1 |
44322151 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR KASIMANIK HOUSE,NATAPADA. |
20000 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR KASIMANIK HOUSE,NATAPADA.1 |
Roof laid |
-
latitude : 21.36044799350202
Longitude : 86.52865952812135
file name : Image_04022021145006782.png
|
2021-02-04 14:50:06.896677 |
2 |
44322202 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT AT JAGABANDHU HIGH SCHOOL |
20000 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT AT JAGABANDHU HIGH SCHOOL1 |
Roof laid |
-
latitude : 21.345798270776868
Longitude : 86.52856037020683
file name : Image_04022021151633737.png
|
2021-02-04 15:16:33.819911 |
3 |
44322093 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR REST HOUSE AT MUNIPADA |
20000 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR REST HOUSE AT MUNIPADA1 |
Roof laid |
-
latitude : 21.33890767581761
Longitude : 86.52584270574152
file name : Image_04022021142046749.png
|
2021-02-04 14:20:46.840409 |
4 |
44322129 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR AWC, NUASAHI. |
20000 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR AWC, NUASAHI.1 |
Roof laid |
-
latitude : 21.35703094303608
Longitude : 86.52946653775871
file name : Image_04022021145820229.png
|
2021-02-04 14:58:20.351884 |
5 |
44322678 |
CONST. OF REPAIRING COMMUNITY CENTRE AT AGUANI SAHI,NATAPADA. |
100000 |
CONST. OF REPAIRING COMMUNITY CENTRE AT AGUANI SAHI,NATAPADA.1 |
Roof laid |
-
latitude : 21.36029724497348
Longitude : 86.52945555746555
file name : Image_04022021145409186.png
|
2021-02-04 14:54:09.292593 |
6 |
44321982 |
REMUNERATION OF SEM |
24000 |
REMUNERATION OF SEM1 |
Plinth level |
-
latitude : 21.329385000000002
Longitude : 86.50584666666667
file name : Image_07102021110417701.png
|
2021-10-07 11:04:17.798219 |
7 |
37765619 |
Repair of Nodal UP School Kamarpal |
100000 |
Repair of Nodal UP School Kamarpal1 |
Completed |
-
latitude : 21.3389348750934
Longitude : 86.55044778250158
file name : Image_11122020145053909.png
|
2020-12-11 14:50:54.015687 |
8 |
37765776 |
Completion of GP Office toilet with bathroom work and other office maintainance |
96969 |
Completion of GP Office toilet with bathroom work and other office maintainance1 |
Completed |
-
latitude : 21.352204559370875
Longitude : 86.53546823188663
file name : Image_11122020161553670.png
|
2020-12-11 16:15:53.756174 |
9 |
37765559 |
Const,of boundary wall and competion of GP office gate and office building repair. |
149660 |
Const,of boundary wall and competion of GP office gate and office building repair.1 |
COMPLETED |
-
latitude : 21.352003854699433
Longitude : 86.53549279086292
file name : Image_19122020114337062.png
|
2020-12-19 11:43:37.158077 |
10 |
44322868 |
CONST. OF ROAD FROM BABU PALEI HOUSE TO BUDHIADI PADA. |
120000 |
CONST. OF ROAD FROM BABU PALEI HOUSE TO BUDHIADI PADA.1 |
Roof laid |
-
latitude : 21.343330051749945,21.343320328742266
Longitude : 86.54963423497975,86.5496002882719
file name : Image_18122020170709024.png
|
2020-12-18 17:07:09.093385 |
11 |
44322913 |
CONST. OF CC ROAD FROM BULU PRUSTY HOUSE TO MADHU MANDAL HOUSE. |
150000 |
CONST. OF CC ROAD FROM BULU PRUSTY HOUSE TO MADHU MANDAL HOUSE.1 |
Roof laid |
-
latitude : 21.343100890517235,21.34311694186181
Longitude : 86.55059262178838,86.55059949494898
file name : Image_18122020170156823.png
|
2020-12-18 17:01:56.889211 |
12 |
37765673 |
Construction of Approch road from Chinchida AWC to Adibasi sahi Tube well chhaka |
100000 |
Construction of Approch road from Chinchida AWC to Adibasi sahi Tube well chhaka1 |
Completed |
-
latitude : 21.347566726617515,21.347514088265598
Longitude : 86.5398761909455,86.53986747376621
file name : Image_03012021165252213.png
|
2021-01-03 16:52:52.340479 |
13 |
44322657 |
COMPLETION OF INCOMPLETE COMMUNITY CENTRE AT MANGALPADA. |
165000 |
COMPLETION OF INCOMPLETE COMMUNITY CENTRE AT MANGALPADA.1 |
Roof laid |
-
latitude : 21.337445000000002
Longitude : 86.55487833333333
file name : Image_20042022135934671.png
|
2022-04-20 13:59:34.869558 |
14 |
44322657 |
COMPLETION OF INCOMPLETE COMMUNITY CENTRE AT MANGALPADA. |
165000 |
COMPLETION OF INCOMPLETE COMMUNITY CENTRE AT MANGALPADA.1 |
Roof laid |
-
latitude : 21.337462719529867
Longitude : 86.55478399246931
file name : Image_01012021120819437.png
|
2021-01-01 12:08:19.51694 |
15 |
44322525 |
CONST. OF APPROACHING ROAD IN AGHIRAPADA ARJUN CHARAN NODAL SCHOOL. |
100000 |
CONST. OF APPROACHING ROAD IN AGHIRAPADA ARJUN CHARAN NODAL SCHOOL.1 |
Roof laid |
-
latitude : 21.339631620794535,21.339619467034936
Longitude : 86.5265710093081,86.52648727409542
file name : Image_01012021125358846.png
|
2021-01-01 12:53:58.966824 |
16 |
44322113 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR MANGALPADA |
20000 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR MANGALPADA1 |
Roof laid |
-
latitude : 21.33761413861066
Longitude : 86.55477854423225
file name : Image_01012021121134447.png
|
2021-01-01 12:11:34.518879 |
17 |
37715635 |
Raised platform at aghirapada jenasahi tube well |
15000 |
Raised platform at aghirapada jenasahi tube well1 |
Completed |
-
latitude : 21.343321666666665
Longitude : 86.52856666666666
file name : Image_12022021171745233.png
|
2021-02-12 17:17:45.33165 |
18 |
24997391 |
AGUAN SAHI BADA SAHI TUBE WELL PLATFORM NEAR MANDIR |
20000 |
AGUAN SAHI BADA SAHI TUBE WELL PLATFORM NEAR MANDIR1 |
Completed |
-
latitude : 21.35886833333333
Longitude : 86.53161666666668
file name : Image_12022021172839944.png
|
2021-02-12 17:28:40.039675 |
19 |
44322264 |
CONST. OF DRAIN FROM UPENDRA SAHI PUMP HOUSE TO SANIA BEHERA HOUSE. |
150000 |
CONST. OF DRAIN FROM UPENDRA SAHI PUMP HOUSE TO SANIA BEHERA HOUSE.1 |
Roof laid |
-
latitude : 21.34185,21.341901666666665
Longitude : 86.54989666666667,86.54992666666666
file name : Image_13022021164641628.png
|
2021-02-13 16:46:41.748141 |
20 |
44322886 |
CONST. OF DRAIN FROM HARIHATA TO PAGAL BEHERA HOUSE. |
164032 |
CONST. OF DRAIN FROM HARIHATA TO PAGAL BEHERA HOUSE.1 |
Roof laid |
-
latitude : 21.342761666666668,21.34276333333333,21.342791666666667
Longitude : 86.54979166666665,86.54973333333334,86.54967166666665
file name : Image_13022021165015814.png
|
2021-02-13 16:50:15.9359 |
21 |
44322590 |
CONST. OF BOUNDARY WALL AT PALISHREE NODAL SCHOOL. |
21000 |
CONST. OF BOUNDARY WALL AT PALISHREE NODAL SCHOOL.1 |
Roof laid |
-
latitude : 21.349153333333334
Longitude : 86.53825
file name : Image_24022021183016269.png
|
2021-02-24 18:30:16.358066 |
22 |
44322590 |
CONST. OF BOUNDARY WALL AT PALISHREE NODAL SCHOOL. |
21000 |
CONST. OF BOUNDARY WALL AT PALISHREE NODAL SCHOOL.1 |
Roof laid |
-
latitude : 21.349153333333334
Longitude : 86.53825
file name : Image_24022021183022164.png
|
2021-02-24 18:30:22.256938 |
23 |
44322175 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR NIRANJAN BEHERA HOUSE AT BEHERA SAHI. |
20000 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR NIRANJAN BEHERA HOUSE AT BEHERA SAHI.1 |
Roof laid |
-
latitude : 21.348315000000003
Longitude : 86.52879666666668
file name : Image_24022021171111344.png
|
2021-02-24 17:11:11.428954 |
24 |
44322175 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR NIRANJAN BEHERA HOUSE AT BEHERA SAHI. |
20000 |
RAISED TUBEWELL PLATFORM WITH RECHARGE PIT NEAR NIRANJAN BEHERA HOUSE AT BEHERA SAHI.1 |
Roof laid |
-
latitude : 21.34833
Longitude : 86.52882333333334
file name : Image_24022021183010834.png
|
2021-02-24 18:30:10.918374 |
25 |
44322713 |
DALEI SAHI INCOMPLETE CC ROAD TO UPENDRA NAYAK HOUSE. |
100000 |
DALEI SAHI INCOMPLETE CC ROAD TO UPENDRA NAYAK HOUSE.1 |
Roof laid |
-
latitude : 21.337149999999998,21.337138333333336
Longitude : 86.52594333333333,86.525945
file name : Image_20032021160137588.png
|
2021-03-20 16:01:38.226773 |
26 |
37762587 |
Raised platform at patrasahi harihat tube well |
16000 |
Raised platform at patrasahi harihat tube well1 |
Completed |
-
latitude : 21.348985000000003
Longitude : 86.52930833333333
file name : Image_18032021173853994.png
|
2021-03-18 17:38:54.100654 |
27 |
37765524 |
Approch road from Aghirapada primary school to Dalei sahi |
100000 |
Approch road from Aghirapada primary school to Dalei sahi1 |
Completed |
-
latitude : 21.33739166666667,21.337371666666666,21.337343333333333
Longitude : 86.52598666666667,86.52595833333335,86.52595333333332
file name : Image_20032021160408739.png
|
2021-03-20 16:04:09.297067 |
28 |
37715285 |
sinking of new tube well at Gada behera sahi near Karunakar behera house |
85000 |
sinking of new tube well at Gada behera sahi near Karunakar behera house1 |
Completed |
-
latitude : 21.338428333333333
Longitude : 86.55231833333333
file name : Image_18032021175438849.png
|
2021-03-18 17:54:38.974134 |
29 |
24968127 |
DIGGING OF NEW TUBE WELL AT GARUDA HATA NEAR MAJHI SAHI DHARMA BEHERA HOUSE |
100000 |
DIGGING OF NEW TUBE WELL AT GARUDA HATA NEAR MAJHI SAHI DHARMA BEHERA HOUSE1 |
Completed |
-
latitude : 21.338833333333334
Longitude : 86.55831333333332
file name : Image_18032021175847854.png
|
2021-03-18 17:58:47.95623 |
30 |
44322936 |
CONST. OF DRAIN FROM KAITHA CHAKA TO NIRANJAN BARIK HOUSE CHINCHIDA |
80000 |
CONST. OF DRAIN FROM KAITHA CHAKA TO NIRANJAN BARIK HOUSE CHINCHIDA1 |
Roof laid |
-
latitude : 21.346709999999998,21.346715000000003
Longitude : 86.54007000000001,86.53999
file name : Image_03062021172723733.png
|
2021-06-03 17:27:23.827326 |
31 |
44322478 |
CONST. OF ROAD FROM MANGA PRADHAN HOUSE TO PALLISHREE NODAL SCHOOL, CHINCHIDA. |
150000 |
CONST. OF ROAD FROM MANGA PRADHAN HOUSE TO PALLISHREE NODAL SCHOOL, CHINCHIDA.1 |
Roof laid |
-
latitude : 21.348664999999997,21.348664999999997
Longitude : 86.53843333333334,86.53844499999998
file name : Image_03062021171555484.png
|
2021-06-03 17:15:55.57272 |
32 |
44322756 |
COMPLETION OF INCOMPLETE COMMUNITY CENTRE NEAR ANANDA BEHERA HOUSE. |
100312 |
COMPLETION OF INCOMPLETE COMMUNITY CENTRE NEAR ANANDA BEHERA HOUSE.1 |
Roof laid |
-
latitude : 21.342023333333334
Longitude : 86.54987000000001
file name : Image_03062021174458982.png
|
2021-06-03 17:44:59.083017 |
33 |
44322277 |
CONST. OF DRAIN FROM MANORANJAN HOUSE TO DHODHYA NALA AT BISWAL SAHI. |
150000 |
CONST. OF DRAIN FROM MANORANJAN HOUSE TO DHODHYA NALA AT BISWAL SAHI.1 |
Roof laid |
-
latitude : 21.345928333333337,21.34598
Longitude : 86.52724333333332,86.52722666666665
file name : Image_09062021100212849.png
|
2021-06-09 10:02:12.951838 |
34 |
25233698 |
RENOVATION OF SANAMARALI TANK PATRA SAHI |
100000 |
RENOVATION OF SANAMARALI TANK PATRA SAHI1 |
Completed |
-
latitude : 21.348568333333333
Longitude : 86.52897833333333
file name : Image_04062021095602484.png
|
2021-06-04 09:56:02.664142 |
35 |
25205223 |
RENOVATION OF SANAMARALI TANK PATRA SAHI |
50000 |
RENOVATION OF SANAMARALI TANK PATRA SAHI1 |
Completed |
-
latitude : 21.348568333333333
Longitude : 86.52900999999999
file name : Image_04062021100618725.png
|
2021-06-04 10:06:18.822464 |
36 |
44322241 |
SINKING OF NEW TUBE WELL NEAR CHINCHIDA PADA., |
99000 |
SINKING OF NEW TUBE WELL NEAR CHINCHIDA PADA.,1 |
Roof laid |
-
latitude : 21.348046666666665
Longitude : 86.53952499999998
file name : Image_09062021134149498.png
|
2021-06-09 13:41:49.601919 |
37 |
44322897 |
CONST. OF CC ROAD FROM HAREKRUSHNA PRUSTY HOUSE TO KAILASH BEHERA HOUSE. |
300000 |
CONST. OF CC ROAD FROM HAREKRUSHNA PRUSTY HOUSE TO KAILASH BEHERA HOUSE.1 |
Completion of work |
-
latitude : 21.335448333333336,21.335444999999996
Longitude : 86.52987499999999,86.52987499999999
file name : Image_13082021163927307.png
|
2021-08-13 16:39:27.488785 |
38 |
56139428 |
CONST OF ROAD FROM KARUNAKAR JENA HOUSE TO ISHWAR JENA HOUSE |
100000 |
CONST OF ROAD FROM KARUNAKAR JENA HOUSE TO ISHWAR JENA HOUSE1 |
Roof laid |
-
latitude : 21.32974,21.329493333333335
Longitude : 86.507365,86.50586666666668
file name : Image_14022022181305637.png
|
2022-02-14 18:13:05.721127 |
39 |
56139428 |
CONST OF ROAD FROM KARUNAKAR JENA HOUSE TO ISHWAR JENA HOUSE |
100000 |
CONST OF ROAD FROM KARUNAKAR JENA HOUSE TO ISHWAR JENA HOUSE1 |
Roof laid |
-
latitude : 21.32974,21.329493333333335
Longitude : 86.507365,86.50586666666668
file name : Image_14022022181309701.png
|
2022-02-14 18:13:09.783485 |
40 |
56139423 |
CONST OF ROAD FROM BHABAGRAHI NAYAK HOUSE TO ROUT SAHI |
100000 |
CONST OF ROAD FROM BHABAGRAHI NAYAK HOUSE TO ROUT SAHI1 |
Roof laid |
-
latitude : 21.3293776,21.3294682
Longitude : 86.5057062,86.5057873
file name : Image_14022022181301703.png
|
2022-02-14 18:13:01.813028 |
41 |
56138058 |
SBM PHASE 2 |
50000 |
SBM PHASE 21 |
Roof laid |
-
latitude : 21.319431666666667
Longitude : 86.46154833333334
file name : Image_11042022130102647.png
|
2022-04-11 13:01:02.820534 |
42 |
56139407 |
CONST OF ROAD FROM PRABHAKAR PATRA HOUSE TO NAYAK SAHI |
100000 |
CONST OF ROAD FROM PRABHAKAR PATRA HOUSE TO NAYAK SAHI1 |
Roof laid |
-
latitude : 21.344965000000002,21.344974999999998
Longitude : 86.52834999999999,86.52831833333333
file name : Image_20042022151345953.png
|
2022-04-20 15:13:46.169969 |
43 |
44322013 |
MAINTENANCE OF PWC OF KAMARPAL ADIBASI SAHI |
50000 |
MAINTENANCE OF PWC OF KAMARPAL ADIBASI SAHI1 |
Roof laid |
-
latitude : 21.341548333333336,21.34155333333333
Longitude : 86.54987333333332,86.54988333333334
file name : Image_20042022114916864.png
|
2022-04-20 11:49:17.03151 |
44 |
56138004 |
WATER SUPPLY OF AGHIRAPADA HIGH SCHOOL |
100000 |
WATER SUPPLY OF AGHIRAPADA HIGH SCHOOL1 |
Roof laid |
-
latitude : 21.33565666666667
Longitude : 86.57384500000002
file name : Image_18062022132451317.png
|
2022-06-18 13:24:51.446862 |
45 |
56138004 |
WATER SUPPLY OF AGHIRAPADA HIGH SCHOOL |
100000 |
WATER SUPPLY OF AGHIRAPADA HIGH SCHOOL1 |
Roof laid |
-
latitude : 21.344998333333333
Longitude : 86.52813666666667
file name : Image_20042022151216532.png
|
2022-04-20 15:12:16.685986 |
46 |
56137998 |
WATER SUPPLY OF AWC CENTRE PAIDAJHARA ADIBASI SAHI,KAMARPAL |
100000 |
WATER SUPPLY OF AWC CENTRE PAIDAJHARA ADIBASI SAHI,KAMARPAL1 |
Roof laid |
-
latitude : 21.335759999999997
Longitude : 86.57381666666667
file name : Image_18062022132447216.png
|
2022-06-18 13:24:47.354937 |
47 |
56137998 |
WATER SUPPLY OF AWC CENTRE PAIDAJHARA ADIBASI SAHI,KAMARPAL |
100000 |
WATER SUPPLY OF AWC CENTRE PAIDAJHARA ADIBASI SAHI,KAMARPAL1 |
Roof laid |
-
latitude : 21.335759999999997
Longitude : 86.57381666666667
file name : Image_18062022132504076.png
|
2022-06-18 13:25:04.215563 |
48 |
56137994 |
WATER SUPPLY OF MAHULAGADIA PRIMARY SCHOOL |
100000 |
WATER SUPPLY OF MAHULAGADIA PRIMARY SCHOOL 1 |
Roof laid |
-
latitude : 21.335626666666666
Longitude : 86.57392833333333
file name : Image_18062022132443488.png
|
2022-06-18 13:24:43.638 |
49 |
56137994 |
WATER SUPPLY OF MAHULAGADIA PRIMARY SCHOOL |
100000 |
WATER SUPPLY OF MAHULAGADIA PRIMARY SCHOOL 1 |
Roof laid |
-
latitude : 21.335626666666666
Longitude : 86.57392833333333
file name : Image_18062022132500009.png
|
2022-06-18 13:25:00.155029 |
50 |
56137990 |
WATER SUPPLY OF RAMBHAMANI NODAL AND KAMARPAL AWC CENTRE |
158789 |
WATER SUPPLY OF RAMBHAMANI NODAL AND KAMARPAL AWC CENTRE1 |
Roof laid |
-
latitude : 21.33560333333333
Longitude : 86.57395833333334
file name : Image_18062022132439765.png
|
2022-06-18 13:24:39.902127 |
51 |
56137990 |
WATER SUPPLY OF RAMBHAMANI NODAL AND KAMARPAL AWC CENTRE |
158789 |
WATER SUPPLY OF RAMBHAMANI NODAL AND KAMARPAL AWC CENTRE1 |
Roof laid |
-
latitude : 21.33560333333333
Longitude : 86.57395833333334
file name : Image_18062022132455972.png
|
2022-06-18 13:24:56.107019 |
52 |
56137987 |
WATER SUPPLY OF GARUDAHATA PRIMARY SCHOOL |
100000 |
WATER SUPPLY OF GARUDAHATA PRIMARY SCHOOL1 |
Roof laid |
-
latitude : 21.335551666666667
Longitude : 86.57392999999999
file name : Image_18062022132434446.png
|
2022-06-18 13:24:34.644668 |
53 |
44322566 |
CONST. OF BOUNDARY WALL AT PALDAJHARAN PRIMARY SCHOOL. |
100000 |
CONST. OF BOUNDARY WALL AT PALDAJHARAN PRIMARY SCHOOL.1 |
Roof laid |
-
latitude : 21.346616666666666
Longitude : 86.55149333333333
file name : Image_20042022112352513.png
|
2022-04-20 11:23:52.664557 |
54 |
65467503 |
Const of class room at Kamarpal High School under High School Transformation Kamarpal |
50000 |
Const of class room at Kamarpal High School under High School Transformation Kamarpal1 |
Roof laid |
-
latitude : 21.3293301
Longitude : 86.5058332
file name : Image_01122022165918389.png
|
2022-12-01 16:59:18.480842 |
55 |
65467546 |
Construction of toilets in public institutions |
400000 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 21.3293299
Longitude : 86.5058329
file name : Image_01122022165715122.png
|
2022-12-01 16:57:15.225361 |
56 |
56138014 |
CONST OF TOILET AT PABITRA DEVI SISU BHABAN |
100000 |
CONST OF TOILET AT PABITRA DEVI SISU BHABAN1 |
Roof laid |
-
latitude : 21.3293299
Longitude : 86.5058333
file name : Image_01122022170403348.png
|
2022-12-01 17:04:03.437561 |
57 |
64777135 |
Creation of community compost pits for a group of Households |
18000 |
Creation of community compost pits for a group of Households1 |
Roof laid |
-
latitude : 21.35677118
Longitude : 86.65117663
file name : Image_05012023194459684.png
|
2023-01-05 19:44:59.848527 |
58 |
64777184 |
Operation & maintenance of community soak pits |
6000 |
Operation & maintenance of community soak pits1 |
Roof laid |
-
latitude : 21.35676678
Longitude : 86.65118724
file name : Image_05012023194253564.png
|
2023-01-05 19:42:53.713205 |
59 |
64776968 |
Purchase of Tricycles/other battery-operated vehicles for door to door collection of waste |
9000 |
Purchase of Tricycles/other battery-operated vehicles for door to door collection of waste1 |
Roof laid |
-
latitude : 21.3294931
Longitude : 86.5056335
file name : Image_31122022191913461.png
|
2022-12-31 19:19:13.538231 |
60 |
65467777 |
Const of class room at Kamarpal High School under High School Transformation Kamarpal |
150000 |
Const of class room at Kamarpal High School under High School Transformation Kamarpal1 |
Completion of work |
-
latitude : 21.3293733
Longitude : 86.5057493
file name : Image_03022023181244382.png
|
2023-02-03 18:12:44.44621 |
61 |
65467771 |
Construction of toilets in public institutions |
208789 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 21.3293736
Longitude : 86.5057559
file name : Image_03022023181058702.png
|
2023-02-03 18:10:58.76794 |
62 |
56138022 |
CONST OF TOILET AT AKHYA ACHARYA ADIBASI UP SCHOOL , AGUANISAHI |
100000 |
CONST OF TOILET AT AKHYA ACHARYA ADIBASI UP SCHOOL , AGUANISAHI1 |
Roof laid |
-
latitude : 21.358797890134156
Longitude : 86.53061267919838
file name : Image_19052023094237899.png
|
2023-05-19 09:42:37.990295 |
63 |
64775869 |
Construction of CC road from Kailash Nayak house to Behera sahi. |
200000 |
Construction of CC road from Kailash Nayak house to Behera sahi.1 |
Roof laid |
-
latitude : 21.348642627708614,21.34863709565252,21.348619577474892
Longitude : 86.52806432917714,86.52804857119918,86.52810011990368
file name : Image_08052023094551381.png
|
2023-05-08 09:45:51.483069 |
64 |
56139495 |
CONSTRUCTION OF CC ROAD FROM KELA SINGH HOUSE TO RAJENDRA SINGH HOUSE |
120000 |
CONSTRUCTION OF CC ROAD FROM KELA SINGH HOUSE TO RAJENDRA SINGH HOUSE1 |
Roof laid |
-
latitude : 21.34675749577582,21.34675908833742
Longitude : 86.55695607885718,86.55693671666086
file name : Image_08052023092409431.png
|
2023-05-08 09:24:09.517728 |
65 |
56139495 |
CONSTRUCTION OF CC ROAD FROM KELA SINGH HOUSE TO RAJENDRA SINGH HOUSE |
120000 |
CONSTRUCTION OF CC ROAD FROM KELA SINGH HOUSE TO RAJENDRA SINGH HOUSE1 |
Roof laid |
-
latitude : 21.346773086115718,21.34673440363258
Longitude : 86.55700377188623,86.55692431144416
file name : Image_08052023092121584.png
|
2023-05-08 09:21:21.677448 |
66 |
64776679 |
Operation & maintenance of drinking water supply system |
25000 |
Operation & maintenance of drinking water supply system1 |
Roof laid |
-
latitude : 21.3377078
Longitude : 86.5190628
file name : Image_09062023122759767.png
|
2023-06-09 12:27:59.860866 |
67 |
56138044 |
RAISE TUBE WELL PLATFORM WITH RECHARGE PIT NEAR AT RAGUDI PADA, LAXMISUL |
25000 |
RAISE TUBE WELL PLATFORM WITH RECHARGE PIT NEAR AT RAGUDI PADA, LAXMISUL1 |
Roof laid |
-
latitude : 21.331045785918832
Longitude : 86.50644455105066
file name : Image_09062023123823038.png
|
2023-06-09 12:38:23.126979 |
68 |
56138030 |
RAISE TUBE WELL PLATFORM WITH RECHARGE PIT NEAR NETAJI CLUB, SINGADAPUR |
25000 |
RAISE TUBE WELL PLATFORM WITH RECHARGE PIT NEAR NETAJI CLUB, SINGADAPUR1 |
Roof laid |
-
latitude : 21.337708
Longitude : 86.519064
file name : Image_09062023123013885.png
|
2023-06-09 12:30:13.987494 |
69 |
64776327 |
Construction of CC road from Karunakar Parida house to village road. |
130000 |
Construction of CC road from Karunakar Parida house to village road.1 |
Roof laid |
-
latitude : 21.341441441327333,21.341464365832508,21.341464365832508
Longitude : 86.55786124058068,86.5577550418675,86.5577550418675
file name : Image_23062023120905397.png
|
2023-06-23 12:09:05.485713 |
70 |
64777213 |
Repair of drainage channel |
145000 |
Repair of drainage channel1 |
Completion of work |
-
latitude : 21.3296026
Longitude : 86.5055903
file name : Image_03082023131405273.png
|
2023-08-03 13:14:05.375179 |
71 |
81183331 |
Operation and Maintenance of drinking water supply system |
468000 |
Operation and Maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 21.3296094
Longitude : 86.5056696
file name : Image_27092023145436686.png
|
2023-09-27 14:54:36.85916 |
72 |
86508301 |
CONST OF C C ROAD FROM BISWAL SAHI MAHADEV TEMPLE TO PWD ROAD |
100000 |
CONST OF C C ROAD FROM BISWAL SAHI MAHADEV TEMPLE TO PWD ROAD1 |
Commenced |
-
latitude : 21.3295586,21.3295639
Longitude : 86.5056755,86.5056702
file name : Image_18102023170630041.png
|
2023-10-18 17:06:30.112503 |
73 |
78127126 |
Repairing/Construction of Building |
60000 |
Repairing/Construction of Building1 |
Roof laid |
-
latitude : 21.3354261
Longitude : 86.5768848
file name : Image_13042024195954263.png
|
2024-04-13 19:59:54.361556 |
74 |
78127126 |
Repairing/Construction of Building |
60000 |
Repairing/Construction of Building1 |
Plinth level |
-
latitude : 21.3354272
Longitude : 86.5768846
file name : Image_13042024195759245.png
|
2024-04-13 19:57:59.316986 |
75 |
78127126 |
Repairing/Construction of Building |
60000 |
Repairing/Construction of Building1 |
Completion of work |
-
latitude : 21.3354243
Longitude : 86.5768912
file name : Image_13042024195620765.png
|
2024-04-13 19:56:20.852646 |
76 |
107551401 |
Installation of Street Light |
50000 |
Installation of Street Light1 |
Roof laid |
-
latitude : 21.335448
Longitude : 86.5769111
file name : Image_05092024135516103.png
|
2024-09-05 13:55:16.208275 |
77 |
107551401 |
Installation of Street Light |
50000 |
Installation of Street Light1 |
Plinth level |
-
latitude : 21.33551
Longitude : 86.57685000000001
file name : Image_05092024135343256.png
|
2024-09-05 13:53:43.348388 |
78 |
107551401 |
Installation of Street Light |
50000 |
Installation of Street Light1 |
Completion of work |
-
latitude : 21.3354482
Longitude : 86.5769122
file name : Image_05092024134855492.png
|
2024-09-05 13:48:55.565122 |
79 |
64775851 |
Construction of CC road from RD road to incomplete CC road Mohapatra sahi. |
150000 |
Construction of CC road from RD road to incomplete CC road Mohapatra sahi.1 |
Completion of work |
-
latitude : 21.29717333333333,21.297196666666665
Longitude : 86.66291166666666,86.66290833333332
file name : Image_25012024161503132.png
|
2024-01-25 16:15:03.238945 |
80 |
78076493 |
Boundary wall and Gate |
100000 |
Boundary wall and Gate1 |
Roof laid |
-
latitude : 21.3353204
Longitude : 86.5768882
file name : Image_22022024114237081.png
|
2024-02-22 11:42:37.186116 |
81 |
78076493 |
Boundary wall and Gate |
100000 |
Boundary wall and Gate1 |
Plinth level |
-
latitude : 21.335444
Longitude : 86.5768891
file name : Image_22022024114035741.png
|
2024-02-22 11:40:35.838247 |
82 |
78076493 |
Boundary wall and Gate |
100000 |
Boundary wall and Gate1 |
Completion of work |
-
latitude : 21.3351548
Longitude : 86.5769019
file name : Image_22022024113835023.png
|
2024-02-22 11:38:35.125161 |
83 |
78098547 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Roof laid |
-
latitude : 21.3354452
Longitude : 86.5768854
file name : Image_25022024181728635.png
|
2024-02-25 18:17:28.724147 |
84 |
78098547 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Plinth level |
-
latitude : 21.3354464
Longitude : 86.5768828
file name : Image_25022024181008891.png
|
2024-02-25 18:10:08.977722 |
85 |
78098547 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Completion of work |
-
latitude : 21.3354441
Longitude : 86.5768883
file name : Image_25022024174719861.png
|
2024-02-25 17:47:19.94799 |
86 |
78097312 |
Installation of Solar lights |
50000 |
Installation of Solar lights1 |
Roof laid |
-
latitude : 21.3354443
Longitude : 86.5768869
file name : Image_25022024181930884.png
|
2024-02-25 18:19:30.980301 |
87 |
78097312 |
Installation of Solar lights |
50000 |
Installation of Solar lights1 |
Plinth level |
-
latitude : 21.3354445
Longitude : 86.5768871
file name : Image_25022024181208739.png
|
2024-02-25 18:12:08.840236 |
88 |
78097312 |
Installation of Solar lights |
50000 |
Installation of Solar lights1 |
Completion of work |
-
latitude : 21.3354439
Longitude : 86.5768885
file name : Image_25022024180301289.png
|
2024-02-25 18:03:01.395157 |
89 |
78095865 |
Installation of Solar lights |
50000 |
Installation of Solar lights1 |
Roof laid |
-
latitude : 21.3354438
Longitude : 86.5768887
file name : Image_25022024181848886.png
|
2024-02-25 18:18:48.979923 |
90 |
78095865 |
Installation of Solar lights |
50000 |
Installation of Solar lights1 |
Plinth level |
-
latitude : 21.3354446
Longitude : 86.5768864
file name : Image_25022024181046961.png
|
2024-02-25 18:10:47.05078 |
91 |
78095865 |
Installation of Solar lights |
50000 |
Installation of Solar lights1 |
Completion of work |
-
latitude : 21.3354441
Longitude : 86.5768876
file name : Image_25022024180145278.png
|
2024-02-25 18:01:45.370166 |
92 |
78101971 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Roof laid |
-
latitude : 21.3354449
Longitude : 86.5768864
file name : Image_25022024182003591.png
|
2024-02-25 18:20:03.69551 |
93 |
78101971 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Plinth level |
-
latitude : 21.335445
Longitude : 86.5768863
file name : Image_25022024181245954.png
|
2024-02-25 18:12:46.049657 |
94 |
78101971 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Completion of work |
-
latitude : 21.3354442
Longitude : 86.5768883
file name : Image_25022024180337853.png
|
2024-02-25 18:03:37.955348 |
95 |
78100764 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Roof laid |
-
latitude : 21.3354443
Longitude : 86.5768869
file name : Image_25022024181852299.png
|
2024-02-25 18:18:52.392338 |
96 |
78100764 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Plinth level |
-
latitude : 21.3354442
Longitude : 86.5768874
file name : Image_25022024181132239.png
|
2024-02-25 18:11:32.326391 |
97 |
78100764 |
Installation of Street Lights |
50000 |
Installation of Street Lights1 |
Completion of work |
-
latitude : 21.3354451
Longitude : 86.5768859
file name : Image_25022024180226388.png
|
2024-02-25 18:02:26.482042 |
98 |
56139513 |
FOUNDATION OF MAHATMA GANDHI STATUE AT GP AREA |
20000 |
FOUNDATION OF MAHATMA GANDHI STATUE AT GP AREA1 |
Completion of work |
-
latitude : 21.3521311
Longitude : 86.5355048
file name : Image_28032024114221625.png
|
2024-03-28 11:42:21.734528 |
99 |
78555080 |
Construction of Segregation Unit |
66000 |
Construction of Segregation Unit1 |
Roof laid |
-
latitude : 21.3294111
Longitude : 86.5057258
file name : Image_28032024141613193.png
|
2024-03-28 14:16:13.277772 |
100 |
78555080 |
Construction of Segregation Unit |
66000 |
Construction of Segregation Unit1 |
Plinth level |
-
latitude : 21.3294058
Longitude : 86.5057242
file name : Image_28032024141432974.png
|
2024-03-28 14:14:33.105091 |
101 |
78555080 |
Construction of Segregation Unit |
66000 |
Construction of Segregation Unit1 |
Completion of work |
-
latitude : 21.3294038
Longitude : 86.5057245
file name : Image_28032024141308568.png
|
2024-03-28 14:13:08.64509 |
102 |
64777001 |
Creation of Shed for segregation and processing of wet and dry waste |
54000 |
Creation of Shed for segregation and processing of wet and dry waste1 |
Plinth level |
-
latitude : 21.3293891
Longitude : 86.5057245
file name : Image_28032024151848540.png
|
2024-03-28 15:18:48.63547 |
103 |
64777001 |
Creation of Shed for segregation and processing of wet and dry waste |
54000 |
Creation of Shed for segregation and processing of wet and dry waste1 |
Completion of work |
-
latitude : 21.3294026
Longitude : 86.5057283
file name : Image_28032024151704217.png
|
2024-03-28 15:17:04.306321 |
104 |
81187035 |
Water Supply to villages |
10000 |
Water Supply to villages1 |
Roof laid |
-
latitude : 21.3354604
Longitude : 86.5769
file name : Image_29032024203510605.png
|
2024-03-29 20:35:10.696422 |
105 |
81187035 |
Water Supply to villages |
10000 |
Water Supply to villages1 |
Plinth level |
-
latitude : 21.3354275
Longitude : 86.576885
file name : Image_29032024203343773.png
|
2024-03-29 20:33:43.869135 |
106 |
81187035 |
Water Supply to villages |
10000 |
Water Supply to villages1 |
Completion of work |
-
latitude : 21.3354643
Longitude : 86.5768988
file name : Image_29032024203148317.png
|
2024-03-29 20:31:48.414274 |
107 |
106661263 |
Retrofitting of single pit toilets to twin pit toilets |
241500 |
Retrofitting of single pit toilets to twin pit toilets1 |
Roof laid |
-
latitude : 19.7943746
Longitude : 85.8195931
file name : Image_24062024125838225.png
|
2024-06-24 12:58:38.314843 |
108 |
106661263 |
Retrofitting of single pit toilets to twin pit toilets |
241500 |
Retrofitting of single pit toilets to twin pit toilets1 |
Plinth level |
-
latitude : 19.7943748
Longitude : 85.8195939
file name : Image_24062024125636650.png
|
2024-06-24 12:56:36.745567 |
109 |
106661263 |
Retrofitting of single pit toilets to twin pit toilets |
241500 |
Retrofitting of single pit toilets to twin pit toilets1 |
Completion of work |
-
latitude : 19.7943741
Longitude : 85.8195933
file name : Image_24062024124438912.png
|
2024-06-24 12:44:39.001454 |
110 |
81184673 |
Operation and Maintenance of drinking water supply system |
24000 |
Operation and Maintenance of drinking water supply system1 |
Roof laid |
-
latitude : 21.676926666666667
Longitude : 87.12327833333332
file name : Image_03112023173906124.png
|
2023-11-03 17:39:06.22088 |
111 |
81184673 |
Operation and Maintenance of drinking water supply system |
24000 |
Operation and Maintenance of drinking water supply system1 |
Plinth level |
-
latitude : 21.679436666666668
Longitude : 87.10624666666666
file name : Image_03112023173245302.png
|
2023-11-03 17:32:45.378842 |
112 |
81184673 |
Operation and Maintenance of drinking water supply system |
24000 |
Operation and Maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 21.329558
Longitude : 86.5056715
file name : Image_01112023163940255.png
|
2023-11-01 16:39:40.419122 |
113 |
78552557 |
Retrofitting of single pit toilets to twin pit toilets |
70000 |
Retrofitting of single pit toilets to twin pit toilets1 |
Roof laid |
-
latitude : 21.3521408
Longitude : 86.5355211
file name : Image_01072024123244541.png
|
2024-07-01 12:32:44.645566 |
114 |
78552557 |
Retrofitting of single pit toilets to twin pit toilets |
70000 |
Retrofitting of single pit toilets to twin pit toilets1 |
Plinth level |
-
latitude : 21.3521412
Longitude : 86.5355207
file name : Image_01072024123029801.png
|
2024-07-01 12:30:29.892666 |
115 |
78552557 |
Retrofitting of single pit toilets to twin pit toilets |
70000 |
Retrofitting of single pit toilets to twin pit toilets1 |
Completion of work |
-
latitude : 21.3521408
Longitude : 86.5355211
file name : Image_01072024122812239.png
|
2024-07-01 12:28:12.343962 |
116 |
107099588 |
Greywater management system |
100000 |
Greywater management system1 |
Completion of work |
-
latitude : 21.3354556
Longitude : 86.5768997
file name : Image_22072024091512427.png
|
2024-07-22 09:15:12.532925 |
117 |
107099601 |
Greywater management system |
79000 |
Greywater management system1 |
Completion of work |
-
latitude : 21.3354485
Longitude : 86.5768907
file name : Image_22072024091606675.png
|
2024-07-22 09:16:06.778687 |
118 |
78079755 |
Construction of Boundary Wall |
100000 |
Construction of Boundary Wall1 |
Roof laid |
-
latitude : 21.285995000000003
Longitude : 86.67093500000001
file name : Image_19102024111301915.png
|
2024-10-19 11:13:02.014296 |
119 |
78079755 |
Construction of Boundary Wall |
100000 |
Construction of Boundary Wall1 |
Plinth level |
-
latitude : 21.286044999999998
Longitude : 86.67092166666667
file name : Image_19102024111017245.png
|
2024-10-19 11:10:17.073278 |
120 |
78079755 |
Construction of Boundary Wall |
100000 |
Construction of Boundary Wall1 |
Completion of work |
-
latitude : 21.286025000000002
Longitude : 86.67097
file name : Image_19102024110528182.png
|
2024-10-19 11:05:28.289101 |
121 |
78085058 |
Construction of roads |
100000 |
Construction of roads1 |
Roof laid |
-
latitude : 21.285238333333336,21.285238333333336
Longitude : 86.67069833333335,86.67069833333335
file name : Image_19102024111415348.png
|
2024-10-19 11:14:15.423271 |
122 |
78085058 |
Construction of roads |
100000 |
Construction of roads1 |
Plinth level |
-
latitude : 21.285956666666667,21.286005
Longitude : 86.67092,86.670905
file name : Image_19102024110915738.png
|
2024-10-19 11:09:15.815222 |
123 |
78085058 |
Construction of roads |
100000 |
Construction of roads1 |
Completion of work |
-
latitude : 21.286026666666665,21.286025000000002
Longitude : 86.67092,86.67092166666667
file name : Image_19102024110630173.png
|
2024-10-19 11:06:30.252165 |
124 |
78124073 |
Repairing and maintenance of roads |
100000 |
Repairing and maintenance of roads1 |
Roof laid |
-
latitude : 21.3295486,21.329706666666667
Longitude : 86.5056624,86.50556499999999
file name : Image_19102024134123021.png
|
2024-10-19 13:41:22.479917 |
125 |
78124073 |
Repairing and maintenance of roads |
100000 |
Repairing and maintenance of roads1 |
Plinth level |
-
latitude : 21.3295569,21.28578
Longitude : 86.5056404,86.66956
file name : Image_19102024133938318.png
|
2024-10-19 13:39:38.404994 |
126 |
78124073 |
Repairing and maintenance of roads |
100000 |
Repairing and maintenance of roads1 |
Completion of work |
-
latitude : 21.3295512,21.3295498
Longitude : 86.505666,86.5056614
file name : Image_19102024133746687.png
|
2024-10-19 13:37:46.300738 |
127 |
101103372 |
Construction of Retaining Walls/ Fencing Work |
100000 |
Construction of Retaining Walls/ Fencing Work1 |
Roof laid |
-
latitude : 21.286025000000002
Longitude : 86.67089499999999
file name : Image_19102024114245118.png
|
2024-10-19 11:42:44.38936 |
128 |
101103372 |
Construction of Retaining Walls/ Fencing Work |
100000 |
Construction of Retaining Walls/ Fencing Work1 |
Plinth level |
-
latitude : 21.286026666666665
Longitude : 86.67087166666667
file name : Image_19102024113636118.png
|
2024-10-19 11:36:36.204724 |
129 |
101103372 |
Construction of Retaining Walls/ Fencing Work |
100000 |
Construction of Retaining Walls/ Fencing Work1 |
Completion of work |
-
latitude : 21.286040000000003
Longitude : 86.67088833333334
file name : Image_19102024113354580.png
|
2024-10-19 11:33:54.665671 |
130 |
101100308 |
Construction of roads |
100000 |
Construction of roads1 |
Roof laid |
-
latitude : 21.28605,21.28602166666667
Longitude : 86.67094833333334,86.67092833333332
file name : Image_19102024114209076.png
|
2024-10-19 11:42:09.160354 |
131 |
101100308 |
Construction of roads |
100000 |
Construction of roads1 |
Plinth level |
-
latitude : 21.28603666666667,21.286025000000002
Longitude : 86.67088333333335,86.67089166666668
file name : Image_19102024113814643.png
|
2024-10-19 11:38:14.744051 |
132 |
101100308 |
Construction of roads |
100000 |
Construction of roads1 |
Completion of work |
-
latitude : 21.286043333333335,21.286043333333335
Longitude : 86.67086833333333,86.67086833333333
file name : Image_19102024113350656.png
|
2024-10-19 11:33:50.734755 |
133 |
101027326 |
Retrofitting of single pit toilets to twin pit toilets |
308000 |
Retrofitting of single pit toilets to twin pit toilets1 |
Roof laid |
-
latitude : 21.3293409
Longitude : 86.5057639
file name : Image_21102024154821611.png
|
2024-10-21 15:48:21.701991 |
134 |
101027326 |
Retrofitting of single pit toilets to twin pit toilets |
308000 |
Retrofitting of single pit toilets to twin pit toilets1 |
Plinth level |
-
latitude : 21.3293404
Longitude : 86.5057641
file name : Image_21102024154607759.png
|
2024-10-21 15:46:07.86564 |
135 |
101027326 |
Retrofitting of single pit toilets to twin pit toilets |
308000 |
Retrofitting of single pit toilets to twin pit toilets1 |
Completion of work |
-
latitude : 21.3293405
Longitude : 86.5057643
file name : Image_21102024154420076.png
|
2024-10-21 15:44:21.08999 |
136 |
78553704 |
Creation of community soak pits for group of Households |
40500 |
Creation of community soak pits for group of Households1 |
Roof laid |
-
latitude : 21.3295431
Longitude : 86.5057069
file name : Image_05082024135502074.png
|
2024-08-05 13:55:02.163783 |
137 |
78553704 |
Creation of community soak pits for group of Households |
40500 |
Creation of community soak pits for group of Households1 |
Plinth level |
-
latitude : 21.329552
Longitude : 86.505703
file name : Image_05082024134948727.png
|
2024-08-05 13:49:48.821986 |
138 |
78553704 |
Creation of community soak pits for group of Households |
40500 |
Creation of community soak pits for group of Households1 |
Completion of work |
-
latitude : 21.3292711
Longitude : 86.5057464
file name : Image_05082024130622283.png
|
2024-08-05 13:06:22.386729 |