Tubewell Materials1 |
Completion of work |
-
latitude : 24.0768305
Longitude : 87.7027792
file name : Image_19072022171622600.png
|
2022-07-19 17:16:22.695022 |
42 |
46546126 |
New sinking of tubewell with sockpit and platform of sansad one to five |
350000 |
New sinking of tubewell with sockpit and platform of sansad one to five1 |
Roof laid |
-
latitude : 24.0764607
Longitude : 87.7036233
file name : Image_05082022162114365.png
|
2022-08-05 16:21:14.45664 |
43 |
46546126 |
New sinking of tubewell with sockpit and platform of sansad one to five |
350000 |
New sinking of tubewell with sockpit and platform of sansad one to five1 |
Plinth level |
-
latitude : 24.0764665
Longitude : 87.7036464
file name : Image_05082022161549619.png
|
2022-08-05 16:15:49.705423 |
44 |
46546126 |
New sinking of tubewell with sockpit and platform of sansad one to five |
350000 |
New sinking of tubewell with sockpit and platform of sansad one to five1 |
Completion of work |
-
latitude : 24.0765368
Longitude : 87.703681
file name : Image_05082022160147488.png
|
2022-08-05 16:01:47.585999 |
45 |
46927791 |
Cons of pcc road from Alu let house to menu let house |
60000 |
Cons of pcc road from Alu let house to menu let house 1 |
Roof laid |
-
latitude : 24.07176861539483,24.07174141611904
Longitude : 87.69862862303853,87.69864471629262
file name : Image_25082021135257817.png
|
2021-08-25 13:52:57.921604 |
46 |
46927791 |
Cons of pcc road from Alu let house to menu let house |
60000 |
Cons of pcc road from Alu let house to menu let house 1 |
Plinth level |
-
latitude : 24.07183479052037,24.071765136905015
Longitude : 87.69873842597008,87.6987147051841
file name : Image_25082021134429919.png
|
2021-08-25 13:44:30.023611 |
47 |
46927791 |
Cons of pcc road from Alu let house to menu let house |
60000 |
Cons of pcc road from Alu let house to menu let house 1 |
Completion of work |
-
latitude : 24.071767861023545,24.071737015619874
Longitude : 87.69867648370564,87.69873767159879
file name : Image_25082021133028627.png
|
2021-08-25 13:30:28.750046 |
48 |
46912539 |
Cons of pcc road from Mister sk to B.R. Road |
200000 |
Cons of pcc road from Mister sk to B.R. Road 1 |
Roof laid |
-
latitude : 24.0520555,24.0520555
Longitude : 87.71247,87.71247
file name : Image_05082021153345971.png
|
2021-08-05 15:33:46.088458 |
49 |
46912539 |
Cons of pcc road from Mister sk to B.R. Road |
200000 |
Cons of pcc road from Mister sk to B.R. Road 1 |
Plinth level |
-
latitude : 24.050666000694036,24.05075053218752
Longitude : 87.71207235753536,87.71191620267928
file name : Image_05082021152538608.png
|
2021-08-05 15:25:38.70765 |
50 |
46912539 |
Cons of pcc road from Mister sk to B.R. Road |
200000 |
Cons of pcc road from Mister sk to B.R. Road 1 |
Completion of work |
-
latitude : 24.0520555,24.0520558
Longitude : 87.7124712,87.7124664
file name : Image_05082021151706299.png
|
2021-08-05 15:17:06.389911 |
51 |
46927350 |
Road protection wall near primary School |
58000 |
Road protection wall near primary School1 |
Roof laid |
-
latitude : 24.06188023276627,24.06185554806143
Longitude : 87.71251257508993,87.71255238913
file name : Image_05082021155816994.png
|
2021-08-05 15:58:17.119814 |
52 |
46927350 |
Road protection wall near primary School |
58000 |
Road protection wall near primary School1 |
Plinth level |
-
latitude : 24.061893266625702,24.061842514202
Longitude : 87.71248323842883,87.71253503859043
file name : Image_05082021155213292.png
|
2021-08-05 15:52:13.400289 |
53 |
46927350 |
Road protection wall near primary School |
58000 |
Road protection wall near primary School1 |
Completion of work |
-
latitude : 24.061873694881797,24.06182399019599
Longitude : 87.71254065446556,87.71243353374302
file name : Image_05082021154728176.png
|
2021-08-05 15:47:28.297483 |
54 |
46928403 |
Cons of pcc road Anil let house to Sunil Let house |
150000 |
Cons of pcc road Anil let house to Sunil Let house1 |
Roof laid |
-
latitude : 24.097808003425598,24.097840692847967
Longitude : 87.68740181811154,87.68731020390987
file name : Image_07082021140211195.png
|
2021-08-07 14:02:11.277148 |
55 |
46928403 |
Cons of pcc road Anil let house to Sunil Let house |
150000 |
Cons of pcc road Anil let house to Sunil Let house1 |
Plinth level |
-
latitude : 24.097803602926433,24.097821582108736
Longitude : 87.68737675622106,87.68732814118266
file name : Image_07082021135704807.png
|
2021-08-07 13:57:04.913355 |
56 |
46928403 |
Cons of pcc road Anil let house to Sunil Let house |
150000 |
Cons of pcc road Anil let house to Sunil Let house1 |
Completion of work |
-
latitude : 24.09777611028403,24.097767476923764
Longitude : 87.68750784918666,87.68743433989584
file name : Image_07082021135144643.png
|
2021-08-07 13:51:44.765181 |
57 |
46926842 |
Cons of Pcc road from Mukul Club TO Kiran Mia house |
117000 |
Cons of Pcc road from Mukul Club TO Kiran Mia house1 |
Roof laid |
-
latitude : 24.080744250677526,24.080675183795393
Longitude : 87.71189264953136,87.71175728179514
file name : Image_07082021123141042.png
|
2021-08-07 12:31:41.138647 |
58 |
46926842 |
Cons of Pcc road from Mukul Club TO Kiran Mia house |
117000 |
Cons of Pcc road from Mukul Club TO Kiran Mia house1 |
Plinth level |
-
latitude : 24.08076767809689,24.08073125872761
Longitude : 87.71193204447627,87.71184353157878
file name : Image_07082021122419560.png
|
2021-08-07 12:24:19.651113 |
59 |
46926842 |
Cons of Pcc road from Mukul Club TO Kiran Mia house |
117000 |
Cons of Pcc road from Mukul Club TO Kiran Mia house1 |
Completion of work |
-
latitude : 24.08075179439038,24.08072073943913
Longitude : 87.71190061233938,87.71182995289564
file name : Image_07082021121906871.png
|
2021-08-07 12:19:06.965735 |
60 |
46927538 |
Cons of pcc road from Raghu Bagdi house to Sadai Let house |
60000 |
Cons of pcc road from Raghu Bagdi house to Sadai Let house 1 |
Roof laid |
-
latitude : 24.070410830900073,24.070472731254995
Longitude : 87.69938274286687,87.69942264072597
file name : Image_07082021130715921.png
|
2021-08-07 13:07:16.002928 |
61 |
46927538 |
Cons of pcc road from Raghu Bagdi house to Sadai Let house |
60000 |
Cons of pcc road from Raghu Bagdi house to Sadai Let house 1 |
Plinth level |
-
latitude : 24.070426924154162,24.07045445870608
Longitude : 87.69942859187722,87.69941912032664
file name : Image_07082021130353592.png
|
2021-08-07 13:03:53.674761 |
62 |
46927538 |
Cons of pcc road from Raghu Bagdi house to Sadai Let house |
60000 |
Cons of pcc road from Raghu Bagdi house to Sadai Let house 1 |
Completion of work |
-
latitude : 24.07044808845967,24.07047583255917
Longitude : 87.69936631433666,87.6993949804455
file name : Image_07082021125901128.png
|
2021-08-07 12:59:01.232249 |
63 |
35098394 |
Install Street Light From BRroad to Alimgir House |
300000 |
Install Street Light From BRroad to Alimgir House1 |
Roof laid |
-
latitude : 24.065836323425174
Longitude : 87.71998051553965
file name : Image_07012022143726243.png
|
2022-01-07 14:37:26.385472 |
64 |
35098394 |
Install Street Light From BRroad to Alimgir House |
300000 |
Install Street Light From BRroad to Alimgir House1 |
Plinth level |
-
latitude : 24.065830414183438
Longitude : 87.71997154690325
file name : Image_07012022142932841.png
|
2022-01-07 14:29:32.97575 |
65 |
35098394 |
Install Street Light From BRroad to Alimgir House |
300000 |
Install Street Light From BRroad to Alimgir House1 |
Completion of work |
-
latitude : 24.0783591
Longitude : 87.7100542
file name : Image_07012022142004742.png
|
2022-01-07 14:20:04.923707 |
66 |
35098394 |
Install Street Light From BRroad to Alimgir House |
300000 |
Install Street Light From BRroad to Alimgir House1 |
Completion of work |
-
latitude : 24.06110947486013
Longitude : 87.71760106086731
file name : Image_03062021172101792.png
|
2021-06-03 17:21:01.895655 |
67 |
35184866 |
Operation Maintenance of Drain of all sansad |
320000 |
Operation Maintenance of Drain of all sansad 1 |
Roof laid |
-
latitude : 24.082873756997287,24.08283193130046
Longitude : 87.7120545040816,87.71201862953603
file name : Image_27012022132642234.png
|
2022-01-27 13:26:42.377966 |
68 |
35184866 |
Operation Maintenance of Drain of all sansad |
320000 |
Operation Maintenance of Drain of all sansad 1 |
Plinth level |
-
latitude : 24.082929454743862,24.08283842727542
Longitude : 87.71201930008829,87.71201821044087
file name : Image_27012022131722984.png
|
2022-01-27 13:17:23.094983 |
69 |
35184866 |
Operation Maintenance of Drain of all sansad |
320000 |
Operation Maintenance of Drain of all sansad 1 |
Completion of work |
-
latitude : 24.08287706784904,24.082783525809646
Longitude : 87.71208208054304,87.71202634088695
file name : Image_27012022130033602.png
|
2022-01-27 13:00:33.730436 |
70 |
35091229 |
Install Street Light From Joydeb to Totan House |
300000 |
Install Street Light From Joydeb to Totan House1 |
Roof laid |
-
latitude : 24.080394725315273
Longitude : 87.71049764938653
file name : Image_28052021143832294.png
|
2021-05-28 14:38:32.384223 |
71 |
35091229 |
Install Street Light From Joydeb to Totan House |
300000 |
Install Street Light From Joydeb to Totan House1 |
Completion of work |
-
latitude : 24.080385002307594
Longitude : 87.71051567047834
file name : Image_28052021142207843.png
|
2021-05-28 14:22:07.983557 |
72 |
35091229 |
Install Street Light From Joydeb to Totan House |
300000 |
Install Street Light From Joydeb to Totan House1 |
Completion of work |
-
latitude : 24.0861856
Longitude : 87.7186549
file name : Image_28052021141724194.png
|
2021-05-28 14:17:24.297271 |
73 |
39038892 |
Install Street Light From Prasanta House to Supriya House |
300000 |
Install Street Light From Prasanta House to Supriya House1 |
Roof laid |
-
latitude : 24.076461642980576
Longitude : 87.70590319298208
file name : Image_07012021143404761.png
|
2021-01-07 14:34:04.885203 |
74 |
39038892 |
Install Street Light From Prasanta House to Supriya House |
300000 |
Install Street Light From Prasanta House to Supriya House1 |
Plinth level |
-
latitude : 24.0768111
Longitude : 87.7030576
file name : Image_05012021141134252.png
|
2021-01-05 14:11:34.338218 |
75 |
39038892 |
Install Street Light From Prasanta House to Supriya House |
300000 |
Install Street Light From Prasanta House to Supriya House1 |
Completion of work |
-
latitude : 24.0768018
Longitude : 87.7030701
file name : Image_02012021154114747.png
|
2021-01-02 15:41:14.910756 |
76 |
35185410 |
Operation Maintenance of Drain Slab |
200000 |
Operation Maintenance of Drain Slab1 |
Roof laid |
-
latitude : 24.0771085,24.0771085
Longitude : 87.7080774,87.7080774
file name : Image_20012021124817569.png
|
2021-01-20 12:48:17.676338 |
77 |
35185410 |
Operation Maintenance of Drain Slab |
200000 |
Operation Maintenance of Drain Slab1 |
Plinth level |
-
latitude : 24.0771082,24.0771082
Longitude : 87.70807,87.70807
file name : Image_20012021124421586.png
|
2021-01-20 12:44:21.69531 |
78 |
35185410 |
Operation Maintenance of Drain Slab |
200000 |
Operation Maintenance of Drain Slab1 |
Completion of work |
-
latitude : 24.0774875,24.0774875
Longitude : 87.7076712,87.7076712
file name : Image_20012021123608031.png
|
2021-01-20 12:36:08.13385 |
79 |
35052681 |
Install Street Light From NH Sixty to Udita Lodug |
350000 |
Install Street Light From NH Sixty to Udita Lodug1 |
Roof laid |
-
latitude : 24.075524
Longitude : 87.7180918
file name : Image_05012021152314697.png
|
2021-01-05 15:23:14.803774 |
80 |
35052681 |
Install Street Light From NH Sixty to Udita Lodug |
350000 |
Install Street Light From NH Sixty to Udita Lodug1 |
Completion of work |
-
latitude : 24.0755306
Longitude : 87.7180943
file name : Image_18122020132948603.png
|
2020-12-18 13:29:48.710081 |
81 |
35039976 |
Install Street Light From NH Sixty to Bankim House |
300000 |
Install Street Light From NH Sixty to Bankim House1 |
Roof laid |
-
latitude : 24.076559962704778
Longitude : 87.70653921179473
file name : Image_07012021145130318.png
|
2021-01-07 14:51:30.417605 |
82 |
35039976 |
Install Street Light From NH Sixty to Bankim House |
300000 |
Install Street Light From NH Sixty to Bankim House1 |
Plinth level |
-
latitude : 24.07686125021428
Longitude : 87.70947438664734
file name : Image_05012021142706547.png
|
2021-01-05 14:27:06.669952 |
83 |
35039976 |
Install Street Light From NH Sixty to Bankim House |
300000 |
Install Street Light From NH Sixty to Bankim House1 |
Completion of work |
-
latitude : 24.07689129933715
Longitude : 87.70950288511813
file name : Image_02012021154126271.png
|
2021-01-02 15:41:26.395653 |
84 |
35050178 |
Install Street Light From Mithun to Bhuban House |
300000 |
Install Street Light From Mithun to Bhuban House1 |
Roof laid |
-
latitude : 24.076486327685416
Longitude : 87.70630736835301
file name : Image_07012021144957948.png
|
2021-01-07 14:49:58.052462 |
85 |
35050178 |
Install Street Light From Mithun to Bhuban House |
300000 |
Install Street Light From Mithun to Bhuban House1 |
Plinth level |
-
latitude : 24.076842349022627
Longitude : 87.70967161282897
file name : Image_05012021142831274.png
|
2021-01-05 14:28:31.370473 |
86 |
35050178 |
Install Street Light From Mithun to Bhuban House |
300000 |
Install Street Light From Mithun to Bhuban House1 |
Completion of work |
-
latitude : 24.0756915
Longitude : 87.7165865
file name : Image_02012021154723964.png
|
2021-01-02 15:47:24.081243 |
87 |
35049705 |
Install Street Light From Durgatala to Santi Hous |
300000 |
Install Street Light From Durgatala to Santi Hous1 |
Roof laid |
-
latitude : 24.076429163105786
Longitude : 87.7057758718729
file name : Image_07012021143036069.png
|
2021-01-07 14:30:36.158911 |
88 |
35049705 |
Install Street Light From Durgatala to Santi Hous |
300000 |
Install Street Light From Durgatala to Santi Hous1 |
Plinth level |
-
latitude : 24.0768151
Longitude : 87.70306
file name : Image_05012021141554585.png
|
2021-01-05 14:15:54.678437 |
89 |
35049705 |
Install Street Light From Durgatala to Santi Hous |
300000 |
Install Street Light From Durgatala to Santi Hous1 |
Completion of work |
-
latitude : 24.0766926901415
Longitude : 87.70276584662497
file name : Image_02012021154120919.png
|
2021-01-02 15:41:21.01793 |
90 |
35102295 |
Install Street Light From Shibtala to Tati para |
250000 |
Install Street Light From Shibtala to Tati para1 |
Completion of work |
-
latitude : 24.047930859960616
Longitude : 87.71215785294771
file name : Image_03062021173153967.png
|
2021-06-03 17:31:54.078819 |
91 |
39040194 |
Operation Maintenance of Tubewells With Platforms and Soffits |
1900000 |
Operation Maintenance of Tubewells With Platforms and Soffits1 |
Completion of work |
-
latitude : 24.0768682
Longitude : 87.7029073
file name : Image_09082021191552209.png
|
2021-08-09 19:15:52.295765 |
92 |
46922533 |
Installation of Street light of sansad no one to seven |
300000 |
Installation of Street light of sansad no one to seven1 |
Roof laid |
-
latitude : 24.073373372666538
Longitude : 87.69848738797009
file name : Image_05072022131321815.png
|
2022-07-05 13:13:21.929325 |
93 |
46922533 |
Installation of Street light of sansad no one to seven |
300000 |
Installation of Street light of sansad no one to seven1 |
Plinth level |
-
latitude : 24.073394327424467
Longitude : 87.69849015399814
file name : Image_05072022130322108.png
|
2022-07-05 13:03:22.215655 |
94 |
46922533 |
Installation of Street light of sansad no one to seven |
300000 |
Installation of Street light of sansad no one to seven1 |
Completion of work |
-
latitude : 24.073409750126302
Longitude : 87.69847271963954
file name : Image_05072022125638346.png
|
2022-07-05 12:56:38.471536 |
95 |
46911553 |
Cons of pcc road from Madhu sk to Baduruddin sk house |
130000 |
Cons of pcc road from Madhu sk to Baduruddin sk house1 |
Roof laid |
-
latitude : 24.061545082367957,24.061505352146924
Longitude : 87.7143167797476,87.71430881693959
file name : Image_11082022131824784.png
|
2022-08-11 13:18:24.9589 |
96 |
46911553 |
Cons of pcc road from Madhu sk to Baduruddin sk house |
130000 |
Cons of pcc road from Madhu sk to Baduruddin sk house1 |
Plinth level |
-
latitude : 24.06146210152656,24.061510800383985
Longitude : 87.71427403204143,87.71431954577565
file name : Image_11082022131136758.png
|
2022-08-11 13:11:36.835976 |
97 |
46911553 |
Cons of pcc road from Madhu sk to Baduruddin sk house |
130000 |
Cons of pcc road from Madhu sk to Baduruddin sk house1 |
Completion of work |
-
latitude : 24.06153280287981,24.06155941542238
Longitude : 87.71429414860904,87.71430362015963
file name : Image_11082022130338984.png
|
2022-08-11 13:03:39.05779 |
98 |
46924726 |
Installation of Street light of sansad no eight to thirteen |
300000 |
Installation of Street light of sansad no eight to thirteen1 |
Roof laid |
-
latitude : 24.050785819999874
Longitude : 87.70650400780141
file name : Image_16082022173930000.png
|
2022-08-16 17:39:30.156924 |
99 |
46924726 |
Installation of Street light of sansad no eight to thirteen |
300000 |
Installation of Street light of sansad no eight to thirteen1 |
Plinth level |
-
latitude : 24.05080266762525
Longitude : 87.7064928598702
file name : Image_16082022173553392.png
|
2022-08-16 17:35:53.657929 |
100 |
46924726 |
Installation of Street light of sansad no eight to thirteen |
300000 |
Installation of Street light of sansad no eight to thirteen1 |
Completion of work |
-
latitude : 24.050777019001544
Longitude : 87.70640183240175
file name : Image_16082022173022495.png
|
2022-08-16 17:30:22.729942 |
101 |
57000950 |
Const and Repairing of GP office Building |
200000 |
Const and Repairing of GP office Building1 |
Roof laid |
-
latitude : 24.0768508
Longitude : 87.7027985
file name : Image_12082022133747363.png
|
2022-08-12 13:37:47.467566 |
102 |
57000950 |
Const and Repairing of GP office Building |
200000 |
Const and Repairing of GP office Building1 |
Plinth level |
-
latitude : 24.0768468
Longitude : 87.7027542
file name : Image_12082022133129606.png
|
2022-08-12 13:31:29.706011 |
103 |
57000950 |
Const and Repairing of GP office Building |
200000 |
Const and Repairing of GP office Building1 |
Completion of work |
-
latitude : 24.0768475
Longitude : 87.7027878
file name : Image_12082022132157787.png
|
2022-08-12 13:21:58.030796 |
104 |
56929275 |
Const of Pcc road of all sansad under Mollarpur two gp |
205000 |
Const of Pcc road of all sansad under Mollarpur two gp1 |
Roof laid |
-
latitude : 24.075894355773926,24.07582340296358
Longitude : 87.70986255258322,87.70978543907404
file name : Image_13082022115215001.png
|
2022-08-13 11:52:15.111192 |
105 |
56929275 |
Const of Pcc road of all sansad under Mollarpur two gp |
205000 |
Const of Pcc road of all sansad under Mollarpur two gp1 |
Plinth level |
-
latitude : 24.075798634439707,24.075813344679773
Longitude : 87.70982617512345,87.709822319448
file name : Image_13082022114749132.png
|
2022-08-13 11:47:49.242642 |
106 |
56929275 |
Const of Pcc road of all sansad under Mollarpur two gp |
205000 |
Const of Pcc road of all sansad under Mollarpur two gp1 |
Plinth level |
-
latitude : 24.075835389085114,24.07582440879196
Longitude : 87.70984327420592,87.70981083624065
file name : Image_13082022114757297.png
|
2022-08-13 11:47:57.412347 |
107 |
56929275 |
Const of Pcc road of all sansad under Mollarpur two gp |
205000 |
Const of Pcc road of all sansad under Mollarpur two gp1 |
Completion of work |
-
latitude : 24.075806764885783,24.075829186476767
Longitude : 87.7098115067929,87.70980111323297
file name : Image_13082022114020865.png
|
2022-08-13 11:40:20.984815 |
108 |
46911248 |
Cons of Pcc road from Naru Kahar to Santi Kahar house |
100000 |
Cons of Pcc road from Naru Kahar to Santi Kahar house1 |
Roof laid |
-
latitude : 24.082746729254723,24.082732647657394
Longitude : 87.70887164399028,87.70889561623335
file name : Image_30032022165402269.png
|
2022-03-30 16:54:02.377242 |
109 |
46911248 |
Cons of Pcc road from Naru Kahar to Santi Kahar house |
100000 |
Cons of Pcc road from Naru Kahar to Santi Kahar house1 |
Plinth level |
-
latitude : 24.082727911882102,24.082719194702804
Longitude : 87.70882587879896,87.70891791209579
file name : Image_30032022164758684.png
|
2022-03-30 16:47:58.782312 |
110 |
46911248 |
Cons of Pcc road from Naru Kahar to Santi Kahar house |
100000 |
Cons of Pcc road from Naru Kahar to Santi Kahar house1 |
Completion of work |
-
latitude : 24.08276072703302,24.08273088745773
Longitude : 87.70884959958494,87.70890592597425
file name : Image_30032022164323858.png
|
2022-03-30 16:43:23.963055 |
111 |
46910808 |
Construction of Culvert near the land of Sukhen Karmakar house |
100000 |
Construction of Culvert near the land of Sukhen Karmakar house1 |
Roof laid |
-
latitude : 24.084043158218265,24.08416725229472
Longitude : 87.70774209871888,87.70782189443707
file name : Image_21022022122136626.png
|
2022-02-21 12:21:36.719148 |
112 |
46910808 |
Construction of Culvert near the land of Sukhen Karmakar house |
100000 |
Construction of Culvert near the land of Sukhen Karmakar house1 |
Plinth level |
-
latitude : 24.08414386678487,24.084073291160166
Longitude : 87.70779088139534,87.70773774012923
file name : Image_21022022121032060.png
|
2022-02-21 12:10:32.152554 |
113 |
46910808 |
Construction of Culvert near the land of Sukhen Karmakar house |
100000 |
Construction of Culvert near the land of Sukhen Karmakar house1 |
Completion of work |
-
latitude : 24.084089593961835,24.084147890098393
Longitude : 87.70774930715561,87.70776883699
file name : Image_21022022120109782.png
|
2022-02-21 12:01:09.898822 |
114 |
48427381 |
Cons of Culvert Near Prasanta Chatterjee at Mollarpur |
100000 |
Cons of Culvert Near Prasanta Chatterjee at Mollarpur1 |
Roof laid |
-
latitude : 24.07951898407191,24.079634654335678
Longitude : 87.70689728669822,87.7069487515837
file name : Image_07032022165804598.png
|
2022-03-07 16:58:04.702865 |
115 |
48427381 |
Cons of Culvert Near Prasanta Chatterjee at Mollarpur |
100000 |
Cons of Culvert Near Prasanta Chatterjee at Mollarpur1 |
Plinth level |
-
latitude : 24.079576232470572,24.07961441203952
Longitude : 87.70685319788754,87.70693257451057
file name : Image_07032022165424509.png
|
2022-03-07 16:54:24.615323 |
116 |
48427381 |
Cons of Culvert Near Prasanta Chatterjee at Mollarpur |
100000 |
Cons of Culvert Near Prasanta Chatterjee at Mollarpur1 |
Completion of work |
-
latitude : 24.079524432308972,24.079624679870903
Longitude : 87.70687381736934,87.70694389007986
file name : Image_07032022165028709.png
|
2022-03-07 16:50:28.807505 |
117 |
46930718 |
Cons of culvert near Agrani Sangha Rural Library at Mollarpur |
91650 |
Cons of culvert near Agrani Sangha Rural Library at Mollarpur1 |
Roof laid |
-
latitude : 24.075829102657735,24.075872395187616
Longitude : 87.70969910547137,87.70977915264666
file name : Image_23032022122459080.png
|
2022-03-23 12:24:59.170411 |
118 |
46930718 |
Cons of culvert near Agrani Sangha Rural Library at Mollarpur |
91650 |
Cons of culvert near Agrani Sangha Rural Library at Mollarpur1 |
Plinth level |
-
latitude : 24.075837191194296,24.075862085446715
Longitude : 87.70979180932045,87.7097911387682
file name : Image_23032022121826781.png
|
2022-03-23 12:18:26.869974 |
119 |
46930718 |
Cons of culvert near Agrani Sangha Rural Library at Mollarpur |
91650 |
Cons of culvert near Agrani Sangha Rural Library at Mollarpur1 |
Completion of work |
-
latitude : 24.075857559219003,24.075829228386283
Longitude : 87.70981024950743,87.70977261476219
file name : Image_23032022121256791.png
|
2022-03-23 12:12:56.877917 |
120 |
46909951 |
Changing Room or feeding room with toilet for men and women at Gp office Building |
350000 |
Changing Room or feeding room with toilet for men and women at Gp office Building1 |
Roof laid |
-
latitude : 24.0768502
Longitude : 87.7029519
file name : Image_29032022134105156.png
|
2022-03-29 13:41:05.28362 |
121 |
46909951 |
Changing Room or feeding room with toilet for men and women at Gp office Building |
350000 |
Changing Room or feeding room with toilet for men and women at Gp office Building1 |
Plinth level |
-
latitude : 24.0768393
Longitude : 87.7028851
file name : Image_29032022131529633.png
|
2022-03-29 13:15:29.762583 |
122 |
46909951 |
Changing Room or feeding room with toilet for men and women at Gp office Building |
350000 |
Changing Room or feeding room with toilet for men and women at Gp office Building1 |
Completion of work |
-
latitude : 24.0768189
Longitude : 87.7026309
file name : Image_29032022131004274.png
|
2022-03-29 13:10:04.361643 |
123 |
57167252 |
Operation and Maintanence of Tubewell Sansad I to V |
480000 |
Operation and Maintanence of Tubewell Sansad I to V1 |
Completion of work |
-
latitude : 24.076753
Longitude : 87.7025427
file name : Image_06032023170709030.png
|
2023-03-06 17:07:09.134613 |
124 |
46549954 |
Cons of drain with slab both side of NH60 |
161717 |
Cons of drain with slab both side of NH60 1 |
Roof laid |
-
latitude : 24.07645594328642,24.07646361272782
Longitude : 87.70522316917777,87.70527547225356
file name : Image_29032022124722620.png
|
2022-03-29 12:47:22.733183 |
125 |
46549954 |
Cons of drain with slab both side of NH60 |
161717 |
Cons of drain with slab both side of NH60 1 |
Plinth level |
-
latitude : 24.076445340178907,24.076462858356535
Longitude : 87.70521378144622,87.7052546851337
file name : Image_29032022123842323.png
|
2022-03-29 12:38:42.429742 |
126 |
46549954 |
Cons of drain with slab both side of NH60 |
161717 |
Cons of drain with slab both side of NH60 1 |
Completion of work |
-
latitude : 24.076845,24.076845
Longitude : 87.7029766,87.7029766
file name : Image_29032022122810013.png
|
2022-03-29 12:28:10.120814 |
127 |
39040596 |
Construction of Drain With Cover From BR Road to Anarul Sekh |
200000 |
Construction of Drain With Cover From BR Road to Anarul Sekh1 |
Roof laid |
-
latitude : 24.059814806096256
Longitude : 87.71650194190443
file name : Image_07012021155529162.png
|
2021-01-07 15:55:29.2607 |
128 |
39040596 |
Construction of Drain With Cover From BR Road to Anarul Sekh |
200000 |
Construction of Drain With Cover From BR Road to Anarul Sekh1 |
Plinth level |
-
latitude : 24.0598106989637
Longitude : 87.7164804842323
file name : Image_07012021154908546.png
|
2021-01-07 15:49:08.633254 |
129 |
39040596 |
Construction of Drain With Cover From BR Road to Anarul Sekh |
200000 |
Construction of Drain With Cover From BR Road to Anarul Sekh1 |
Completion of work |
-
latitude : 24.05980860348791
Longitude : 87.7164582721889
file name : Image_07012021153613287.png
|
2021-01-07 15:36:13.408409 |
130 |
46921373 |
Cons of pcc road from Main Road to Idgaha chatal |
100000 |
Cons of pcc road from Main Road to Idgaha chatal 1 |
Roof laid |
-
latitude : 24.05402483884245,24.05405266676098
Longitude : 87.70674674771726,87.70672855898738
file name : Image_21092021135944452.png
|
2021-09-21 13:59:44.570349 |
131 |
46921373 |
Cons of pcc road from Main Road to Idgaha chatal |
100000 |
Cons of pcc road from Main Road to Idgaha chatal 1 |
Plinth level |
-
latitude : 24.054032214917243,24.054031879641116
Longitude : 87.70674859173596,87.70672378130257
file name : Image_21092021135629279.png
|
2021-09-21 13:56:29.392328 |
132 |
39040795 |
Construction of Drain With Cover From Tarun Let to Sadhan Let |
350000 |
Construction of Drain With Cover From Tarun Let to Sadhan Let1 |
Roof laid |
-
latitude : 24.088979428634048
Longitude : 87.70064790733159
file name : Image_06012021113249980.png
|
2021-01-06 11:32:50.090794 |
133 |
39040795 |
Construction of Drain With Cover From Tarun Let to Sadhan Let |
350000 |
Construction of Drain With Cover From Tarun Let to Sadhan Let1 |
Plinth level |
-
latitude : 24.08896957989782
Longitude : 87.70066844299436
file name : Image_06012021111504184.png
|
2021-01-06 11:15:04.28944 |
134 |
39040795 |
Construction of Drain With Cover From Tarun Let to Sadhan Let |
350000 |
Construction of Drain With Cover From Tarun Let to Sadhan Let1 |
Completion of work |
-
latitude : 24.08903395291418
Longitude : 87.70064983516932
file name : Image_05012021114518023.png
|
2021-01-05 11:45:18.145905 |
135 |
46929198 |
Cons of pcc road from BR road to Talu Sekh house at Rukunpur. |
220000 |
Cons of pcc road from BR road to Talu Sekh house at Rukunpur.1 |
Roof laid |
-
latitude : 24.061375558376312,24.06130858696997
Longitude : 87.71516385488212,87.71512513048947
file name : Image_25082021164600118.png
|
2021-08-25 16:46:00.22779 |
136 |
46929198 |
Cons of pcc road from BR road to Talu Sekh house at Rukunpur. |
220000 |
Cons of pcc road from BR road to Talu Sekh house at Rukunpur.1 |
Plinth level |
-
latitude : 24.061391442082822,24.06133763026446
Longitude : 87.71515681408346,87.7151474263519
file name : Image_25082021163636243.png
|
2021-08-25 16:36:36.346008 |
137 |
46929198 |
Cons of pcc road from BR road to Talu Sekh house at Rukunpur. |
220000 |
Cons of pcc road from BR road to Talu Sekh house at Rukunpur.1 |
Completion of work |
-
latitude : 24.06137073878199,24.061346598900855
Longitude : 87.71517307497561,87.71516435779631
file name : Image_25082021163134366.png
|
2021-08-25 16:31:34.486978 |
138 |
46928014 |
Cons of pcc road from Bankim Pal house to Rafik sk house |
60000 |
Cons of pcc road from Bankim Pal house to Rafik sk house 1 |
Roof laid |
-
latitude : 24.06899361871183,24.068918474949896
Longitude : 87.7000165823847,87.70002974197268
file name : Image_02092021173714790.png
|
2021-09-02 17:37:14.937522 |
139 |
46928014 |
Cons of pcc road from Bankim Pal house to Rafik sk house |
60000 |
Cons of pcc road from Bankim Pal house to Rafik sk house 1 |
Plinth level |
-
latitude : 24.068959839642048,24.068923546001315
Longitude : 87.7000205218792,87.70002915523946
file name : Image_02092021173328980.png
|
2021-09-02 17:33:29.128791 |
140 |
46928014 |
Cons of pcc road from Bankim Pal house to Rafik sk house |
60000 |
Cons of pcc road from Bankim Pal house to Rafik sk house 1 |
Completion of work |
-
latitude : 24.06899118795991,24.068926395848393
Longitude : 87.70002035424113,87.69998925738037
file name : Image_02092021172530227.png
|
2021-09-02 17:25:30.328472 |
141 |
39040824 |
Construction of Drain With Cover From Ramprasad to Pratima Das |
200000 |
Construction of Drain With Cover From Ramprasad to Pratima Das1 |
Roof laid |
-
latitude : 24.076988152228296
Longitude : 87.70724203437567
file name : Image_14012021111409519.png
|
2021-01-14 11:14:09.608104 |
142 |
39040824 |
Construction of Drain With Cover From Ramprasad to Pratima Das |
200000 |
Construction of Drain With Cover From Ramprasad to Pratima Das1 |
Plinth level |
-
latitude : 24.0767599
Longitude : 87.7072121
file name : Image_08012021121014973.png
|
2021-01-08 12:10:15.060258 |
143 |
39040824 |
Construction of Drain With Cover From Ramprasad to Pratima Das |
200000 |
Construction of Drain With Cover From Ramprasad to Pratima Das1 |
Completion of work |
-
latitude : 24.0767596
Longitude : 87.7072119
file name : Image_08012021120213681.png
|
2021-01-08 12:02:13.786481 |
144 |
57018244 |
Const of Drain of all Sansad under Mollarpur two gp |
340000 |
Const of Drain of all Sansad under Mollarpur two gp1 |
Roof laid |
-
latitude : 24.0765959,24.077077796682715
Longitude : 87.7055957,87.70561854355037
file name : Image_28032023160512955.png
|
2023-03-28 16:05:13.045718 |
145 |
57018244 |
Const of Drain of all Sansad under Mollarpur two gp |
340000 |
Const of Drain of all Sansad under Mollarpur two gp1 |
Plinth level |
-
latitude : 24.0765018,24.077043011784554,24.07717628404498
Longitude : 87.7081786,87.7056186273694,87.70566154271364
file name : Image_20032023124518813.png
|
2023-03-20 12:45:18.898569 |
146 |
57018244 |
Const of Drain of all Sansad under Mollarpur two gp |
340000 |
Const of Drain of all Sansad under Mollarpur two gp1 |
Completion of work |
-
latitude : 24.076449321582913,24.07636537682265
Longitude : 87.70491169765592,87.70491764880717
file name : Image_27022023173618977.png
|
2023-02-27 17:36:19.077659 |
147 |
56928340 |
Const of Pcc road from Lalan sekh to Nantu Sekh house at VIII |
120000 |
Const of Pcc road from Lalan sekh to Nantu Sekh house at VIII1 |
Roof laid |
-
latitude : 24.06927608884871,24.06928459648043
Longitude : 87.7016197051853,87.70163965411484
file name : Image_27032023122741764.png
|
2023-03-27 12:27:42.537108 |
148 |
56928340 |
Const of Pcc road from Lalan sekh to Nantu Sekh house at VIII |
120000 |
Const of Pcc road from Lalan sekh to Nantu Sekh house at VIII1 |
Plinth level |
-
latitude : 24.06928053125739,24.069269089959562
Longitude : 87.70181693136692,87.70164015702903
file name : Image_21032023172200340.png
|
2023-03-21 17:22:00.428426 |
149 |
56928340 |
Const of Pcc road from Lalan sekh to Nantu Sekh house at VIII |
120000 |
Const of Pcc road from Lalan sekh to Nantu Sekh house at VIII1 |
Completion of work |
-
latitude : 24.069260875694454,24.069274747744203
Longitude : 87.70175968296826,87.70161652006209
file name : Image_16032023160004768.png
|
2023-03-16 16:00:04.850229 |
150 |
57017644 |
Const of Culvert near Supriya Saha house at Mollarpur v |
300000 |
Const of Culvert near Supriya Saha house at Mollarpur v1 |
Roof laid |
-
latitude : 24.077510931529105,24.07751068007201,24.077457622624934,24.077457622624934
Longitude : 87.71406046114862,87.7140617184341,87.71406683139503,87.71406683139503
file name : Image_06042023120809542.png
|
2023-04-06 12:08:09.641163 |
151 |
57017644 |
Const of Culvert near Supriya Saha house at Mollarpur v |
300000 |
Const of Culvert near Supriya Saha house at Mollarpur v1 |
Completion of work |
-
latitude : 24.077536454424262,24.077478451654315,24.077478451654315,24.077478451654315
Longitude : 87.71406196989119,87.714151320979,87.714151320979,87.714151320979
file name : Image_02032023111755156.png
|
2023-03-02 11:17:55.263503 |
152 |
57017644 |
Const of Culvert near Supriya Saha house at Mollarpur v |
300000 |
Const of Culvert near Supriya Saha house at Mollarpur v1 |
Completion of work |
-
latitude : 24.077548189088702,24.077535406686366,24.077535406686366,24.077535406686366
Longitude : 87.71414344199002,87.71419725380838,87.71419725380838,87.71419725380838
file name : Image_01032023162751141.png
|
2023-03-01 16:27:51.246596 |
153 |
56928800 |
Const of Pcc road of all Sansad under Mollarpur two No gp |
350000 |
Const of Pcc road of all Sansad under Mollarpur two No gp1 |
Roof laid |
-
latitude : 24.08201708458364,24.081626487895846
Longitude : 87.70572700537741,87.70556305535138
file name : Image_10042023114655081.png
|
2023-04-10 11:46:55.206832 |
154 |
56928800 |
Const of Pcc road of all Sansad under Mollarpur two No gp |
350000 |
Const of Pcc road of all Sansad under Mollarpur two No gp1 |
Plinth level |
-
latitude : 24.08163122367114,24.082015533931553,24.08202102407813
Longitude : 87.70551133900881,87.7056979201734,87.70569507032633
file name : Image_06042023133132600.png
|
2023-04-06 13:31:32.705511 |
155 |
56928800 |
Const of Pcc road of all Sansad under Mollarpur two No gp |
350000 |
Const of Pcc road of all Sansad under Mollarpur two No gp1 |
Completion of work |
-
latitude : 24.081704900600016,24.08202932216227,24.08202932216227
Longitude : 87.70555987022817,87.7057156059891,87.7057156059891
file name : Image_05042023131256282.png
|
2023-04-05 13:12:56.387736 |
156 |
71456860 |
Operation and Maintenance of drinking water supply system |
500000 |
Operation and Maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 24.0768083
Longitude : 87.7026292
file name : Image_09042024132948082.png
|
2024-04-09 13:29:48.178724 |
157 |
56932437 |
Const and Maintenance of LEd street light and Solar light at I to VII |
350000 |
Const and Maintenance of LEd street light and Solar light at I to VII1 |
Roof laid |
-
latitude : 24.075793102383614
Longitude : 87.70937900058925
file name : Image_24072023143959243.png
|
2023-07-24 14:39:59.415434 |
158 |
56932437 |
Const and Maintenance of LEd street light and Solar light at I to VII |
350000 |
Const and Maintenance of LEd street light and Solar light at I to VII1 |
Plinth level |
-
latitude : 24.07579637132585
Longitude : 87.7092744782567
file name : Image_24072023143254562.png
|
2023-07-24 14:32:54.675211 |
159 |
56932437 |
Const and Maintenance of LEd street light and Solar light at I to VII |
350000 |
Const and Maintenance of LEd street light and Solar light at I to VII1 |
Completion of work |
-
latitude : 24.07584523782134
Longitude : 87.70928378216922
file name : Image_24072023142519083.png
|
2023-07-24 14:25:19.200878 |
160 |
57014352 |
Const of Pucca Drain from Rasul Box to Mainuddin sekh at Rukunpur |
300000 |
Const of Pucca Drain from Rasul Box to Mainuddin sekh at Rukunpur1 |
Completion of work |
-
latitude : 24.0615237923339,24.061516751535237
Longitude : 87.71427646279335,87.7142842579633
file name : Image_01042024155152569.png
|
2024-04-01 15:51:52.671462 |
161 |
57013403 |
Const of Pucca Drain from Anganwary center to Dutta pukur at Birajpur |
300000 |
Const of Pucca Drain from Anganwary center to Dutta pukur at Birajpur1 |
Roof laid |
-
latitude : 24.1004744,24.1004919
Longitude : 87.6881344,87.6881286
file name : Image_17102023140853555.png
|
2023-10-17 14:08:53.641752 |
162 |
57013403 |
Const of Pucca Drain from Anganwary center to Dutta pukur at Birajpur |
300000 |
Const of Pucca Drain from Anganwary center to Dutta pukur at Birajpur1 |
Plinth level |
-
latitude : 24.1004473,24.1004473,24.1004473
Longitude : 87.688149,87.688149,87.688149
file name : Image_15092023123450236.png
|
2023-09-15 12:34:50.438807 |
163 |
57013403 |
Const of Pucca Drain from Anganwary center to Dutta pukur at Birajpur |
300000 |
Const of Pucca Drain from Anganwary center to Dutta pukur at Birajpur1 |
Completion of work |
-
latitude : 24.1005178,24.1005182
Longitude : 87.6881684,87.6881686
file name : Image_07092023131014689.png
|
2023-09-07 13:10:14.779028 |
164 |
56923724 |
Const of Pcc road from Dinesh Muemu to Bablu let house |
75000 |
Const of Pcc road from Dinesh Muemu to Bablu let house1 |
Roof laid |
-
latitude : 24.082597950473428,24.082597950473428
Longitude : 87.70952308550477,87.70952308550477
file name : Image_12092023143103664.png
|
2023-09-12 14:31:03.764437 |
165 |
56923724 |
Const of Pcc road from Dinesh Muemu to Bablu let house |
75000 |
Const of Pcc road from Dinesh Muemu to Bablu let house1 |
Plinth level |
-
latitude : 24.08253428991884,24.082475658506155
Longitude : 87.70981184206903,87.70980999805033
file name : Image_12092023142431025.png
|
2023-09-12 14:24:31.197649 |
166 |
56923724 |
Const of Pcc road from Dinesh Muemu to Bablu let house |
75000 |
Const of Pcc road from Dinesh Muemu to Bablu let house1 |
Completion of work |
-
latitude : 24.08256991300732,24.082575319334865
Longitude : 87.70955518819392,87.70960438996553
file name : Image_12092023141346902.png
|
2023-09-12 14:13:46.99082 |
167 |
57000652 |
Const of pcc road from Haru Kahar to Jayanto Kahar house at Sansad II |
75000 |
Const of pcc road from Haru Kahar to Jayanto Kahar house at Sansad II1 |
Roof laid |
-
latitude : 24.08316532149911,24.08312483690679
Longitude : 87.70811291411519,87.70814183168113
file name : Image_21092023151325657.png
|
2023-09-21 15:13:25.745535 |
168 |
57000652 |
Const of pcc road from Haru Kahar to Jayanto Kahar house at Sansad II |
75000 |
Const of pcc road from Haru Kahar to Jayanto Kahar house at Sansad II1 |
Plinth level |
-
latitude : 24.082005517557263,24.08199654892087
Longitude : 87.70844131708145,87.7084522973746
file name : Image_21092023150331146.png
|
2023-09-21 15:03:31.231341 |
169 |
57000652 |
Const of pcc road from Haru Kahar to Jayanto Kahar house at Sansad II |
75000 |
Const of pcc road from Haru Kahar to Jayanto Kahar house at Sansad II1 |
Completion of work |
-
latitude : 24.083160795271397,24.083144031465054
Longitude : 87.7080521453172,87.7080397401005
file name : Image_15092023123445239.png
|
2023-09-15 12:34:45.338782 |
170 |
57014567 |
Const of Pucca Drain from Bari Pukur to Canel at Mollarpur VI |
300000 |
Const of Pucca Drain from Bari Pukur to Canel at Mollarpur VI1 |
Roof laid |
-
latitude : 24.0797034278512,24.079732806421816
Longitude : 87.71384940482676,87.71378804929554
file name : Image_26092023125207999.png
|
2023-09-26 12:52:08.090774 |
171 |
57014567 |
Const of Pucca Drain from Bari Pukur to Canel at Mollarpur VI |
300000 |
Const of Pucca Drain from Bari Pukur to Canel at Mollarpur VI1 |
Plinth level |
-
latitude : 24.07947761937976,24.079494257457554
Longitude : 87.71383590996265,87.71376566961408
file name : Image_20092023140440928.png
|
2023-09-20 14:04:41.034193 |
172 |
57014567 |
Const of Pucca Drain from Bari Pukur to Canel at Mollarpur VI |
300000 |
Const of Pucca Drain from Bari Pukur to Canel at Mollarpur VI1 |
Completion of work |
-
latitude : 24.07967953942716,24.079678491689265
Longitude : 87.71388955414295,87.7139443717897
file name : Image_15092023123750650.png
|
2023-09-15 12:37:50.827785 |
173 |
57013532 |
Const of Pucca Drain From Ganseh Dalui to Sarbeswar Bauri at Mahishakura |
300000 |
Const of Pucca Drain From Ganseh Dalui to Sarbeswar Bauri at Mahishakura1 |
Roof laid |
-
latitude : 24.0783304,24.07866256311536
Longitude : 87.7041418,87.70428976044059
file name : Image_02102023122620077.png
|
2023-10-02 12:26:20.169409 |
174 |
57013532 |
Const of Pucca Drain From Ganseh Dalui to Sarbeswar Bauri at Mahishakura |
300000 |
Const of Pucca Drain From Ganseh Dalui to Sarbeswar Bauri at Mahishakura1 |
Plinth level |
-
latitude : 24.0785468,24.07867609988898
Longitude : 87.7040851,87.70434273406863
file name : Image_27092023155332846.png
|
2023-09-27 15:53:32.953825 |
175 |
57013532 |
Const of Pucca Drain From Ganseh Dalui to Sarbeswar Bauri at Mahishakura |
300000 |
Const of Pucca Drain From Ganseh Dalui to Sarbeswar Bauri at Mahishakura1 |
Completion of work |
-
latitude : 24.0783926,24.0784161
Longitude : 87.7041168,87.7040899
file name : Image_13092023130349230.png
|
2023-09-13 13:03:49.421133 |
176 |
57177572 |
Operation and Maintanence of Tubewell sansad Xi to XIII |
400000 |
Operation and Maintanence of Tubewell sansad Xi to XIII1 |
Completion of work |
-
latitude : 24.0767901
Longitude : 87.7026834
file name : Image_27092023160505497.png
|
2023-09-27 16:05:05.599868 |
177 |
57167665 |
Operation and Maintanence of tubewell Sansad VI to X |
400000 |
Operation and Maintanence of tubewell Sansad VI to X1 |
Plinth level |
-
latitude : 24.0768614
Longitude : 87.7027544
file name : Image_04012024125522966.png
|
2024-01-04 12:55:23.077337 |
178 |
57167665 |
Operation and Maintanence of tubewell Sansad VI to X |
400000 |
Operation and Maintanence of tubewell Sansad VI to X1 |
Completion of work |
-
latitude : 24.0768587
Longitude : 87.7027472
file name : Image_04012024125049008.png
|
2024-01-04 12:50:49.127743 |
179 |
71571491 |
Construction of roads |
200000 |
Construction of PCC Road From Meeting SK House towards Sohid Sk House at Modian |
Roof laid |
-
latitude : 24.069839562289417,24.069832772947848
Longitude : 87.69631588831544,87.69632468931377
file name : Image_26012024122438035.png
|
2024-01-26 12:24:38.13097 |
180 |
71571491 |
Construction of roads |
200000 |
Construction of PCC Road From Meeting SK House towards Sohid Sk House at Modian |
Plinth level |
-
latitude : 24.069863157346845,24.069824893958867
Longitude : 87.69626786001027,87.69627263769507
file name : Image_26012024122203949.png
|
2024-01-26 12:22:04.044362 |
181 |
71571491 |
Construction of roads |
200000 |
Construction of PCC Road From Meeting SK House towards Sohid Sk House at Modian |
Completion of work |
-
latitude : 24.069851506501436,24.069884615018964
Longitude : 87.69641546532512,87.69638068042696
file name : Image_26012024121944171.png
|
2024-01-26 12:19:44.2692 |
182 |
71568571 |
Construction of roads |
200000 |
Construction of PCC Road From Monsur Sk House towards Haradhan Sk House at Mollarpur |
Roof laid |
-
latitude : 24.0795533,24.0795533
Longitude : 87.7116634,87.7116634
file name : Image_26012024142737606.png
|
2024-01-26 14:27:37.699972 |
183 |
71568571 |
Construction of roads |
200000 |
Construction of PCC Road From Monsur Sk House towards Haradhan Sk House at Mollarpur |
Plinth level |
-
latitude : 24.0795533,24.0795533
Longitude : 87.7116634,87.7116634
file name : Image_26012024142323848.png
|
2024-01-26 14:23:23.941006 |
184 |
71568571 |
Construction of roads |
200000 |
Construction of PCC Road From Monsur Sk House towards Haradhan Sk House at Mollarpur |
Completion of work |
-
latitude : 24.07909649424255,24.0791042894125
Longitude : 87.71163406781852,87.71160850301385
file name : Image_10012024151600422.png
|
2024-01-10 15:16:00.514429 |
185 |
71578773 |
Construction of roads |
200000 |
Construction of PCC Road From Samir Sk House towards Canel Parchandrapur Muslimpara |
Roof laid |
-
latitude : 24.050323432311416,24.050355409272015
Longitude : 87.71558990702033,87.7155776694417
file name : Image_26012024121119449.png
|
2024-01-26 12:11:19.545864 |
186 |
71578773 |
Construction of roads |
200000 |
Construction of PCC Road From Samir Sk House towards Canel Parchandrapur Muslimpara |
Plinth level |
-
latitude : 24.050296400673687,24.050340615212917
Longitude : 87.71565671078861,87.7156070061028
file name : Image_18012024130038360.png
|
2024-01-18 13:00:38.439171 |
187 |
71578773 |
Construction of roads |
200000 |
Construction of PCC Road From Samir Sk House towards Canel Parchandrapur Muslimpara |
Completion of work |
-
latitude : 24.050256125628948,24.050239445641637
Longitude : 87.71546049043536,87.71538664586842
file name : Image_10012024124442285.png
|
2024-01-10 12:44:42.374456 |
188 |
71583831 |
Construction of Store Room in GP Bhawan |
300000 |
Renovation of GP Office Building and Construction of Store Room at Mollarpur Two GP Office |
Plinth level |
-
latitude : 24.0768363
Longitude : 87.7026904
file name : Image_02082024125535116.png
|
2024-08-02 12:55:35.223338 |
189 |
71583831 |
Construction of Store Room in GP Bhawan |
300000 |
Renovation of GP Office Building and Construction of Store Room at Mollarpur Two GP Office |
Completion of work |
-
latitude : 24.0768659
Longitude : 87.7027723
file name : Image_16012024122652175.png
|
2024-01-16 12:26:52.267184 |
190 |
71602027 |
Construction of roads |
350000 |
Construction of PCC Road From Sushil Saha House towards Ramesh Saha House at Mollarpur |
Roof laid |
-
latitude : 24.0779457,24.0779457
Longitude : 87.7118648,87.7118648
file name : Image_26012024141650364.png
|
2024-01-26 14:16:50.453321 |
191 |
71602027 |
Construction of roads |
350000 |
Construction of PCC Road From Sushil Saha House towards Ramesh Saha House at Mollarpur |
Plinth level |
-
latitude : 24.078465714119375,24.07846688758582
Longitude : 87.7123433444649,87.71234057843685
file name : Image_26012024121130979.png
|
2024-01-26 12:11:31.083486 |
192 |
71602027 |
Construction of roads |
350000 |
Construction of PCC Road From Sushil Saha House towards Ramesh Saha House at Mollarpur |
Completion of work |
-
latitude : 24.078536666929722,24.078536666929722
Longitude : 87.71288070827723,87.71288070827723
file name : Image_16012024113926439.png
|
2024-01-16 11:39:26.518817 |
193 |
71572615 |
Construction of roads |
200000 |
Construction of PCC Road From Badsa Mia House towards Kiram Mia House at Mollarpur |
Plinth level |
-
latitude : 24.0798527514562,24.079866665415466
Longitude : 87.71188829094172,87.71184504032135
file name : Image_19122023123535856.png
|
2023-12-19 12:35:38.165454 |
194 |
71572615 |
Construction of roads |
200000 |
Construction of PCC Road From Badsa Mia House towards Kiram Mia House at Mollarpur |
Plinth level |
-
latitude : 24.0798086,24.0798068
Longitude : 87.7116094,87.7116126
file name : Image_12122023122005780.png
|
2023-12-12 12:20:05.894856 |
195 |
71572615 |
Construction of roads |
200000 |
Construction of PCC Road From Badsa Mia House towards Kiram Mia House at Mollarpur |
Completion of work |
-
latitude : 24.0798086,24.0798079
Longitude : 87.7116096,87.7116121
file name : Image_08122023133728466.png
|
2023-12-08 13:37:28.552755 |
196 |
71562408 |
Construction of roads |
150000 |
Construction of PCC Road From Bablu Let House towards Rampada Sadhu House at Mahisakura |
Roof laid |
-
latitude : 24.087793054059148,24.08775923307985
Longitude : 87.6999600045383,87.69991340115666
file name : Image_09012024134620901.png
|
2024-01-09 13:46:20.989879 |
197 |
71562408 |
Construction of roads |
150000 |
Construction of PCC Road From Bablu Let House towards Rampada Sadhu House at Mahisakura |
Plinth level |
-
latitude : 24.087751982733607,24.0877894917503
Longitude : 87.69991608336568,87.69993360154331
file name : Image_09012024134414719.png
|
2024-01-09 13:44:14.817258 |
198 |
71562408 |
Construction of roads |
150000 |
Construction of PCC Road From Bablu Let House towards Rampada Sadhu House at Mahisakura |
Completion of work |
-
latitude : 24.087863168679178,24.087870963849127
Longitude : 87.69990845583379,87.69991130568087
file name : Image_29122023125133416.png
|
2023-12-29 12:51:33.521879 |
199 |
71489087 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain fron Rajesh sekh towards Hira Sekh House at Mollarpur |
Roof laid |
-
latitude : 24.081721412949264
Longitude : 87.71191854961216
file name : Image_10012024151930644.png
|
2024-01-10 15:19:30.746338 |
200 |
71489087 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain fron Rajesh sekh towards Hira Sekh House at Mollarpur |
Plinth level |
-
latitude : 24.081744672730565
Longitude : 87.71193564869463
file name : Image_29122023125129182.png
|
2023-12-29 12:51:29.276012 |
201 |
71489087 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain fron Rajesh sekh towards Hira Sekh House at Mollarpur |
Completion of work |
-
latitude : 24.081791024655104
Longitude : 87.71191762760282
file name : Image_08122023134030202.png
|
2023-12-08 13:40:30.276603 |
202 |
71602904 |
Construction of roads |
350000 |
Construction of PCC Road From Mohitosh Saha House towards Durga Mandir House at Mollarpur |
Roof laid |
-
latitude : 24.07754102256149,24.077534987591207
Longitude : 87.71394864656031,87.71394764073193
file name : Image_10012024135613167.png
|
2024-01-10 13:56:13.299243 |
203 |
71602904 |
Construction of roads |
350000 |
Construction of PCC Road From Mohitosh Saha House towards Durga Mandir House at Mollarpur |
Plinth level |
-
latitude : 24.078539684414864,24.078600998036563
Longitude : 87.71278825588524,87.7127574943006
file name : Image_04012024124519853.png
|
2024-01-04 12:45:19.943484 |
204 |
71602904 |
Construction of roads |
350000 |
Construction of PCC Road From Mohitosh Saha House towards Durga Mandir House at Mollarpur |
Completion of work |
-
latitude : 24.078550916165113,24.078562608920038
Longitude : 87.71262330003083,87.71266411989927
file name : Image_08122023134659312.png
|
2023-12-08 13:46:59.412757 |
205 |
71490457 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain From Modan Let House towards Arun Let House at Mollarpur |
Roof laid |
-
latitude : 24.081894708797336
Longitude : 87.71004309877753
file name : Image_04012024141927726.png
|
2024-01-04 14:19:27.813858 |
206 |
71490457 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain From Modan Let House towards Arun Let House at Mollarpur |
Plinth level |
-
latitude : 24.081881884485483
Longitude : 87.7099737804383
file name : Image_04012024141034720.png
|
2024-01-04 14:10:34.810878 |
207 |
71490457 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain From Modan Let House towards Arun Let House at Mollarpur |
Completion of work |
-
latitude : 24.0819078264758
Longitude : 87.7099481318146
file name : Image_12122023123244037.png
|
2023-12-12 12:32:44.136338 |
208 |
71485975 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Sunil Pal House towards Suboth Ganguli House At Mollar |
Roof laid |
-
latitude : 24.081759215332568
Longitude : 87.7077654004097
file name : Image_15012024162543518.png
|
2024-01-15 16:25:43.616186 |
209 |
71485975 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Sunil Pal House towards Suboth Ganguli House At Mollar |
Plinth level |
-
latitude : 24.081538813188672
Longitude : 87.70794418640435
file name : Image_22122023135013602.png
|
2023-12-22 13:50:13.705019 |
210 |
71485975 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Sunil Pal House towards Suboth Ganguli House At Mollar |
Completion of work |
-
latitude : 24.08161806408316
Longitude : 87.70790797658265
file name : Image_08122023132034671.png
|
2023-12-08 13:20:34.772952 |
211 |
71492995 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain from Nur Alam SK House towards Bayen Para at Parchandrapur |
Roof laid |
-
latitude : 24.05082177836448
Longitude : 87.7143529895693
file name : Image_30012024131343931.png
|
2024-01-30 13:13:44.087371 |
212 |
71492995 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain from Nur Alam SK House towards Bayen Para at Parchandrapur |
Roof laid |
-
latitude : 24.050632431171834
Longitude : 87.71438148804009
file name : Image_30012024131242282.png
|
2024-01-30 13:12:42.398545 |
213 |
71492995 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain from Nur Alam SK House towards Bayen Para at Parchandrapur |
Plinth level |
-
latitude : 24.050622791983187
Longitude : 87.71438819356263
file name : Image_30012024130325673.png
|
2024-01-30 13:03:25.771249 |
214 |
71492995 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain from Nur Alam SK House towards Bayen Para at Parchandrapur |
Completion of work |
-
latitude : 24.05062882695347
Longitude : 87.71431032568216
file name : Image_10012024124915097.png
|
2024-01-10 12:49:15.18563 |
215 |
71479080 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Tuten sekh towards Bablu Sekh House at Mdian |
Roof laid |
-
latitude : 24.069821792654693
Longitude : 87.69307502545416
file name : Image_11012024135723951.png
|
2024-01-11 13:57:24.047187 |
216 |
71479080 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Tuten sekh towards Bablu Sekh House at Mdian |
Plinth level |
-
latitude : 24.06986977905035
Longitude : 87.69316270016134
file name : Image_02012024154423117.png
|
2024-01-02 15:44:23.200951 |
217 |
71479080 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Tuten sekh towards Bablu Sekh House at Mdian |
Completion of work |
-
latitude : 24.06982849817723
Longitude : 87.69311961717904
file name : Image_08122023140900007.png
|
2023-12-08 14:09:00.114772 |
218 |
71487355 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain From Mahalay House towards Nemai Mondal House At Mollarpur |
Roof laid |
-
latitude : 24.0797634
Longitude : 87.7047638
file name : Image_10012024151233775.png
|
2024-01-10 15:12:33.864039 |
219 |
71487355 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain From Mahalay House towards Nemai Mondal House At Mollarpur |
Roof laid |
-
latitude : 24.07996133901179
Longitude : 87.70476174540818
file name : Image_10012024151228627.png
|
2024-01-10 15:12:28.757449 |
220 |
71487355 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain From Mahalay House towards Nemai Mondal House At Mollarpur |
Plinth level |
-
latitude : 24.0797525
Longitude : 87.7047666
file name : Image_29122023125248791.png
|
2023-12-29 12:52:48.883036 |
221 |
71487355 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain From Mahalay House towards Nemai Mondal House At Mollarpur |
Completion of work |
-
latitude : 24.079330475069582
Longitude : 87.7045429777354
file name : Image_08122023130639488.png
|
2023-12-08 13:06:39.587291 |
222 |
71487355 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain From Mahalay House towards Nemai Mondal House At Mollarpur |
Completion of work |
-
latitude : 24.07933604903519
Longitude : 87.70455764606595
file name : Image_08122023130412601.png
|
2023-12-08 13:04:12.692758 |
223 |
71475611 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Mukhagnitala towards Culvert at Mehedinagar |
Roof laid |
-
latitude : 24.0710777
Longitude : 87.6984456
file name : Image_26012024121136212.png
|
2024-01-26 12:11:36.303176 |
224 |
71475611 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Mukhagnitala towards Culvert at Mehedinagar |
Plinth level |
-
latitude : 24.0770553
Longitude : 87.7002828
file name : Image_16012024120402892.png
|
2024-01-16 12:04:03.008462 |
225 |
71475611 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Mukhagnitala towards Culvert at Mehedinagar |
Completion of work |
-
latitude : 24.072665604762733
Longitude : 87.69866902381182
file name : Image_08122023135803744.png
|
2023-12-08 13:58:03.843151 |
226 |
71929506 |
Electricity |
150000 |
Electricity1 |
Plinth level |
-
latitude : 24.0768828
Longitude : 87.7027445
file name : Image_03062024165822590.png
|
2024-06-03 16:58:22.69783 |
227 |
71929506 |
Electricity |
150000 |
Electricity1 |
Completion of work |
-
latitude : 24.0768507
Longitude : 87.7026471
file name : Image_20052024125402202.png
|
2024-05-20 12:54:02.315394 |
228 |
71484312 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Prallahad Roy House towards Mukti Bauri House At Molla |
Plinth level |
-
latitude : 24.0783354
Longitude : 87.7041425
file name : Image_06022024131728124.png
|
2024-02-06 13:17:28.210463 |
229 |
71484312 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Prallahad Roy House towards Mukti Bauri House At Molla |
Completion of work |
-
latitude : 24.078761134296656
Longitude : 87.70430317148566
file name : Image_16012024120203972.png
|
2024-01-16 12:02:04.091983 |
230 |
71574161 |
Construction of roads |
200000 |
Constructoin of PCC Road From Law pukur towards Nishakar Let House at Mollarpur |
Plinth level |
-
latitude : 24.083967050537467,24.083966044709086
Longitude : 87.70770505070686,87.70770404487848
file name : Image_14122023122849057.png
|
2023-12-14 12:28:49.152135 |
231 |
71574161 |
Construction of roads |
200000 |
Constructoin of PCC Road From Law pukur towards Nishakar Let House at Mollarpur |
Completion of work |
-
latitude : 24.083441966213286,24.083417365327477
Longitude : 87.70743942819536,87.70742853172123
file name : Image_08122023131342501.png
|
2023-12-08 13:13:42.593541 |
232 |
71494559 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain from Avijit Mondal House towards Nandadulal Mondal House Pa |
Roof laid |
-
latitude : 24.04823059681803
Longitude : 87.71066939458251
file name : Image_15032024150809778.png
|
2024-03-15 15:08:09.869132 |
233 |
71494559 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain from Avijit Mondal House towards Nandadulal Mondal House Pa |
Roof laid |
-
latitude : 24.048267393372953
Longitude : 87.71071172319353
file name : Image_14032024170055152.png
|
2024-03-14 17:00:55.260052 |
234 |
71494559 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain from Avijit Mondal House towards Nandadulal Mondal House Pa |
Plinth level |
-
latitude : 24.04819132760167
Longitude : 87.71071683615446
file name : Image_14032024162908619.png
|
2024-03-14 16:29:08.717052 |
235 |
71494559 |
Drainage Construction |
220000 |
Construction of RCC Cover Slab With PCC Drain from Avijit Mondal House towards Nandadulal Mondal House Pa |
Completion of work |
-
latitude : 24.048262992873788
Longitude : 87.71099167875946
file name : Image_10012024131624122.png
|
2024-01-10 13:16:24.209371 |
236 |
71472709 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Birajpur Pry School towards Cham Pond at Birajpur |
Roof laid |
-
latitude : 24.098632405512035
Longitude : 87.6878647506237
file name : Image_06022024135620281.png
|
2024-02-06 13:56:20.386736 |
237 |
71472709 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Birajpur Pry School towards Cham Pond at Birajpur |
Roof laid |
-
latitude : 24.0784861
Longitude : 87.704088
file name : Image_06022024132645358.png
|
2024-02-06 13:26:45.454683 |
238 |
71472709 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Birajpur Pry School towards Cham Pond at Birajpur |
Plinth level |
-
latitude : 24.09864774439484
Longitude : 87.68783206120133
file name : Image_31012024120920770.png
|
2024-01-31 12:09:20.864809 |
239 |
71472709 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Birajpur Pry School towards Cham Pond at Birajpur |
Completion of work |
-
latitude : 24.09861404914409
Longitude : 87.68673076294363
file name : Image_22122023133502791.png
|
2023-12-22 13:35:02.88436 |
240 |
57178101 |
Sinking and Resinking of Tubewell of Various Sansad under mollarpur two gp |
358060 |
Sinking and Resinking of Tubewell of Various Sansad under mollarpur two gp1 |
Roof laid |
-
latitude : 24.0767875
Longitude : 87.7026037
file name : Image_01042024130228561.png
|
2024-04-01 13:02:28.683613 |
241 |
57178101 |
Sinking and Resinking of Tubewell of Various Sansad under mollarpur two gp |
358060 |
Sinking and Resinking of Tubewell of Various Sansad under mollarpur two gp1 |
Plinth level |
-
latitude : 24.0768426
Longitude : 87.7026901
file name : Image_01042024125239240.png
|
2024-04-01 12:52:39.327367 |
242 |
57178101 |
Sinking and Resinking of Tubewell of Various Sansad under mollarpur two gp |
358060 |
Sinking and Resinking of Tubewell of Various Sansad under mollarpur two gp1 |
Completion of work |
-
latitude : 24.0767957
Longitude : 87.7026369
file name : Image_19052023143203637.png
|
2023-05-19 14:32:03.736676 |
243 |
67220507 |
Construction of Community Sanitary Complex |
188500 |
Construction of Community Sanitary Complex |
Roof laid |
-
latitude : 24.052046
Longitude : 87.7124116
file name : Image_27062024091539281.png
|
2024-06-27 09:15:39.388977 |
244 |
67220507 |
Construction of Community Sanitary Complex |
188500 |
Construction of Community Sanitary Complex |
Plinth level |
-
latitude : 24.0517954
Longitude : 87.7122465
file name : Image_01042024155205035.png
|
2024-04-01 15:52:05.124746 |
245 |
67220507 |
Construction of Community Sanitary Complex |
188500 |
Construction of Community Sanitary Complex |
Plinth level |
-
latitude : 24.0517954
Longitude : 87.7122465
file name : Image_01042024155158919.png
|
2024-04-01 15:51:59.006954 |
246 |
67220507 |
Construction of Community Sanitary Complex |
188500 |
Construction of Community Sanitary Complex |
Completion of work |
-
latitude : 24.050767673179507
Longitude : 87.71228617988527
file name : Image_15122023131246322.png
|
2023-12-15 13:12:46.452459 |
247 |
71338758 |
Operation and Maintenance of drinking water supply system |
978060 |
Operation and Maintenance of drinking water supply system1 |
Plinth level |
-
latitude : 24.0768038
Longitude : 87.7026384
file name : Image_03072024165511324.png
|
2024-07-03 16:55:11.411965 |
248 |
71338758 |
Operation and Maintenance of drinking water supply system |
978060 |
Operation and Maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 24.076864
Longitude : 87.7027401
file name : Image_03072024165255167.png
|
2024-07-03 16:52:55.255783 |
249 |
98717457 |
Water Supply to villages |
183060 |
Repairing and maintenance of Submarcible Pump with pipeline at Mollarpur two GP Area |
Roof laid |
-
latitude : 24.079983299598098
Longitude : 87.71057451143861
file name : Image_24092024154218522.png
|
2024-09-24 15:42:18.600731 |
250 |
98717457 |
Water Supply to villages |
183060 |
Repairing and maintenance of Submarcible Pump with pipeline at Mollarpur two GP Area |
Plinth level |
-
latitude : 24.07998103648424
Longitude : 87.71061952225864
file name : Image_24092024153140597.png
|
2024-09-24 15:31:40.764717 |
251 |
98717457 |
Water Supply to villages |
183060 |
Repairing and maintenance of Submarcible Pump with pipeline at Mollarpur two GP Area |
Completion of work |
-
latitude : 24.079899983480573
Longitude : 87.71054450422525
file name : Image_24092024152845648.png
|
2024-09-24 15:28:45.767146 |
252 |
71523039 |
Drainage Construction |
130000 |
Construction of RCC Cover Slab at Both Side of NH14 Drain |
Plinth level |
-
latitude : 24.07700034789741
Longitude : 87.70974537357688
file name : Image_24092024155603152.png
|
2024-09-24 15:56:03.240211 |
253 |
71523039 |
Drainage Construction |
130000 |
Construction of RCC Cover Slab at Both Side of NH14 Drain |
Completion of work |
-
latitude : 24.077060697600245
Longitude : 87.70981142297387
file name : Image_24092024155126286.png
|
2024-09-24 15:51:26.386881 |
254 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 24.076601495034993
Longitude : 87.70680047571659
file name : Image_15072024150259699.png
|
2024-07-15 15:02:59.863783 |
255 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 24.076617755927145
Longitude : 87.70681631751359
file name : Image_15072024145912130.png
|
2024-07-15 14:59:12.286068 |
256 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 24.07661679200828
Longitude : 87.7067582309246
file name : Image_15072024145455526.png
|
2024-07-15 14:54:55.633594 |
257 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water2 |
Roof laid |
-
latitude : 24.076590640470386
Longitude : 87.70680718123913
file name : Image_15072024150314340.png
|
2024-07-15 15:03:14.499669 |
258 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water2 |
Roof laid |
-
latitude : 24.076590640470386
Longitude : 87.70680718123913
file name : Image_15072024150304217.png
|
2024-07-15 15:03:04.426539 |
259 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water2 |
Plinth level |
-
latitude : 24.076586994342506
Longitude : 87.70679636858404
file name : Image_15072024145917352.png
|
2024-07-15 14:59:17.479119 |
260 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water2 |
Completion of work |
-
latitude : 24.076612894423306
Longitude : 87.70681363530457
file name : Image_15072024145459782.png
|
2024-07-15 14:54:59.887325 |
261 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water3 |
Roof laid |
-
latitude : 24.076631292700768
Longitude : 87.70677985623479
file name : Image_15072024150319123.png
|
2024-07-15 15:03:19.285372 |
262 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water3 |
Roof laid |
-
latitude : 24.076631292700768
Longitude : 87.70677985623479
file name : Image_15072024150309048.png
|
2024-07-15 15:03:09.19277 |
263 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water3 |
Plinth level |
-
latitude : 24.07661993522197
Longitude : 87.70680223591626
file name : Image_15072024145922351.png
|
2024-07-15 14:59:22.467558 |
264 |
71377738 |
Creation of a new source of drinking water |
105000 |
Creation of a new source of drinking water3 |
Completion of work |
-
latitude : 24.07663338817656
Longitude : 87.70679913461208
file name : Image_15072024145506930.png
|
2024-07-15 14:55:07.111958 |
265 |
71399976 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 24.0569419
Longitude : 87.7150316
file name : Image_16072024170232206.png
|
2024-07-16 17:02:32.308618 |
266 |
71399976 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 24.0569423
Longitude : 87.7150349
file name : Image_16072024165747227.png
|
2024-07-16 16:57:47.324871 |
267 |
71399976 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 24.06519066542387
Longitude : 87.71908214315772
file name : Image_16072024165406383.png
|
2024-07-16 16:54:06.488985 |
268 |
71399976 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Roof laid |
-
latitude : 24.0569419
Longitude : 87.7150327
file name : Image_16072024170244758.png
|
2024-07-16 17:02:44.880368 |
269 |
71399976 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Roof laid |
-
latitude : 24.0569419
Longitude : 87.7150327
file name : Image_16072024170236707.png
|
2024-07-16 17:02:36.813642 |
270 |
71399976 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Plinth level |
-
latitude : 24.065216397866607
Longitude : 87.71910645067692
file name : Image_16072024165856284.png
|
2024-07-16 16:58:56.379359 |
271 |
71399976 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Completion of work |
-
latitude : 24.06523781362921
Longitude : 87.71908708848059
file name : Image_16072024165422368.png
|
2024-07-16 16:54:22.469339 |
272 |
71399976 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Completion of work |
-
latitude : 24.06523781362921
Longitude : 87.71908708848059
file name : Image_16072024165413630.png
|
2024-07-16 16:54:13.726909 |
273 |
71381565 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 24.0697044
Longitude : 87.692299
file name : Image_15072024153309576.png
|
2024-07-15 15:33:09.661648 |
274 |
71381565 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 24.0701472
Longitude : 87.6908629
file name : Image_15072024153000483.png
|
2024-07-15 15:30:00.569943 |
275 |
71381565 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 24.06964891590178
Longitude : 87.69204740412533
file name : Image_15072024152647281.png
|
2024-07-15 15:26:47.368543 |
276 |
71381565 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Roof laid |
-
latitude : 24.0696592
Longitude : 87.6923405
file name : Image_15072024153315367.png
|
2024-07-15 15:33:15.462542 |
277 |
71381565 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Plinth level |
-
latitude : 24.0697079
Longitude : 87.6922848
file name : Image_15072024153005898.png
|
2024-07-15 15:30:05.98695 |
278 |
71381565 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Completion of work |
-
latitude : 24.069646359421313
Longitude : 87.6920695323497
file name : Image_15072024152653844.png
|
2024-07-15 15:26:53.917585 |
279 |
71385740 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 24.06908862758428
Longitude : 87.70717020146549
file name : Image_15072024151824484.png
|
2024-07-15 15:18:24.587566 |
280 |
71385740 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 24.069101703353226
Longitude : 87.70719115622342
file name : Image_15072024151634536.png
|
2024-07-15 15:16:34.621686 |
281 |
71385740 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 24.069154551252723
Longitude : 87.7071657590568
file name : Image_15072024151146945.png
|
2024-07-15 15:11:47.055658 |
282 |
71385740 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Roof laid |
-
latitude : 24.0691048046574
Longitude : 87.70718210376799
file name : Image_15072024151829776.png
|
2024-07-15 15:18:29.880574 |
283 |
71385740 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Plinth level |
-
latitude : 24.06914122402668
Longitude : 87.70718964748085
file name : Image_15072024151640612.png
|
2024-07-15 15:16:40.719312 |
284 |
71385740 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Completion of work |
-
latitude : 24.069087454117835
Longitude : 87.7071490790695
file name : Image_15072024151152614.png
|
2024-07-15 15:11:52.706036 |
285 |
71401193 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 24.04839894734323
Longitude : 87.71425969898701
file name : Image_12072024152518317.png
|
2024-07-12 15:25:18.420637 |
286 |
71401193 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 24.048384320922196
Longitude : 87.71424972452223
file name : Image_12072024151505367.png
|
2024-07-12 15:15:05.477484 |
287 |
71401193 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 24.048394630663097
Longitude : 87.71427168510854
file name : Image_12072024145508099.png
|
2024-07-12 14:55:08.246999 |
288 |
71401193 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Roof laid |
-
latitude : 24.048365210182965
Longitude : 87.7142654825002
file name : Image_12072024152610082.png
|
2024-07-12 15:26:10.177634 |
289 |
71401193 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Plinth level |
-
latitude : 24.048419608734548
Longitude : 87.71420898847282
file name : Image_12072024151557804.png
|
2024-07-12 15:15:57.922181 |
290 |
71401193 |
Creation of a new source of drinking water |
70000 |
Creation of a new source of drinking water2 |
Completion of work |
-
latitude : 24.048397396691144
Longitude : 87.71426565013826
file name : Image_12072024145613347.png
|
2024-07-12 14:56:13.443861 |
291 |
71474249 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Ananwari Kaendra towards Pry School at Gayespur |
Roof laid |
-
latitude : 24.051570701412857
Longitude : 87.70429252646863
file name : Image_05082024125446801.png
|
2024-08-05 12:54:46.896622 |
292 |
71474249 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Ananwari Kaendra towards Pry School at Gayespur |
Plinth level |
-
latitude : 24.0645027
Longitude : 87.7192997
file name : Image_01082024114722605.png
|
2024-08-01 11:47:22.715644 |
293 |
71474249 |
Drainage Construction |
200000 |
Construction of RCC Cover Slab With PCC Drain From Ananwari Kaendra towards Pry School at Gayespur |
Completion of work |
-
latitude : 24.051443757489324
Longitude : 87.70425321534276
file name : Image_18072024134633933.png
|
2024-07-18 13:46:34.054309 |
294 |
71575489 |
Construction of roads |
200000 |
Construction of PCC Road From BR Road towards Rilgate at Rukunpur |
Roof laid |
-
latitude : 24.061137135140598,24.061124939471483
Longitude : 87.71754213608801,87.71758203394711
file name : Image_23072024172105145.png
|
2024-07-23 17:21:05.254965 |
295 |
71575489 |
Construction of roads |
200000 |
Construction of PCC Road From BR Road towards Rilgate at Rukunpur |
Plinth level |
-
latitude : 24.061141996644437,24.061066936701536
Longitude : 87.7175495121628,87.71752269007266
file name : Image_23072024171608084.png
|
2024-07-23 17:16:08.181469 |
296 |
71575489 |
Construction of roads |
200000 |
Construction of PCC Road From BR Road towards Rilgate at Rukunpur |
Completion of work |
-
latitude : 24.061177745461464,24.06116190366447
Longitude : 87.7170521300286,87.71713083609939
file name : Image_16072024170943129.png
|
2024-07-16 17:09:43.248491 |
297 |
71564369 |
Construction of roads |
150000 |
Construction of PCC Road From Goutam Panda House towards Samir Panda House at Mollarpur |
Roof laid |
-
latitude : 24.07767052296549,24.077669559046626
Longitude : 87.70636822097003,87.70636696368456
file name : Image_01082024134641381.png
|
2024-08-01 13:46:41.477941 |
298 |
71564369 |
Construction of roads |
150000 |
Construction of PCC Road From Goutam Panda House towards Samir Panda House at Mollarpur |
Plinth level |
-
latitude : 24.07767630647868,24.077678946778178
Longitude : 87.7063369564712,87.70633628591895
file name : Image_01082024134523640.png
|
2024-08-01 13:45:23.742477 |
299 |
71564369 |
Construction of roads |
150000 |
Construction of PCC Road From Goutam Panda House towards Samir Panda House at Mollarpur |
Plinth level |
-
latitude : 24.077975121326745,24.077975121326745
Longitude : 87.70627224817872,87.70627224817872
file name : Image_01082024114600531.png
|
2024-08-01 11:46:00.625478 |
300 |
71564369 |
Construction of roads |
150000 |
Construction of PCC Road From Goutam Panda House towards Samir Panda House at Mollarpur |
Completion of work |
-
latitude : 24.077561097219586,24.07755812164396
Longitude : 87.70636914297938,87.70637123845518
file name : Image_18072024140223728.png
|
2024-07-18 14:02:23.830851 |
301 |
98540717 |
Construction of roads |
140000 |
Construction of PCC road from Babar Ali towards Ismatara Begam house at Mollarpur Seven |
Plinth level |
-
latitude : 24.076754129491746,24.076754129491746,24.076749980449677
Longitude : 87.71922731772065,87.71922731772065,87.71931398659945
file name : Image_25112024134749374.png
|
2024-11-25 13:47:49.474537 |
302 |
98540717 |
Construction of roads |
140000 |
Construction of PCC road from Babar Ali towards Ismatara Begam house at Mollarpur Seven |
Completion of work |
-
latitude : 24.0759562,24.0759562
Longitude : 87.7197172,87.7197172
file name : Image_29102024132454418.png
|
2024-10-29 13:24:54.515586 |
303 |
98541934 |
Construction of roads |
100000 |
Construction of PCC road from Somadish Let house towards Sima Let house at Mollarpur eight |
Roof laid |
-
latitude : 24.081716719083488,24.081716467626393
Longitude : 87.71060426719487,87.7106056921184
file name : Image_06112024130153032.png
|
2024-11-06 13:01:53.114885 |
304 |
98541934 |
Construction of roads |
100000 |
Construction of PCC road from Somadish Let house towards Sima Let house at Mollarpur eight |
Plinth level |
-
latitude : 24.08170992974192,24.08171923365444
Longitude : 87.71060996688902,87.71064802072942
file name : Image_06112024125907254.png
|
2024-11-06 12:59:07.339763 |
305 |
98541934 |
Construction of roads |
100000 |
Construction of PCC road from Somadish Let house towards Sima Let house at Mollarpur eight |
Completion of work |
-
latitude : 24.081671121530235,24.081670702435076
Longitude : 87.71058423444629,87.71058473736048
file name : Image_29102024132448176.png
|
2024-10-29 13:24:48.280002 |
306 |
98543121 |
Construction of roads |
100000 |
Construction of PCC road from Dalim Sk house towards Anarul Sk house at Mehendinagar |
Completion of work |
-
latitude : 24.06904671806842,24.069041437469423
Longitude : 87.70096281543374,87.70095627754927
file name : Image_04102024145217894.png
|
2024-10-04 14:52:17.997198 |
307 |
98575579 |
Construction of roads |
100000 |
Construction of PCC road from Pradip Das house towards Raju Bagdi house at Prachandrapur |
Roof laid |
-
latitude : 24.047285285778344,24.04728432185948
Longitude : 87.71407613530755,87.71407722495496
file name : Image_06112024132309282.png
|
2024-11-06 13:23:09.368648 |
308 |
98575579 |
Construction of roads |
100000 |
Construction of PCC road from Pradip Das house towards Raju Bagdi house at Prachandrapur |
Plinth level |
-
latitude : 24.047297900542617,24.047307246364653
Longitude : 87.71413514390588,87.71413296461105
file name : Image_06112024131623498.png
|
2024-11-06 13:16:23.598792 |
309 |
98575579 |
Construction of roads |
100000 |
Construction of PCC road from Pradip Das house towards Raju Bagdi house at Prachandrapur |
Completion of work |
-
latitude : 24.0768559,24.0768559
Longitude : 87.7027731,87.7027731
file name : Image_29102024132512535.png
|
2024-10-29 13:25:12.664755 |
310 |
98575579 |
Construction of roads |
100000 |
Construction of PCC road from Pradip Das house towards Raju Bagdi house at Prachandrapur |
Completion of work |
-
latitude : 24.0768559,24.0768559,24.0768559
Longitude : 87.7027731,87.7027731,87.7027731
file name : Image_29102024132505505.png
|
2024-10-29 13:25:05.628096 |
311 |
98575579 |
Construction of roads |
100000 |
Construction of PCC road from Pradip Das house towards Raju Bagdi house at Prachandrapur |
Completion of work |
-
latitude : 24.047583513893187,24.047583513893187,24.047586154192686
Longitude : 87.71398502402008,87.71398502402008,87.71400036290288
file name : Image_05112024133734490.png
|
2024-11-05 13:37:34.626865 |
312 |
98524668 |
Construction of roads |
190000 |
Construction of PCC road from Astam Mondal house towards Sanaka Mondal house Mollarpur four |
Completion of work |
-
latitude : 24.081573681905866,24.08157372381538
Longitude : 87.70581283606589,87.70581266842782
file name : Image_04102024114032641.png
|
2024-10-04 11:40:32.815966 |
313 |
98734353 |
Construction of roads |
250000 |
Construction of PCC road from Tapan Mondal house towards Saraswati Let house Mollarpur nine for tribal de |
Plinth level |
-
latitude : 24.080658671446145,24.080658671446145
Longitude : 87.70940029062331,87.70940029062331
file name : Image_16112024110346020.png
|
2024-11-16 11:03:46.108654 |
314 |
98734353 |
Construction of roads |
250000 |
Construction of PCC road from Tapan Mondal house towards Saraswati Let house Mollarpur nine for tribal de |
Completion of work |
-
latitude : 24.080511066131294,24.080513203516603
Longitude : 87.70949098281562,87.70949400030077
file name : Image_04102024141734355.png
|
2024-10-04 14:17:34.451452 |
315 |
71498987 |
Drainage Construction |
218060 |
Construction of RCC Cover Slab With PCC Drain from Railgate towards Monirul Islam House at Rukunpu |
Roof laid |
-
latitude : 24.061408918350935
Longitude : 87.71539838053286
file name : Image_16072024170730844.png
|
2024-07-16 17:07:30.941152 |
316 |
71498987 |
Drainage Construction |
218060 |
Construction of RCC Cover Slab With PCC Drain from Railgate towards Monirul Islam House at Rukunpu |
Plinth level |
-
latitude : 24.061389472335577
Longitude : 87.71539645269513
file name : Image_01042024153722552.png
|
2024-04-01 15:37:22.641978 |
317 |
71498987 |
Drainage Construction |
218060 |
Construction of RCC Cover Slab With PCC Drain from Railgate towards Monirul Islam House at Rukunpu |
Completion of work |
-
latitude : 24.061446259729564
Longitude : 87.71536661311984
file name : Image_26012024121125304.png
|
2024-01-26 12:11:25.39919 |
318 |
98525128 |
Construction of roads |
190000 |
Construction of PCC road from Prasanta Mondal house towards Bankim Mondal house |
Plinth level |
-
latitude : 24.078954211436212,24.078958737663925
Longitude : 87.70644734613597,87.70642672665417
file name : Image_19112024143703709.png
|
2024-11-19 14:37:03.9112 |
319 |
98525128 |
Construction of roads |
190000 |
Construction of PCC road from Prasanta Mondal house towards Bankim Mondal house |
Plinth level |
-
latitude : 24.078775299713016,24.078772659413517,24.078814359381795
Longitude : 87.70640677772462,87.70640627481043,87.70666125230491
file name : Image_16112024110357332.png
|
2024-11-16 11:03:57.42005 |
320 |
98525128 |
Construction of roads |
190000 |
Construction of PCC road from Prasanta Mondal house towards Bankim Mondal house |
Completion of work |
-
latitude : 24.07732430845499,24.07736215274781
Longitude : 87.70999565720558,87.71000571548939
file name : Image_04102024113335892.png
|
2024-10-04 11:33:35.987949 |
321 |
98736457 |
Construction of roads |
200000 |
Construction of PCC road from Nishakar Let house towards Swapan Mondal Land at Mollarpur four |
Plinth level |
-
latitude : 24.084546617232263,24.084546617232263,24.084546617232263
Longitude : 87.70838800817728,87.70838800817728,87.70838800817728
file name : Image_14112024135300503.png
|
2024-11-14 13:53:00.594164 |
322 |
98736457 |
Construction of roads |
200000 |
Construction of PCC road from Nishakar Let house towards Swapan Mondal Land at Mollarpur four |
Plinth level |
-
latitude : 24.084569164551795,24.084569164551795,24.084569164551795
Longitude : 87.70838691852987,87.70838691852987,87.70838691852987
file name : Image_14112024135241020.png
|
2024-11-14 13:52:41.144646 |
323 |
98736457 |
Construction of roads |
200000 |
Construction of PCC road from Nishakar Let house towards Swapan Mondal Land at Mollarpur four |
Plinth level |
-
latitude : 24.084569164551795,24.084569164551795,24.084569164551795
Longitude : 87.70838691852987,87.70838691852987,87.70838691852987
file name : Image_14112024134949310.png
|
2024-11-14 13:49:49.414169 |
324 |
98736457 |
Construction of roads |
200000 |
Construction of PCC road from Nishakar Let house towards Swapan Mondal Land at Mollarpur four |
Completion of work |
-
latitude : 24.084584419615567,24.084584419615567
Longitude : 87.70844768732786,87.70844768732786
file name : Image_14112024095354005.png
|
2024-11-14 09:53:54.134393 |
325 |
98736457 |
Construction of roads |
200000 |
Construction of PCC road from Nishakar Let house towards Swapan Mondal Land at Mollarpur four |
Completion of work |
-
latitude : 24.084260375238955,24.084260878153145
Longitude : 87.70786430686712,87.70784737542272
file name : Image_29102024132442045.png
|
2024-10-29 13:24:42.197167 |
326 |
71566788 |
Construction of roads |
100000 |
Construction of PCC Road From Laxmitala at Mollarpur |
Roof laid |
-
latitude : 24.078189069405198,24.07818936277181
Longitude : 87.70636319182813,87.70636344328523
file name : Image_21082024115110111.png
|
2024-08-21 11:51:10.206502 |
327 |
71566788 |
Construction of roads |
100000 |
Construction of PCC Road From Laxmitala at Mollarpur |
Plinth level |
-
latitude : 24.07830821815878,24.078297656960785
Longitude : 87.70643083378673,87.70642781630158
file name : Image_21082024114722898.png
|
2024-08-21 11:47:23.003843 |
328 |
71566788 |
Construction of roads |
100000 |
Construction of PCC Road From Laxmitala at Mollarpur |
Completion of work |
-
latitude : 24.078294136561453,24.078297154046595
Longitude : 87.7064561471343,87.70645740441978
file name : Image_01082024115146201.png
|
2024-08-01 11:51:46.363919 |
329 |
71566788 |
Construction of roads |
100000 |
Construction of PCC Road From Laxmitala at Mollarpur |
Completion of work |
-
latitude : 24.078365131281316,24.07834141049534
Longitude : 87.70650233142078,87.70649168640375
file name : Image_01082024114959848.png
|
2024-08-01 11:49:59.98298 |
330 |
98575923 |
Construction of roads |
140740 |
Construction of PCC road from Rail Gate towards Sukhen Sk House at Prachandrapur |
Roof laid |
-
latitude : 24.0542985,24.0542985,24.0542985
Longitude : 87.7128721,87.7128721,87.7128721
file name : Image_16112024124302979.png
|
2024-11-16 12:43:03.104734 |
331 |
98575923 |
Construction of roads |
140740 |
Construction of PCC road from Rail Gate towards Sukhen Sk House at Prachandrapur |
Plinth level |
-
latitude : 24.053965201601386,24.053965201601386,24.053965201601386,24.053965201601386
Longitude : 87.71142477169633,87.71142477169633,87.71142477169633,87.71142477169633
file name : Image_14112024135253984.png
|
2024-11-14 13:52:54.126004 |
332 |
98575923 |
Construction of roads |
140740 |
Construction of PCC road from Rail Gate towards Sukhen Sk House at Prachandrapur |
Plinth level |
-
latitude : 24.053964279592037,24.053964279592037,24.053964279592037
Longitude : 87.71128973923624,87.71128973923624,87.71128973923624
file name : Image_14112024135247562.png
|
2024-11-14 13:52:47.642482 |
333 |
98575923 |
Construction of roads |
140740 |
Construction of PCC road from Rail Gate towards Sukhen Sk House at Prachandrapur |
Plinth level |
-
latitude : 24.053964279592037,24.053964279592037,24.053964279592037
Longitude : 87.71128973923624,87.71128973923624,87.71128973923624
file name : Image_14112024135004959.png
|
2024-11-14 13:50:05.044013 |
334 |
98575923 |
Construction of roads |
140740 |
Construction of PCC road from Rail Gate towards Sukhen Sk House at Prachandrapur |
Completion of work |
-
latitude : 24.053775393404067,24.05377950053662
Longitude : 87.71208945661783,87.71208082325757
file name : Image_05112024133742088.png
|
2024-11-05 13:37:42.187576 |
335 |
98525328 |
Construction of roads |
140000 |
Construction of PCC road from Bisas Bari Durga Mandir towards Jaydeb Roy house |
Plinth level |
-
latitude : 24.07729882746935,24.07729882746935,24.07729882746935
Longitude : 87.71018709987402,87.71018709987402,87.71018709987402
file name : Image_17112024124125258.png
|
2024-11-17 12:41:25.373506 |
336 |
98525328 |
Construction of roads |
140000 |
Construction of PCC road from Bisas Bari Durga Mandir towards Jaydeb Roy house |
Completion of work |
-
latitude : 24.07723860349506,24.07723860349506
Longitude : 87.71030964329839,87.71030964329839
file name : Image_17112024123214101.png
|
2024-11-17 12:32:14.182389 |
337 |
98525328 |
Construction of roads |
140000 |
Construction of PCC road from Bisas Bari Durga Mandir towards Jaydeb Roy house |
Completion of work |
-
latitude : 24.077291577123106,24.077225024811924
Longitude : 87.71003178320825,87.70998174324632
file name : Image_14112024140428456.png
|
2024-11-14 14:04:28.439491 |