1 |
44045209 |
Repair and Maintenance of Road near Gauntiapada |
100000 |
Repair and Maintenance of Road near Gauntiapada1 |
Completion of work |
-
latitude : 20.61757119,20.61757117
Longitude : 82.90279981,82.90279986
file name : Image_29122020153402223.png
|
2020-12-29 15:34:02.328244 |
2 |
44039441 |
Construction of Temporary Chahala |
100000 |
Construction of Temporary Chahala 1 |
Completion of work |
-
latitude : 20.6208528
Longitude : 82.90732122
file name : Image_25012021111749523.png
|
2021-01-25 11:17:49.578636 |
3 |
44039441 |
Construction of Temporary Chahala |
100000 |
Construction of Temporary Chahala 2 |
Completion of work |
-
latitude : 20.6207638
Longitude : 82.90780775
file name : Image_25012021121116451.png
|
2021-01-25 12:11:16.512891 |
4 |
44045155 |
Repair and Maintenance of Basti Road near Mausi Mandir |
100050 |
Repair and Maintenance of Basti Road near Mausi Mandir1 |
Completion of work |
-
latitude : 20.61840825,20.61840673,20.61840456
Longitude : 82.90412464,82.90412311,82.90412293
file name : Image_25012021111743916.png
|
2021-01-25 11:17:43.97267 |
5 |
44045536 |
Beautification of Embarkment of Parlimal Kirlikata |
100000 |
Beautification of Embarkment of Parlimal Kirlikata1 |
Completion of work |
-
latitude : 20.61655224,20.6165309,20.61652969
Longitude : 82.89951622,82.89951131,82.89951166
file name : Image_25012021122659251.png
|
2021-01-25 12:26:59.34439 |
6 |
44038196 |
Sinking of New Tube Well |
219000 |
Sinking of New Tube Well1 |
Completion of work |
-
latitude : 20.61852118
Longitude : 82.87566491
file name : Image_25022021104651205.png
|
2021-02-25 10:46:51.290343 |
7 |
44038196 |
Sinking of New Tube Well |
219000 |
Sinking of New Tube Well1 |
Completion of work |
-
latitude : 20.6184644
Longitude : 82.87567587
file name : Image_25022021110953637.png
|
2021-02-25 11:09:53.692088 |
8 |
44038196 |
Sinking of New Tube Well |
219000 |
Sinking of New Tube Well2 |
Completion of work |
-
latitude : 20.61168364
Longitude : 82.90215109
file name : Image_25022021113108012.png
|
2021-02-25 11:31:08.078914 |
9 |
44038121 |
Honorarium to SEMs & Pump Driver |
72000 |
Honorarium to SEMs & Pump Driver1 |
Completion of work |
-
latitude : 20.6196887
Longitude : 82.87194754
file name : Image_19042021172640333.png
|
2021-04-19 17:26:40.39522 |
10 |
44038121 |
Honorarium to SEMs & Pump Driver |
72000 |
Honorarium to SEMs & Pump Driver2 |
Completion of work |
-
latitude : 20.61971979
Longitude : 82.87194498
file name : Image_19042021173953726.png
|
2021-04-19 17:39:53.799999 |
11 |
44025296 |
Opening of of Jalachhatra(Busstop, Market Place, Main Chowk etc) |
85120 |
Opening of of Jalachhatra(Busstop, Market Place, Main Chowk etc)4 |
Completion of work |
-
latitude : 20.60821204
Longitude : 82.89438498
file name : Image_28052021122416886.png
|
2021-05-28 12:24:16.986312 |
12 |
44025296 |
Opening of of Jalachhatra(Busstop, Market Place, Main Chowk etc) |
85120 |
Opening of of Jalachhatra(Busstop, Market Place, Main Chowk etc)2 |
Completion of work |
-
latitude : 20.61620106
Longitude : 82.89454227
file name : Image_28052021104141256.png
|
2021-05-28 10:41:41.36956 |
13 |
44025296 |
Opening of of Jalachhatra(Busstop, Market Place, Main Chowk etc) |
85120 |
Opening of of Jalachhatra(Busstop, Market Place, Main Chowk etc)3 |
Completion of work |
-
latitude : 20.60829818
Longitude : 82.89446396
file name : Image_28052021122408591.png
|
2021-05-28 12:24:08.693821 |
14 |
44025296 |
Opening of of Jalachhatra(Busstop, Market Place, Main Chowk etc) |
85120 |
Opening of of Jalachhatra(Busstop, Market Place, Main Chowk etc)1 |
Completion of work |
-
latitude : 20.61621051
Longitude : 82.89462556
file name : Image_28052021104136713.png
|
2021-05-28 10:41:36.816697 |
15 |
44038092 |
Provide of Drinking Water to water scarcity Villages during peak summer by Mobile Tanker |
200050 |
Provide of Drinking Water to water scarcity Villages during peak summer by Mobile Tanker1 |
Completion of work |
-
latitude : 20.61654244
Longitude : 82.92732019
file name : Image_28052021122436590.png
|
2021-05-28 12:24:36.680736 |
16 |
44038092 |
Provide of Drinking Water to water scarcity Villages during peak summer by Mobile Tanker |
200050 |
Provide of Drinking Water to water scarcity Villages during peak summer by Mobile Tanker1 |
Completion of work |
-
latitude : 20.61654244
Longitude : 82.92732019
file name : Image_28052021122444640.png
|
2021-05-28 12:24:44.730258 |
17 |
44045417 |
Repair and Mantenance of GP Road from Rengali To Bagdor |
150000 |
Repair and Mantenance of GP Road from Rengali To Bagdor1 |
Completion of work |
-
latitude : 20.61733008,20.61732244
Longitude : 82.85940295,82.85942875
file name : Image_01062021165047783.png
|
2021-06-01 16:50:47.903819 |
18 |
44040964 |
Repair and Maintenance of Existing Road from Ashram to AWC |
231722 |
Repair and Maintenance of Existing Road from Ashram to AWC1 |
Completion of work |
-
latitude : 20.60027282,20.60028456
Longitude : 82.89314947,82.89314561
file name : Image_27072021131035707.png
|
2021-07-27 13:10:35.78312 |
19 |
47933714 |
Construction of Temporary Chahalas at all villages |
100000 |
Construction of Temporary Chahalas at all villages 1 |
Completion of work |
-
latitude : 20.59937645
Longitude : 82.89561272
file name : Image_04102021140307216.png
|
2021-10-04 14:03:07.286646 |
20 |
47933714 |
Construction of Temporary Chahalas at all villages |
100000 |
Construction of Temporary Chahalas at all villages 1 |
Completion of work |
-
latitude : 20.599127
Longitude : 82.89562878
file name : Image_04102021140319627.png
|
2021-10-04 14:03:19.686645 |
21 |
47933714 |
Construction of Temporary Chahalas at all villages |
100000 |
Construction of Temporary Chahalas at all villages 2 |
Completion of work |
-
latitude : 20.59897073
Longitude : 82.89557969
file name : Image_04102021140328123.png
|
2021-10-04 14:03:28.190384 |
22 |
47933714 |
Construction of Temporary Chahalas at all villages |
100000 |
Construction of Temporary Chahalas at all villages 1 |
Completion of work |
-
latitude : 20.5989681
Longitude : 82.89559371
file name : Image_04102021140338488.png
|
2021-10-04 14:03:38.561824 |
23 |
47933714 |
Construction of Temporary Chahalas at all villages |
100000 |
Construction of Temporary Chahalas at all villages 2 |
Completion of work |
-
latitude : 20.59948098
Longitude : 82.89565921
file name : Image_04102021140350532.png
|
2021-10-04 14:03:50.597263 |
24 |
47933265 |
Construction of Cross Bond for Drinking water on Lanth River |
100000 |
Construction of Cross Bond for Drinking water on Lanth River1 |
Completion of work |
-
latitude : 20.61964034
Longitude : 82.90831767
file name : Image_04102021142839608.png
|
2021-10-04 14:28:39.692762 |
25 |
47933265 |
Construction of Cross Bond for Drinking water on Lanth River |
100000 |
Construction of Cross Bond for Drinking water on Lanth River2 |
Completion of work |
-
latitude : 20.61962103
Longitude : 82.90831933
file name : Image_04102021142854280.png
|
2021-10-04 14:28:54.354524 |
26 |
47932664 |
Opening of Jalachhatra ( Bus Stop, Market Place , Main Chowk etc) |
86564 |
Opening of Jalachhatra ( Bus Stop, Market Place , Main Chowk etc)1 |
Completion of work |
-
latitude : 20.6216087
Longitude : 82.8703471
file name : Image_27092021083847563.png
|
2021-09-27 08:38:47.656508 |
27 |
47932664 |
Opening of Jalachhatra ( Bus Stop, Market Place , Main Chowk etc) |
86564 |
Opening of Jalachhatra ( Bus Stop, Market Place , Main Chowk etc)1 |
Completion of work |
-
latitude : 20.62096828
Longitude : 82.87041787
file name : Image_27092021083901235.png
|
2021-09-27 08:39:01.311514 |
28 |
47959056 |
Repair and maintenance of UP School,Rengali |
100000 |
Repair and maintenance of UP School,Rengali1 |
Completion of work |
-
latitude : 20.6185198
Longitude : 82.8758984
file name : Image_29112021122153779.png
|
2021-11-29 12:21:53.897422 |
29 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 1 |
Completion of work |
-
latitude : 20.61936356
Longitude : 82.87317319
file name : Image_29112021112518484.png
|
2021-11-29 11:25:18.598552 |
30 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 2 |
Completion of work |
-
latitude : 20.62042707
Longitude : 82.87033253
file name : Image_29112021122145988.png
|
2021-11-29 12:21:46.086855 |
31 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 2 |
Completion of work |
-
latitude : 20.62042707
Longitude : 82.87033253
file name : Image_29112021112640356.png
|
2021-11-29 11:26:40.453754 |
32 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 1 |
Completion of work |
-
latitude : 20.60412633
Longitude : 82.88949
file name : Image_29112021122248939.png
|
2021-11-29 12:22:49.020675 |
33 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 1 |
Completion of work |
-
latitude : 20.60412633
Longitude : 82.88949
file name : Image_29112021122203716.png
|
2021-11-29 12:22:03.809674 |
34 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 2 |
Completion of work |
-
latitude : 20.61729915
Longitude : 82.89947778
file name : Image_29112021122207817.png
|
2021-11-29 12:22:07.901046 |
35 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 2 |
Completion of work |
-
latitude : 20.61729915
Longitude : 82.89947778
file name : Image_29112021122254261.png
|
2021-11-29 12:22:54.346438 |
36 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 1 |
Completion of work |
-
latitude : 20.61982348
Longitude : 82.90538983
file name : Image_29112021122313655.png
|
2021-11-29 12:23:13.744424 |
37 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 1 |
Completion of work |
-
latitude : 20.61982348
Longitude : 82.90538983
file name : Image_29112021122219472.png
|
2021-11-29 12:22:19.574572 |
38 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 2 |
Completion of work |
-
latitude : 20.61506722
Longitude : 82.90475965
file name : Image_29112021122408542.png
|
2021-11-29 12:24:08.629064 |
39 |
47933986 |
Maintanance of Existing Solar System Project |
146322 |
Maintanance of Existing Solar System Project 2 |
Completion of work |
-
latitude : 20.61506722
Longitude : 82.90475965
file name : Image_29112021122235659.png
|
2021-11-29 12:22:35.751836 |
40 |
47931646 |
Operartion and Maintanance Exsiting Piped water supply system as & when required |
50000 |
Operartion and Maintanance Exsiting Piped water supply system as & when required1 |
Completion of work |
-
latitude : 20.62132685,20.62128617
Longitude : 82.90738592,82.90737099
file name : Image_29112021122230880.png
|
2021-11-29 12:22:30.985846 |
41 |
47931646 |
Operartion and Maintanance Exsiting Piped water supply system as & when required |
50000 |
Operartion and Maintanance Exsiting Piped water supply system as & when required1 |
Completion of work |
-
latitude : 20.62132685,20.62128617
Longitude : 82.90738592,82.90737099
file name : Image_29112021122342935.png
|
2021-11-29 12:23:43.060441 |
42 |
47948243 |
Repair and Maintenance of Road at Munapali Upar Pada |
100000 |
Repair and Maintenance of Road at Munapali Upar Pada1 |
Completion of work |
-
latitude : 20.60410536,20.60412375
Longitude : 82.88953425,82.88950394
file name : Image_29112021122158947.png
|
2021-11-29 12:21:59.025561 |
43 |
47948243 |
Repair and Maintenance of Road at Munapali Upar Pada |
100000 |
Repair and Maintenance of Road at Munapali Upar Pada1 |
Completion of work |
-
latitude : 20.60410536,20.60412375
Longitude : 82.88953425,82.88950394
file name : Image_29112021122240622.png
|
2021-11-29 12:22:40.710718 |
44 |
47948925 |
Construction of New Road to Majhi Pada at- Chitkuljore |
131772 |
Construction of New Road to Majhi Pada at- Chitkuljore1 |
Completion of work |
-
latitude : 20.63551272,20.63551272,20.63551004
Longitude : 82.89256646,82.89256646,82.89256587
file name : Image_29112021122212717.png
|
2021-11-29 12:22:12.810093 |
45 |
47948925 |
Construction of New Road to Majhi Pada at- Chitkuljore |
131772 |
Construction of New Road to Majhi Pada at- Chitkuljore1 |
Completion of work |
-
latitude : 20.63551272,20.63551272,20.63551004
Longitude : 82.89256646,82.89256646,82.89256587
file name : Image_29112021122300467.png
|
2021-11-29 12:23:00.565787 |
46 |
47934519 |
Construction of Bathing step Changing Room at Panti Ghat, Lanth |
100000 |
Construction of Bathing step Changing Room at Panti Ghat, Lanth1 |
Completion of work |
-
latitude : 20.62132969
Longitude : 82.9074058
file name : Image_29112021122225465.png
|
2021-11-29 12:22:25.575414 |
47 |
47934519 |
Construction of Bathing step Changing Room at Panti Ghat, Lanth |
100000 |
Construction of Bathing step Changing Room at Panti Ghat, Lanth1 |
Completion of work |
-
latitude : 20.62132969
Longitude : 82.9074058
file name : Image_29112021122322031.png
|
2021-11-29 12:23:22.124944 |
48 |
44045485 |
Repair and Maintenance of Road at Rengali Uparpada |
100000 |
Repair and Maintenance of Road at Rengali Uparpada1 |
Completion of work |
-
latitude : 20.62179165,20.62177473
Longitude : 82.8705538,82.87055497
file name : Image_29112021164924134.png
|
2021-11-29 16:49:24.2799 |
49 |
44045485 |
Repair and Maintenance of Road at Rengali Uparpada |
100000 |
Repair and Maintenance of Road at Rengali Uparpada1 |
Completion of work |
-
latitude : 20.62178027,20.62177687
Longitude : 82.87049893,82.87049929
file name : Image_29112021162344165.png
|
2021-11-29 16:23:44.266503 |
50 |
56441168 |
Improvement and maintenance of Road from Rengali to Munapali |
200000 |
Improvement and maintenance of Road from Rengali to Munapali1 |
Completion of work |
-
latitude : 20.61783751,20.61783578
Longitude : 82.88088635,82.88088318
file name : Image_05032022175113382.png
|
2022-03-05 17:51:13.499065 |
51 |
56441168 |
Improvement and maintenance of Road from Rengali to Munapali |
200000 |
Improvement and maintenance of Road from Rengali to Munapali1 |
Completion of work |
-
latitude : 20.61783008,20.6178299
Longitude : 82.88087916,82.88087856
file name : Image_05032022175132359.png
|
2022-03-05 17:51:32.440734 |
52 |
56441168 |
Improvement and maintenance of Road from Rengali to Munapali |
200000 |
Improvement and maintenance of Road from Rengali to Munapali1 |
Completion of work |
-
latitude : 20.61783008,20.6178299
Longitude : 82.88087916,82.88087856
file name : Image_05032022175140901.png
|
2022-03-05 17:51:40.994102 |
53 |
47934824 |
Construction of Bathing steps with Dress Changing Room at Kirlikata |
150000 |
Construction of Bathing steps with Dress Changing Room at Kirlikata 1 |
Completion of work |
-
latitude : 20.616028333333336
Longitude : 82.89893
file name : Image_30072022114404740.png
|
2022-07-30 11:44:04.850113 |
54 |
47948394 |
Repair and maintenance of Road near Canara Bank , Parlimal |
150000 |
Repair and maintenance of Road near Canara Bank , Parlimal1 |
Completion of work |
-
latitude : 20.619033333333334,20.619030000000002
Longitude : 82.90118166666667,82.901175
file name : Image_05082022122140870.png
|
2022-08-05 12:21:40.966137 |
55 |
47948394 |
Repair and maintenance of Road near Canara Bank , Parlimal |
150000 |
Repair and maintenance of Road near Canara Bank , Parlimal1 |
Completion of work |
-
latitude : 20.6243796,20.61901,20.61902
Longitude : 82.9096451,82.90112333333333,82.90118
file name : Image_05082022121834696.png
|
2022-08-05 12:18:34.798721 |
56 |
47935302 |
Guardwall at Laxmi Mandir road for disposal of garbage to Drain |
150000 |
Guardwall at Laxmi Mandir road for disposal of garbage to Drain1 |
Completion of work |
-
latitude : 20.59905,20.599036666666667
Longitude : 82.89340833333333,82.89341
file name : Image_05082022123949645.png
|
2022-08-05 12:39:49.754805 |
57 |
47935302 |
Guardwall at Laxmi Mandir road for disposal of garbage to Drain |
150000 |
Guardwall at Laxmi Mandir road for disposal of garbage to Drain1 |
Completion of work |
-
latitude : 20.599035,20.599128333333333,20.599531666666667
Longitude : 82.89342666666668,82.89347166666667,82.89344833333334
file name : Image_05082022125423961.png
|
2022-08-05 12:54:24.082746 |
58 |
62017016 |
Jala Chhatras at all Villages |
86564 |
Jala Chhatras at all Villages1 |
Completion of work |
-
latitude : 20.617998333333333
Longitude : 82.90293666666666
file name : Image_27082022140632281.png
|
2022-08-27 14:06:32.37435 |
59 |
62017016 |
Jala Chhatras at all Villages |
86564 |
Jala Chhatras at all Villages1 |
Completion of work |
-
latitude : 20.617913333333334
Longitude : 82.90292333333333
file name : Image_27082022140442577.png
|
2022-08-27 14:04:42.681773 |
60 |
65277305 |
Creation of cattle troughs |
100000 |
Creation of cattle troughs1 |
Completion of work |
-
latitude : 20.619419999999998
Longitude : 82.90864000000002
file name : Image_15042023141518414.png
|
2023-04-15 14:15:18.501454 |
61 |
65277305 |
Creation of cattle troughs |
100000 |
Creation of cattle troughs1 |
Completion of work |
-
latitude : 20.61940333333333
Longitude : 82.90864333333333
file name : Image_15042023141342947.png
|
2023-04-15 14:13:43.037707 |
62 |
65277305 |
Creation of cattle troughs |
100000 |
Creation of cattle troughs1 |
Completion of work |
-
latitude : 20.619410000000002
Longitude : 82.90865833333334
file name : Image_15042023141125866.png
|
2023-04-15 14:11:25.959755 |
63 |
86162275 |
CONST OFN BATJING STEP AT MEHERBANDH |
100000 |
CONST OFN BATJING STEP AT MEHERBANDH1 |
Completion of work |
-
latitude : 20.592114
Longitude : 82.9613507
file name : Image_10072023120704882.png
|
2023-07-10 12:07:04.999841 |
64 |
62017273 |
Construction of Boundary Wall at Parlimal High School |
400000 |
Construction of Boundary Wall at Parlimal High School1 |
Completion of work |
-
latitude : 20.5921137
Longitude : 82.96135
file name : Image_10072023120503298.png
|
2023-07-10 12:05:03.397619 |
65 |
86162375 |
CONST OF BASTHING STEP MEHERBANDH PHASE 2 |
100000 |
CONST OF BASTHING STEP MEHERBANDH PHASE 21 |
Completion of work |
-
latitude : 20.5921137
Longitude : 82.9613499
file name : Image_10072023121102742.png
|
2023-07-10 12:11:02.833592 |
66 |
65277043 |
Operation & maintenance of community sanitary complex |
58500 |
Operation & maintenance of community sanitary complex1 |
Completion of work |
-
latitude : 20.750708333333332
Longitude : 82.97061833333333
file name : Image_02082023174204635.png
|
2023-08-02 17:42:04.75289 |
67 |
65277043 |
Operation & maintenance of community sanitary complex |
58500 |
Operation & maintenance of community sanitary complex1 |
Completion of work |
-
latitude : 20.75036833333333
Longitude : 82.970525
file name : Image_02082023173846075.png
|
2023-08-02 17:38:46.175285 |
68 |
61145541 |
Reair and Maintenance of UP School at Chitkuljor |
128800 |
Reair and Maintenance of UP School at Chitkuljor1 |
Completion of work |
-
latitude : 20.5920663
Longitude : 82.9613045
file name : Image_13092023154931452.png
|
2023-09-13 15:49:32.058737 |
69 |
65277261 |
Construction of toilets in public institutions |
150000 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 20.5920659
Longitude : 82.9613092
file name : Image_13092023155425081.png
|
2023-09-13 15:54:25.239363 |
70 |
62017175 |
Cleaning of Bathing Ghats, Drains, AWC, Schools, Streets all village |
50000 |
Cleaning of Bathing Ghats, Drains, AWC, Schools, Streets all village1 |
Completion of work |
-
latitude : 20.5922944
Longitude : 82.961569
file name : Image_30122023165537039.png
|
2023-12-30 16:55:37.13465 |
71 |
82826227 |
Augmentation of existing sources of Drinking Water |
85750 |
Augmentation of existing sources of Drinking Water1 |
Roof laid |
-
latitude : 20.592066
Longitude : 82.9613083
file name : Image_14112023115256838.png
|
2023-11-14 11:52:56.923064 |
72 |
82826227 |
Augmentation of existing sources of Drinking Water |
85750 |
Augmentation of existing sources of Drinking Water1 |
Plinth level |
-
latitude : 20.5920659
Longitude : 82.9613085
file name : Image_14112023114949639.png
|
2023-11-14 11:49:49.722662 |
73 |
82826227 |
Augmentation of existing sources of Drinking Water |
85750 |
Augmentation of existing sources of Drinking Water1 |
Completion of work |
-
latitude : 20.592066
Longitude : 82.9613083
file name : Image_14112023114734153.png
|
2023-11-14 11:47:34.237036 |
74 |
106301620 |
CONST OF PEO STAFF QUATER AT PARLIMAL GP OFFICE |
650000 |
CONST OF PEO STAFF QUATER AT PARLIMAL GP OFFICE1 |
Completion of work |
-
latitude : 20.6180395
Longitude : 82.9024602
file name : Image_17052024110751958.png
|
2024-05-17 11:07:52.058693 |