1 |
44342249 |
Const. Of Dudungchuan AWC Boundary |
100000 |
Const. Of Dudungchuan AWC Boundary1 |
Completion of work |
-
latitude : 19.33659042
Longitude : 82.8353087
file name : Image_23042021121235580.png
|
2021-04-23 12:12:35.663964 |
2 |
44342322 |
Repairing of GP Godown |
198900 |
Repairing of GP Godown1 |
Completion of work |
-
latitude : 19.55476638
Longitude : 82.69563618
file name : Image_06092021160323882.png
|
2021-09-06 16:03:23.968389 |
3 |
44342184 |
Repairing of Benakhamar AWC |
100000 |
Repairing of Benakhamar AWC1 |
Completion of work |
-
latitude : 19.55471589
Longitude : 82.69560575
file name : Image_23082021184904207.png
|
2021-08-23 18:49:04.318796 |
4 |
52382655 |
CONST OF G W WITH DRAIN AT BENAKHAMAR CANALPADA |
100000 |
CONST OF G W WITH DRAIN AT BENAKHAMAR CANALPADA1 |
Completion of work |
-
latitude : 19.32954991,19.32981883
Longitude : 82.82864889,82.82857023
file name : Image_28062021122258908.png
|
2021-06-28 12:22:59.002935 |
5 |
52382142 |
CONST OF CULVERT WITH GHAT CUTTING FROM TANGANIGUDA TO UPARCHOBRI |
100000 |
CONST OF CULVERT WITH GHAT CUTTING FROM TANGANIGUDA TO UPARCHOBRI1 |
Completion of work |
-
latitude : 19.5478603,19.5478603
Longitude : 82.9335613,82.9335613
file name : Image_06072021122949125.png
|
2021-07-06 12:29:49.254515 |
6 |
52382035 |
CONST OF DRAIN FROM GOUD SAHI TO ADIVASIPADAFUKIJAL |
100000 |
CONST OF DRAIN FROM GOUD SAHI TO ADIVASIPADAFUKIJAL1 |
Completion of work |
-
latitude : 19.34636457,19.34631751
Longitude : 82.84923223,82.84968762
file name : Image_28062021195154193.png
|
2021-06-28 19:51:54.293209 |
7 |
52381029 |
IMP OF CC ROAD WITH GHAT CUTTING FROM KHAMARPADAR TO CHIKONKHADAK |
100000 |
IMP OF CC ROAD WITH GHAT CUTTING FROM KHAMARPADAR TO CHIKONKHADAK1 |
Completion of work |
-
latitude : 19.5478592,19.5478592
Longitude : 82.9335624,82.9335624
file name : Image_06072021122542267.png
|
2021-07-06 12:25:42.478867 |
8 |
52381029 |
IMP OF CC ROAD WITH GHAT CUTTING FROM KHAMARPADAR TO CHIKONKHADAK |
100000 |
IMP OF CC ROAD WITH GHAT CUTTING FROM KHAMARPADAR TO CHIKONKHADAK1 |
Completion of work |
-
latitude : 19.5478572,19.5478572
Longitude : 82.9335636,82.9335636
file name : Image_06072021122547260.png
|
2021-07-06 12:25:47.383546 |
9 |
52381029 |
IMP OF CC ROAD WITH GHAT CUTTING FROM KHAMARPADAR TO CHIKONKHADAK |
100000 |
IMP OF CC ROAD WITH GHAT CUTTING FROM KHAMARPADAR TO CHIKONKHADAK1 |
Completion of work |
-
latitude : 19.5478572,19.5478572
Longitude : 82.9335636,82.9335636
file name : Image_06072021122556847.png
|
2021-07-06 12:25:57.025721 |
10 |
52382724 |
REPAIRING OF SANCHHATRANG PRIMARY SCHOOL |
100000 |
REPAIRING OF SANCHHATRANG PRIMARY SCHOOL1 |
Completion of work |
-
latitude : 19.44171709
Longitude : 82.85362569
file name : Image_03092021131704155.png
|
2021-09-03 13:17:04.384875 |
11 |
52382724 |
REPAIRING OF SANCHHATRANG PRIMARY SCHOOL |
100000 |
REPAIRING OF SANCHHATRANG PRIMARY SCHOOL1 |
Completion of work |
-
latitude : 19.44170325
Longitude : 82.85365426
file name : Image_03092021131810351.png
|
2021-09-03 13:18:10.453958 |
12 |
52382551 |
IMP OF CC FROM BHOBADAPADAR TO UPERCHOBRI |
100000 |
IMP OF CC FROM BHOBADAPADAR TO UPERCHOBRI1 |
Completion of work |
-
latitude : 19.34927688,19.34905209
Longitude : 82.8421304,82.84186644
file name : Image_28062021195209291.png
|
2021-06-28 19:52:09.386171 |
13 |
52382448 |
REPAIRING OF BHUTGUDA AWC |
100000 |
REPAIRING OF BHUTGUDA AWC1 |
Completion of work |
-
latitude : 19.55471347
Longitude : 82.69571951
file name : Image_24102021182021713.png
|
2021-10-24 18:20:21.826512 |
14 |
52381812 |
REPAIRING OF SANITARYWELL AT SANACHHATRANG |
40000 |
REPAIRING OF SANITARYWELL AT SANACHHATRANG1 |
Completion of work |
-
latitude : 19.55477888
Longitude : 82.69559783
file name : Image_22082021204214809.png
|
2021-08-22 20:42:14.940384 |
15 |
52381768 |
REPAIRING OF SANITARARYWELL AT DUDUNGCHUAN |
40000 |
REPAIRING OF SANITARARYWELL AT DUDUNGCHUAN1 |
Completion of work |
-
latitude : 19.55466664
Longitude : 82.69557629
file name : Image_28072021124724987.png
|
2021-07-28 12:47:25.091655 |
16 |
52381707 |
REPAIRING OF SANITARY WELL AT CHIKONKHADAK |
40000 |
REPAIRING OF SANITARY WELL AT CHIKONKHADAK1 |
Completion of work |
-
latitude : 19.5479542
Longitude : 82.9335597
file name : Image_30072021110606320.png
|
2021-07-30 11:06:06.389498 |
17 |
52381707 |
REPAIRING OF SANITARY WELL AT CHIKONKHADAK |
40000 |
REPAIRING OF SANITARY WELL AT CHIKONKHADAK1 |
Completion of work |
-
latitude : 19.55466509
Longitude : 82.6955799
file name : Image_28072021131105334.png
|
2021-07-28 13:11:05.429568 |
18 |
52381450 |
MINOR AND REPAIRING GATE AND COLOURING OF GP OFFICE |
350000 |
MINOR AND REPAIRING GATE AND COLOURING OF GP OFFICE1 |
Completion of work |
-
latitude : 19.55465557,19.55465616
Longitude : 82.69558504,82.69558465
file name : Image_06092021161907711.png
|
2021-09-06 16:19:07.822981 |
19 |
52381179 |
IMP OF CC ROAD FROM AGARGRAMEE TO GP OFFICE |
200000 |
IMP OF CC ROAD FROM AGARGRAMEE TO GP OFFICE 1 |
Completion of work |
-
latitude : 19.33646361,19.33689384
Longitude : 82.84115477,82.84096303
file name : Image_28062021195131039.png
|
2021-06-28 19:51:31.136332 |
20 |
52381095 |
IMP OF CC ROAD WITH GHATING FORM RD ROAD TO HADSIL TALPADA |
100000 |
IMP OF CC ROAD WITH GHATING FORM RD ROAD TO HADSIL TALPADA1 |
Completion of work |
-
latitude : 19.33457519,19.3342913
Longitude : 82.80006488,82.80046437
file name : Image_28062021112836156.png
|
2021-06-28 11:28:36.262955 |
21 |
47804920 |
Cost of Jalachhatra |
42613 |
Cost of Jalachhatra1 |
Completion of work |
-
latitude : 19.5478913
Longitude : 82.9335592
file name : Image_30072021114713196.png
|
2021-07-30 11:47:13.290608 |
22 |
47804920 |
Cost of Jalachhatra |
42613 |
Cost of Jalachhatra1 |
Completion of work |
-
latitude : 19.5478612
Longitude : 82.9335633
file name : Image_30072021114719929.png
|
2021-07-30 11:47:20.032764 |
23 |
44342221 |
Electrification of 7Nos of School @15000/School |
105000 |
Electrification of 7Nos of School @15000/School1 |
Completion of work |
-
latitude : 19.5478627
Longitude : 82.9335639
file name : Image_11082021103144536.png
|
2021-08-11 10:31:44.624085 |
24 |
44342221 |
Electrification of 7Nos of School @15000/School |
105000 |
Electrification of 7Nos of School @15000/School1 |
Completion of work |
-
latitude : 19.5478586
Longitude : 82.9335612
file name : Image_11082021103140665.png
|
2021-08-11 10:31:40.768425 |
25 |
44342221 |
Electrification of 7Nos of School @15000/School |
105000 |
Electrification of 7Nos of School @15000/School1 |
Completion of work |
-
latitude : 19.5478627
Longitude : 82.9335639
file name : Image_11082021103148548.png
|
2021-08-11 10:31:48.637978 |
26 |
53583317 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN |
50000 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN1 |
Completion of work |
-
latitude : 19.55473337,19.55473286
Longitude : 82.69568003,82.69568412
file name : Image_24082021210736321.png
|
2021-08-24 21:07:36.395941 |
27 |
53583317 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN |
50000 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN1 |
Completion of work |
-
latitude : 19.55472172,19.55472283
Longitude : 82.69567687,82.69567623
file name : Image_24082021210730786.png
|
2021-08-24 21:07:30.864027 |
28 |
53583317 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN |
50000 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN1 |
Completion of work |
-
latitude : 19.55470929,19.55472764
Longitude : 82.69559935,82.69567995
file name : Image_24082021210723090.png
|
2021-08-24 21:07:23.184184 |
29 |
53583317 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN |
50000 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN1 |
Completion of work |
-
latitude : 19.55473525,19.55473255
Longitude : 82.69568465,82.69568341
file name : Image_24082021210742123.png
|
2021-08-24 21:07:42.228874 |
30 |
53583226 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN |
50000 |
CONST OF CULVERT WITH CC ROAD FROM KALIMANDIR TO DUDUNGCHUAN1 |
Completion of work |
-
latitude : 19.5478636,19.5478627
Longitude : 82.9335632,82.9335622
file name : Image_24082021102233179.png
|
2021-08-24 10:22:33.273141 |
31 |
56075104 |
SFC IMPROVEMENT OF ROAD WITH GHAT CUTTING FROM CHIKONKHADAK TO KHAMARPADAR |
100000 |
SFC IMPROVEMENT OF ROAD WITH GHAT CUTTING FROM CHIKONKHADAK TO KHAMARPADAR1 |
Completion of work |
-
latitude : 19.55473314,19.55473319
Longitude : 82.69562097,82.69562094
file name : Image_17022022203020732.png
|
2022-02-17 20:30:20.853331 |
32 |
56155807 |
DIGGING OF TUBE WELLS AT MARKET COMPLEX PLACE OF BENAKHAMAR VILLAGE |
73500 |
DIGGING OF TUBE WELLS AT MARKET COMPLEX PLACE OF BENAKHAMAR VILLAGE1 |
Completion of work |
-
latitude : 19.55473439
Longitude : 82.69562298
file name : Image_17022022202900968.png
|
2022-02-17 20:29:01.053823 |
33 |
56155807 |
DIGGING OF TUBE WELLS AT MARKET COMPLEX PLACE OF BENAKHAMAR VILLAGE |
73500 |
DIGGING OF TUBE WELLS AT MARKET COMPLEX PLACE OF BENAKHAMAR VILLAGE1 |
Completion of work |
-
latitude : 19.55473637
Longitude : 82.69561822
file name : Image_17022022202757394.png
|
2022-02-17 20:27:57.487315 |
34 |
56155790 |
DIGGING OF TUBE WELL AT SANCHHATARANG VILLAGE |
73575 |
DIGGING OF TUBE WELL AT SANCHHATARANG VILLAGE1 |
Completion of work |
-
latitude : 19.5479496
Longitude : 82.933476
file name : Image_19022022105040242.png
|
2022-02-19 10:50:40.347982 |
35 |
52381232 |
RENOVATION OF PADEPADAR POND |
300000 |
RENOVATION OF PADEPADAR POND1 |
Completion of work |
-
latitude : 19.55474298
Longitude : 82.69562
file name : Image_17022022202741221.png
|
2022-02-17 20:27:41.310759 |
36 |
52381232 |
RENOVATION OF PADEPADAR POND |
300000 |
RENOVATION OF PADEPADAR POND1 |
Completion of work |
-
latitude : 19.55475043
Longitude : 82.69562326
file name : Image_17022022202737987.png
|
2022-02-17 20:27:38.074672 |
37 |
52381232 |
RENOVATION OF PADEPADAR POND |
300000 |
RENOVATION OF PADEPADAR POND1 |
Completion of work |
-
latitude : 19.55475595
Longitude : 82.6956255
file name : Image_17022022202734812.png
|
2022-02-17 20:27:34.913035 |
38 |
56075098 |
Sfc COMPLETION OF UP SCHOOL BOUNDARY WALL DURESHPADAR |
100000 |
Sfc COMPLETION OF UP SCHOOL BOUNDARY WALL DURESHPADAR1 |
Completion of work |
-
latitude : 19.55468759
Longitude : 82.69565292
file name : Image_13012022183307039.png
|
2022-01-13 18:33:07.147748 |
39 |
56075228 |
UT IMPROVEMENT OF ROAD WITH CC FROM RD ROAD TO COLONY PADA |
100000 |
UT IMPROVEMENT OF ROAD WITH CC FROM RD ROAD TO COLONY PADA1 |
Completion of work |
-
latitude : 19.55467352,19.55467407
Longitude : 82.69563657,82.6956287
file name : Image_13012022183444263.png
|
2022-01-13 18:34:44.35678 |
40 |
56075094 |
Sfc maintenance and electrification with water supply of gp office and GW with Cc infront of GP offi |
355900 |
Sfc maintenance and electrification with water supply of gp office and GW with Cc infront of GP offi1 |
Completion of work |
-
latitude : 19.5334009
Longitude : 82.8111821
file name : Image_02052022111433927.png
|
2022-05-02 11:14:34.013346 |
41 |
56075108 |
SFC IMPROVEMENT OF ROAD WITH GHAT CUTTING FROM BHUTGUDA TO SINDER |
100000 |
SFC IMPROVEMENT OF ROAD WITH GHAT CUTTING FROM BHUTGUDA TO SINDER1 |
Completion of work |
-
latitude : 19.5334009,19.5334009
Longitude : 82.8111821,82.8111821
file name : Image_02052022113628289.png
|
2022-05-02 11:36:28.396184 |
42 |
47799670 |
Construction of Platform of Tubewell of GP area 7 Nos |
70000 |
Construction of Platform of Tubewell of GP area 7 Nos1 |
Completion of work |
-
latitude : 19.5334009
Longitude : 82.8111821
file name : Image_02052022113338569.png
|
2022-05-02 11:33:38.682258 |
43 |
47799670 |
Construction of Platform of Tubewell of GP area 7 Nos |
70000 |
Construction of Platform of Tubewell of GP area 7 Nos2 |
Completion of work |
-
latitude : 19.5334009
Longitude : 82.8111821
file name : Image_02052022113343192.png
|
2022-05-02 11:33:43.286054 |
44 |
47799670 |
Construction of Platform of Tubewell of GP area 7 Nos |
70000 |
Construction of Platform of Tubewell of GP area 7 Nos3 |
Completion of work |
-
latitude : 19.5334009
Longitude : 82.8111821
file name : Image_02052022113348472.png
|
2022-05-02 11:33:48.570773 |
45 |
47799670 |
Construction of Platform of Tubewell of GP area 7 Nos |
70000 |
Construction of Platform of Tubewell of GP area 7 Nos4 |
Completion of work |
-
latitude : 19.5334009
Longitude : 82.8111821
file name : Image_02052022113353054.png
|
2022-05-02 11:33:53.162647 |
46 |
47799670 |
Construction of Platform of Tubewell of GP area 7 Nos |
70000 |
Construction of Platform of Tubewell of GP area 7 Nos5 |
Completion of work |
-
latitude : 19.5334009
Longitude : 82.8111821
file name : Image_02052022113357900.png
|
2022-05-02 11:33:57.984715 |
47 |
56155753 |
PROVISION FOR ASSURED SAFE PIPE WATER SUPPLY TO KARDAPAS GOVT. PRIMARY SCHOOL |
50791 |
PROVISION FOR ASSURED SAFE PIPE WATER SUPPLY TO KARDAPAS GOVT. PRIMARY SCHOOL1 |
Completion of work |
-
latitude : 19.5334009,19.5334009,19.5334009
Longitude : 82.8111821,82.8111821,82.8111821
file name : Image_02052022114316118.png
|
2022-05-02 11:43:16.240651 |
48 |
56155769 |
PROVIDE ASSURED SAFE PIPED WATER SUPPLY TO HADSIL AWC |
59425 |
PROVIDE ASSURED SAFE PIPED WATER SUPPLY TO HADSIL AWC1 |
Completion of work |
-
latitude : 19.4444055,19.4444055
Longitude : 82.858846,82.858846
file name : Image_19062022122849531.png
|
2022-06-19 12:28:49.623249 |
49 |
56075250 |
UT CC AT MISSION SHAKTI CAMPUS |
88198 |
UT CC AT MISSION SHAKTI CAMPUS1 |
Completion of work |
-
latitude : 19.4444055,19.4444055
Longitude : 82.858846,82.858846
file name : Image_19062022122437392.png
|
2022-06-19 12:24:37.481606 |
50 |
56075241 |
UT IMPROVEMENT OF ROAD WITH GHAT CUTTING FROM RD ROAD TO TIKARPADA HADSIL |
100000 |
UT IMPROVEMENT OF ROAD WITH GHAT CUTTING FROM RD ROAD TO TIKARPADA HADSIL1 |
Completion of work |
-
latitude : 19.5479059,19.5479059
Longitude : 82.9333654,82.9333654
file name : Image_14072022110058841.png
|
2022-07-14 11:00:58.948325 |
51 |
61792385 |
SEM Salary |
72000 |
SEM Salary1 |
Completion of work |
-
latitude : 19.85598576
Longitude : 82.81411351
file name : Image_17082022192414534.png
|
2022-08-17 19:24:14.625392 |
52 |
47799953 |
Purchase of bleaching powder |
5000 |
Purchase of bleaching powder1 |
Completion of work |
-
latitude : 19.866128
Longitude : 82.7865452
file name : Image_24082022173602759.png
|
2022-08-24 17:36:02.866371 |
53 |
44307530 |
Digging of Tubewell at Bhatipas |
80000 |
Digging of Tubewell at Bhatipas1 |
Completion of work |
-
latitude : 19.8663223
Longitude : 82.7862039
file name : Image_30092022180618468.png
|
2022-09-30 18:06:18.549137 |
54 |
44307520 |
Digging of Tubewell at Dureshpadar Totasahi |
80000 |
Digging of Tubewell at Dureshpadar Totasahi1 |
Completion of work |
-
latitude : 19.8663223
Longitude : 82.7862039
file name : Image_30092022180351083.png
|
2022-09-30 18:03:51.172317 |
55 |
56155797 |
DIGGING OF TUBE WELL AT PADEPADAR RURAL PARK |
73500 |
DIGGING OF TUBE WELL AT PADEPADAR RURAL PARK1 |
Completion of work |
-
latitude : 19.84947744
Longitude : 82.83378468
file name : Image_30092022180751313.png
|
2022-09-30 18:07:51.398927 |
56 |
31122372 |
Digging of Tubewell at Bhutguda Tentulipada |
87000 |
Digging of Tubewell at Bhutguda Tentulipada1 |
Commenced |
-
latitude : 19.8663222
Longitude : 82.7862028
file name : Image_30092022180231963.png
|
2022-09-30 18:02:32.048767 |
57 |
31122395 |
Digging of Tubewell at Kendupada Khamarpadar |
87000 |
Digging of Tubewell at Kendupada Khamarpadar1 |
Commenced |
-
latitude : 19.8663225
Longitude : 82.7862525
file name : Image_30092022180120790.png
|
2022-09-30 18:01:20.885387 |
58 |
64870559 |
GP CONTIGENCY |
50000 |
GP CONTIGENCY1 |
Completion of work |
-
latitude : 19.5478603
Longitude : 82.9334769
file name : Image_11112022110301125.png
|
2022-11-11 11:03:01.238782 |
59 |
64870641 |
Water Supply to villages |
166544 |
Water Supply to villages1 |
Completion of work |
-
latitude : 19.5478558
Longitude : 82.9334759
file name : Image_11112022110132932.png
|
2022-11-11 11:01:33.040035 |
60 |
56075208 |
UT IMPROVEMENT OF 5T SCHOOL PADEPADAR UGHS |
300000 |
UT IMPROVEMENT OF 5T SCHOOL PADEPADAR UGHS1 |
Completion of work |
-
latitude : 19.5478556
Longitude : 82.9334774
file name : Image_11112022111947771.png
|
2022-11-11 11:19:47.888595 |
61 |
56075208 |
UT IMPROVEMENT OF 5T SCHOOL PADEPADAR UGHS |
300000 |
UT IMPROVEMENT OF 5T SCHOOL PADEPADAR UGHS1 |
Completion of work |
-
latitude : 19.547949
Longitude : 82.9334755
file name : Image_20012022115014920.png
|
2022-01-20 11:50:15.019741 |
62 |
64870602 |
Creation of a new source of drinking water |
50000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 19.5478634
Longitude : 82.9334696
file name : Image_23122022181123137.png
|
2022-12-23 18:11:23.21628 |
63 |
64870602 |
Creation of a new source of drinking water |
50000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 19.5478625
Longitude : 82.9334739
file name : Image_23122022181314423.png
|
2022-12-23 18:13:14.539458 |
64 |
64870446 |
Repari & Manantance of CC Road Dungali Nala RD Road to Khamarpadar Road |
108992 |
Repari & Manantance of CC Road Dungali Nala RD Road to Khamarpadar Road 1 |
Completion of work |
-
latitude : 19.5478638,19.5478643
Longitude : 82.9334718,82.9334711
file name : Image_23122022183229377.png
|
2022-12-23 18:32:29.46625 |
65 |
64870446 |
Repari & Manantance of CC Road Dungali Nala RD Road to Khamarpadar Road |
108992 |
Repari & Manantance of CC Road Dungali Nala RD Road to Khamarpadar Road 1 |
Completion of work |
-
latitude : 19.5478626,19.5478578
Longitude : 82.9334732,82.9334759
file name : Image_23122022183235838.png
|
2022-12-23 18:32:35.924517 |
66 |
64870433 |
Repari & Maintanance of Drain AWC to Amba Gachha at Mundighati |
100000 |
Repari & Maintanance of Drain AWC to Amba Gachha at Mundighati1 |
Completion of work |
-
latitude : 19.5478632,19.5478632
Longitude : 82.9334697,82.9334697
file name : Image_23122022183319943.png
|
2022-12-23 18:33:20.030782 |
67 |
64870433 |
Repari & Maintanance of Drain AWC to Amba Gachha at Mundighati |
100000 |
Repari & Maintanance of Drain AWC to Amba Gachha at Mundighati1 |
Completion of work |
-
latitude : 19.5478623,19.5478587
Longitude : 82.9334748,82.9334766
file name : Image_23122022183313654.png
|
2022-12-23 18:33:13.74404 |
68 |
64870433 |
Repari & Maintanance of Drain AWC to Amba Gachha at Mundighati |
100000 |
Repari & Maintanance of Drain AWC to Amba Gachha at Mundighati1 |
Completion of work |
-
latitude : 19.5478623,19.5478631
Longitude : 82.9334742,82.9334729
file name : Image_23122022182000151.png
|
2022-12-23 18:20:00.232027 |
69 |
64870485 |
Repair & Maintanance of AWC Boundary Wall at Dureshpadar |
253900 |
Repair & Maintanance of AWC Boundary Wall at Dureshpadar1 |
Completion of work |
-
latitude : 19.5478609
Longitude : 82.9334755
file name : Image_23122022184457956.png
|
2022-12-23 18:44:58.043919 |
70 |
61696857 |
Construction of Segregation Shed for Plastic Waste management at Khamarpadar @ Rs. 19500.00 per Vill |
19500 |
Construction of Segregation Shed for Plastic Waste management at Khamarpadar @ Rs. 19500.00 per Vill1 |
Completion of work |
-
latitude : 19.920621666666666
Longitude : 83.01793
file name : Image_03032023113932758.png
|
2023-03-03 11:39:32.865487 |
71 |
64870414 |
Repair & Maintanance of Drain at Adibashipada to Tentuli Gachha Khamarpadar |
100000 |
Repair & Maintanance of Drain at Adibashipada to Tentuli Gachha Khamarpadar1 |
Completion of work |
-
latitude : 19.920633333333335,19.920628333333333
Longitude : 83.01794166666666,83.01793500000001
file name : Image_03032023115905127.png
|
2023-03-03 11:59:05.218282 |
72 |
64870414 |
Repair & Maintanance of Drain at Adibashipada to Tentuli Gachha Khamarpadar |
100000 |
Repair & Maintanance of Drain at Adibashipada to Tentuli Gachha Khamarpadar1 |
Completion of work |
-
latitude : 19.9206,19.920603333333336
Longitude : 83.01789500000001,83.01791
file name : Image_03032023115909658.png
|
2023-03-03 11:59:09.755715 |
73 |
64870414 |
Repair & Maintanance of Drain at Adibashipada to Tentuli Gachha Khamarpadar |
100000 |
Repair & Maintanance of Drain at Adibashipada to Tentuli Gachha Khamarpadar1 |
Completion of work |
-
latitude : 19.92062,19.920621666666666
Longitude : 83.01790833333334,83.01791666666668
file name : Image_03032023115938434.png
|
2023-03-03 11:59:38.646831 |
74 |
64870498 |
Repair & Maintanance of Khamarpadar UPS |
100000 |
Repair & Maintanance of Khamarpadar UPS1 |
Completion of work |
-
latitude : 19.44369859
Longitude : 82.85912007
file name : Image_18052023185014308.png
|
2023-05-18 18:50:14.392555 |
75 |
64870614 |
Creation of a new source of drinking water |
50000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 19.44364479
Longitude : 82.8589158
file name : Image_18052023185358811.png
|
2023-05-18 18:53:58.899939 |
76 |
64870367 |
Ghatcutting with Convergency from Chikonkhadak to Khamarpadar |
100000 |
Ghatcutting with Convergency from Chikonkhadak to Khamarpadar1 |
Completion of work |
-
latitude : 19.44365935,19.4436528,19.4436528
Longitude : 82.85889919,82.8585095,82.8585095
file name : Image_18052023185621497.png
|
2023-05-18 18:56:21.586465 |
77 |
64870531 |
Ghatcutting with convergency from Amba Gachha to Talpada Hatsil |
100000 |
Ghatcutting with convergency from Amba Gachha to Talpada Hatsil1 |
Completion of work |
-
latitude : 19.52596308,19.52596308
Longitude : 82.91467019,82.91467019
file name : Image_30042023132258034.png
|
2023-04-30 13:22:58.126198 |
78 |
64870401 |
Ghatcutting with Convergency from Bhutguda To Sinder |
100000 |
Ghatcutting with Convergency from Bhutguda To Sinder1 |
Completion of work |
-
latitude : 19.52596567,19.52596567
Longitude : 82.91462155,82.91462155
file name : Image_30042023133032076.png
|
2023-04-30 13:30:32.176118 |
79 |
64870393 |
Ghatcutting with Convergency from RD Road to Fukijal Goud Sai |
100000 |
Ghatcutting with Convergency from RD Road to Fukijal Goud Sai1 |
Completion of work |
-
latitude : 19.52596518,19.52596518
Longitude : 82.91464846,82.91464846
file name : Image_30042023132557667.png
|
2023-04-30 13:25:57.762554 |
80 |
64870682 |
Creation of a new source of drinking water |
26000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 19.37836756
Longitude : 82.81336403
file name : Image_21072023194018878.png
|
2023-07-21 19:40:19.025967 |
81 |
105908649 |
Drinking water facilities/ Installation of RO/ Water Filter |
78000 |
Drinking water facilities/ Installation of RO/ Water Filter1 |
Roof laid |
-
latitude : 19.5479528
Longitude : 82.9335599
file name : Image_02092024131139804.png
|
2024-09-02 13:11:39.919497 |
82 |
105908649 |
Drinking water facilities/ Installation of RO/ Water Filter |
78000 |
Drinking water facilities/ Installation of RO/ Water Filter1 |
Plinth level |
-
latitude : 19.5479524
Longitude : 82.9335602
file name : Image_02092024130840958.png
|
2024-09-02 13:08:41.082538 |
83 |
105908649 |
Drinking water facilities/ Installation of RO/ Water Filter |
78000 |
Drinking water facilities/ Installation of RO/ Water Filter1 |
Completion of work |
-
latitude : 19.54796581
Longitude : 82.93353915
file name : Image_02092024130619244.png
|
2024-09-02 13:06:19.368774 |
84 |
64870667 |
Creation of a new source of drinking water |
5000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 19.44371793
Longitude : 82.85920807
file name : Image_16092023211753780.png
|
2023-09-16 21:17:53.934405 |
85 |
83055566 |
Water Supply to villages |
48000 |
Water Supply to villages1 |
Roof laid |
-
latitude : 19.44370161
Longitude : 82.85904806
file name : Image_09112023190153785.png
|
2023-11-09 19:01:53.903098 |
86 |
83055566 |
Water Supply to villages |
48000 |
Water Supply to villages1 |
Plinth level |
-
latitude : 19.44379464
Longitude : 82.85915112
file name : Image_09112023185330841.png
|
2023-11-09 18:53:30.955981 |
87 |
83055566 |
Water Supply to villages |
48000 |
Water Supply to villages1 |
Completion of work |
-
latitude : 19.4425173
Longitude : 82.8578364
file name : Image_09112023184811116.png
|
2023-11-09 18:48:11.237728 |
88 |
83182034 |
Construction of roads |
150000 |
Construction of roads1 |
Roof laid |
-
latitude : 19.547952,19.547952
Longitude : 82.9335621,82.9335621
file name : Image_19122023163112318.png
|
2023-12-19 16:31:12.406008 |
89 |
83182034 |
Construction of roads |
150000 |
Construction of roads1 |
Roof laid |
-
latitude : 19.5478569,19.5478569
Longitude : 82.9335605,82.9335605
file name : Image_24112023134954296.png
|
2023-11-24 13:49:54.393664 |
90 |
83182034 |
Construction of roads |
150000 |
Construction of roads1 |
Plinth level |
-
latitude : 19.5478566,19.5478566
Longitude : 82.9335583,82.9335583
file name : Image_24112023134657268.png
|
2023-11-24 13:46:57.378584 |
91 |
83182034 |
Construction of roads |
150000 |
Construction of roads1 |
Completion of work |
-
latitude : 19.5478566,19.5478566
Longitude : 82.9335583,82.9335583
file name : Image_24112023133436531.png
|
2023-11-24 13:34:36.706349 |
92 |
83182034 |
Construction of roads |
150000 |
Construction of roads1 |
Completion of work |
-
latitude : 19.55249995,19.55249995
Longitude : 82.91634384,82.91634384
file name : Image_24112023133428195.png
|
2023-11-24 13:34:28.301057 |
93 |
64870712 |
Operation & maintenance of community sanitary complex |
456744 |
Operation & maintenance of community sanitary complex1 |
Completion of work |
-
latitude : 19.547857
Longitude : 82.9335567
file name : Image_24112023133953414.png
|
2023-11-24 13:39:53.50202 |
94 |
64870712 |
Operation & maintenance of community sanitary complex |
456744 |
Operation & maintenance of community sanitary complex1 |
Completion of work |
-
latitude : 19.5478566
Longitude : 82.9335591
file name : Image_24112023133946908.png
|
2023-11-24 13:39:46.992109 |
95 |
64870712 |
Operation & maintenance of community sanitary complex |
456744 |
Operation & maintenance of community sanitary complex1 |
Completion of work |
-
latitude : 19.547859
Longitude : 82.9335612
file name : Image_24112023133752539.png
|
2023-11-24 13:37:52.635399 |
96 |
83288734 |
Services of Collection & transportation of waste from household to treatment site |
77660 |
Services of Collection & transportation of waste from household to treatment site1 |
|
-
latitude : 19.44376194
Longitude : 82.85911841
file name : Image_17022024084604275.png
|
2024-02-17 08:46:04.367922 |
97 |
83288734 |
Services of Collection & transportation of waste from household to treatment site |
77660 |
Services of Collection & transportation of waste from household to treatment site1 |
|
-
latitude : 19.44368384
Longitude : 82.85918859
file name : Image_16022024212129744.png
|
2024-02-16 21:21:29.832415 |
98 |
83287711 |
Drainage Construction |
100000 |
Drainage Construction1 |
Roof laid |
-
latitude : 19.444049
Longitude : 82.8591826
file name : Image_17022024085439337.png
|
2024-02-17 08:54:39.425756 |
99 |
83287711 |
Drainage Construction |
100000 |
Drainage Construction1 |
Plinth level |
-
latitude : 19.44376047
Longitude : 82.85908334
file name : Image_17022024085120684.png
|
2024-02-17 08:51:20.773483 |
100 |
83287711 |
Drainage Construction |
100000 |
Drainage Construction1 |
Completion of work |
-
latitude : 19.44374085
Longitude : 82.85908098
file name : Image_17022024084403879.png
|
2024-02-17 08:44:03.984807 |
101 |
83287711 |
Drainage Construction |
100000 |
Drainage Construction1 |
Completion of work |
-
latitude : 19.44369227
Longitude : 82.85879614
file name : Image_17022024072947344.png
|
2024-02-17 07:29:47.422067 |
102 |
83287307 |
Drainage Construction |
100000 |
Drainage Construction1 |
Roof laid |
-
latitude : 19.44368129
Longitude : 82.85919049
file name : Image_16022024211955507.png
|
2024-02-16 21:19:55.592639 |
103 |
83287307 |
Drainage Construction |
100000 |
Drainage Construction1 |
Roof laid |
-
latitude : 19.547952
Longitude : 82.9335625
file name : Image_19122023164955221.png
|
2023-12-19 16:49:55.306979 |
104 |
83287307 |
Drainage Construction |
100000 |
Drainage Construction1 |
Plinth level |
-
latitude : 19.5479519
Longitude : 82.9335648
file name : Image_19122023163936770.png
|
2023-12-19 16:39:36.856925 |
105 |
83287307 |
Drainage Construction |
100000 |
Drainage Construction1 |
Completion of work |
-
latitude : 19.5479524
Longitude : 82.9335624
file name : Image_19122023162949997.png
|
2023-12-19 16:29:50.089161 |
106 |
83283275 |
Creation of compost pits for individual Households |
80000 |
Creation of compost pits for individual Households1 |
Roof laid |
-
latitude : 19.48210935
Longitude : 82.79550575
file name : Image_02062024111054848.png
|
2024-06-02 11:10:54.951015 |
107 |
83283275 |
Creation of compost pits for individual Households |
80000 |
Creation of compost pits for individual Households1 |
Plinth level |
-
latitude : 19.48208076
Longitude : 82.79556739
file name : Image_02062024110603927.png
|
2024-06-02 11:06:04.03722 |
108 |
83283275 |
Creation of compost pits for individual Households |
80000 |
Creation of compost pits for individual Households1 |
Completion of work |
-
latitude : 19.91323041
Longitude : 83.11099881
file name : Image_01062024203413766.png
|
2024-06-01 20:34:13.871688 |
109 |
83268744 |
Creation of a new source of drinking water |
110000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 19.50479335
Longitude : 82.72908381
file name : Image_31032024100027321.png
|
2024-03-31 10:00:27.445838 |
110 |
83268744 |
Creation of a new source of drinking water |
110000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 19.50487407
Longitude : 82.73504238
file name : Image_31032024095628578.png
|
2024-03-31 09:56:28.693242 |
111 |
83268744 |
Creation of a new source of drinking water |
110000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 19.47982813
Longitude : 82.8067247
file name : Image_31032024095344186.png
|
2024-03-31 09:53:44.290536 |
112 |
83061606 |
Construction of roads |
118080 |
Construction of roads1 |
Roof laid |
-
latitude : 19.44366517,19.44366517
Longitude : 82.85916668,82.85916668
file name : Image_23072024194444038.png
|
2024-07-23 19:44:44.118051 |
113 |
83061606 |
Construction of roads |
118080 |
Construction of roads1 |
Roof laid |
-
latitude : 19.4433096,19.4433096
Longitude : 82.8591826,82.8591826
file name : Image_23072024194324638.png
|
2024-07-23 19:43:24.726393 |
114 |
83061606 |
Construction of roads |
118080 |
Construction of roads1 |
Plinth level |
-
latitude : 19.44367857,19.44367835
Longitude : 82.85916566,82.85916556
file name : Image_23072024193418066.png
|
2024-07-23 19:34:18.154493 |
115 |
83061606 |
Construction of roads |
118080 |
Construction of roads1 |
Completion of work |
-
latitude : 19.4420417,19.4420417
Longitude : 82.8551439,82.8551439
file name : Image_23072024192955449.png
|
2024-07-23 19:29:55.537498 |
116 |
83061219 |
Construction of Sheds |
150000 |
Construction of Sheds1 |
Roof laid |
-
latitude : 19.44370166
Longitude : 82.85915263
file name : Image_23072024193849180.png
|
2024-07-23 19:38:49.259899 |
117 |
83061219 |
Construction of Sheds |
150000 |
Construction of Sheds1 |
Plinth level |
-
latitude : 19.44370605
Longitude : 82.85913686
file name : Image_23072024193512074.png
|
2024-07-23 19:35:12.173692 |
118 |
83061219 |
Construction of Sheds |
150000 |
Construction of Sheds1 |
Completion of work |
-
latitude : 19.44361823
Longitude : 82.85924726
file name : Image_23072024193033045.png
|
2024-07-23 19:30:33.125018 |
119 |
83165734 |
Creation of a new source of drinking water |
315000 |
Creation of a new source of drinking water1 |
Roof laid |
-
latitude : 19.44374116
Longitude : 82.85906724
file name : Image_09082024094628212.png
|
2024-08-09 09:46:28.304629 |
120 |
83165734 |
Creation of a new source of drinking water |
315000 |
Creation of a new source of drinking water1 |
Plinth level |
-
latitude : 19.44374243
Longitude : 82.85907341
file name : Image_09082024094319076.png
|
2024-08-09 09:43:19.169792 |
121 |
83165734 |
Creation of a new source of drinking water |
315000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 19.44361218
Longitude : 82.85935723
file name : Image_08082024071050170.png
|
2024-08-08 07:10:50.25417 |
122 |
105908767 |
Pipeline connection for water supply |
60000 |
Pipeline connection for water supply1 |
Roof laid |
-
latitude : 19.44375106
Longitude : 82.85901774
file name : Image_09082024100531732.png
|
2024-08-09 10:05:31.809938 |
123 |
105908767 |
Pipeline connection for water supply |
60000 |
Pipeline connection for water supply1 |
Plinth level |
-
latitude : 19.44374487
Longitude : 82.85900669
file name : Image_09082024095142730.png
|
2024-08-09 09:51:42.883572 |
124 |
105908767 |
Pipeline connection for water supply |
60000 |
Pipeline connection for water supply1 |
Completion of work |
-
latitude : 19.44362882
Longitude : 82.85892604
file name : Image_09082024093626269.png
|
2024-08-09 09:36:26.441495 |
125 |
105908767 |
Pipeline connection for water supply |
60000 |
Pipeline connection for water supply1 |
Completion of work |
-
latitude : 19.44363816
Longitude : 82.85924188
file name : Image_08082024071248455.png
|
2024-08-08 07:12:48.612719 |