1 |
43936972 |
WASHING OF TWS |
60000 |
WASHING OF TWS1 |
Completion of work |
-
latitude : 18.84119662
Longitude : 82.5347218
file name : Image_18092020110040561.png
|
2020-09-18 11:00:40.767741 |
2 |
43936972 |
WASHING OF TWS |
60000 |
WASHING OF TWS2 |
Completion of work |
-
latitude : 18.84197079
Longitude : 82.53379998
file name : Image_18092020105345735.png
|
2020-09-18 10:53:45.959003 |
3 |
43936892 |
SINKING OF NEW TWS |
120000 |
SINKING OF NEW TWS1 |
Completion of work |
-
latitude : 18.81875703
Longitude : 82.50707881
file name : Image_18092020110855646.png
|
2020-09-18 11:08:55.738018 |
4 |
52177353 |
SMART CLASSROOM AT BAMUNIPUT |
250000 |
SMART CLASSROOM AT BAMUNIPUT 1 |
Completion of work |
-
latitude : 18.82756043
Longitude : 82.51318594
file name : Image_11102021114604623.png
|
2021-10-11 11:46:04.75188 |
5 |
43807386 |
MANPOWER AND TC FOR CLEANING OF CC DRAINS 6 NOS |
180000 |
MANPOWER AND TC FOR CLEANING OF CC DRAINS 6 NOS1 |
Completion of work |
-
latitude : 18.83622364
Longitude : 82.52680783
file name : Image_06042021170713940.png
|
2021-04-06 17:07:14.038401 |
6 |
43807386 |
MANPOWER AND TC FOR CLEANING OF CC DRAINS 6 NOS |
180000 |
MANPOWER AND TC FOR CLEANING OF CC DRAINS 6 NOS1 |
Completion of work |
-
latitude : 18.83297034
Longitude : 82.52572155
file name : Image_06042021170722326.png
|
2021-04-06 17:07:22.415685 |
7 |
43807386 |
MANPOWER AND TC FOR CLEANING OF CC DRAINS 6 NOS |
180000 |
MANPOWER AND TC FOR CLEANING OF CC DRAINS 6 NOS1 |
Completion of work |
-
latitude : 18.83333218
Longitude : 82.52579432
file name : Image_06042021170731082.png
|
2021-04-06 17:07:31.173429 |
8 |
43807386 |
MANPOWER AND TC FOR CLEANING OF CC DRAINS 6 NOS |
180000 |
MANPOWER AND TC FOR CLEANING OF CC DRAINS 6 NOS1 |
Completion of work |
-
latitude : 18.83333218
Longitude : 82.52579432
file name : Image_06042021170753308.png
|
2021-04-06 17:07:53.41241 |
9 |
48366790 |
CONST. OF TUBE WELL PLATFORM AND WATER CONNECTION TO POLKAPUT PRIMARY SCHOOL |
80000 |
CONST. OF TUBE WELL PLATFORM AND WATER CONNECTION TO POLKAPUT PRIMARY SCHOOL1 |
Completion of work |
-
latitude : 18.83623765
Longitude : 82.52661153
file name : Image_21052021125502426.png
|
2021-05-21 12:55:02.551917 |
10 |
48366790 |
CONST. OF TUBE WELL PLATFORM AND WATER CONNECTION TO POLKAPUT PRIMARY SCHOOL |
80000 |
CONST. OF TUBE WELL PLATFORM AND WATER CONNECTION TO POLKAPUT PRIMARY SCHOOL1 |
Completion of work |
-
latitude : 18.83623765
Longitude : 82.52661153
file name : Image_21052021125535224.png
|
2021-05-21 12:55:35.335291 |
11 |
48336238 |
WATER CONNECTION TO PANJIAGUDA PRY. SCHOOL |
60000 |
WATER CONNECTION TO PANJIAGUDA PRY. SCHOOL1 |
Completion of work |
-
latitude : 18.7527085,18.7527085
Longitude : 82.4291182,82.4291182
file name : Image_21052021125513758.png
|
2021-05-21 12:55:13.871047 |
12 |
48336641 |
WATER CONNECTION TO PANJIAGUDA AWC |
60000 |
WATER CONNECTION TO PANJIAGUDA AWC1 |
Completion of work |
-
latitude : 18.8484308,18.8484308
Longitude : 82.5469621,82.5469621
file name : Image_21052021125518471.png
|
2021-05-21 12:55:18.63003 |
13 |
48367423 |
WATER CONNECTION TO BAMUNIPUT PRY. SCHOOL AND BAMUNIPUT AWC |
90000 |
WATER CONNECTION TO BAMUNIPUT PRY. SCHOOL AND BAMUNIPUT AWC1 |
Completion of work |
-
latitude : 18.82753215,18.82757677
Longitude : 82.51320461,82.51323198
file name : Image_21052021125443879.png
|
2021-05-21 12:54:44.004236 |
14 |
48368007 |
WATER CONNECTION TO NUAPUT PRY. SCHOOL, NUAPUT AWC - 1 AND REPAIR & WASHING OF TUBE WELL |
90000 |
WATER CONNECTION TO NUAPUT PRY. SCHOOL, NUAPUT AWC - 1 AND REPAIR & WASHING OF TUBE WELL1 |
Completion of work |
-
latitude : 18.8417604
Longitude : 82.50064229
file name : Image_21052021125454054.png
|
2021-05-21 12:54:54.179912 |
15 |
48368007 |
WATER CONNECTION TO NUAPUT PRY. SCHOOL, NUAPUT AWC - 1 AND REPAIR & WASHING OF TUBE WELL |
90000 |
WATER CONNECTION TO NUAPUT PRY. SCHOOL, NUAPUT AWC - 1 AND REPAIR & WASHING OF TUBE WELL1 |
Completion of work |
-
latitude : 18.8417604
Longitude : 82.50064229
file name : Image_21052021125528614.png
|
2021-05-21 12:55:28.7254 |
16 |
48368082 |
WATER CONNECTION TO AWC BODOUJEI AND POKHANAGUDA |
90000 |
WATER CONNECTION TO AWC BODOUJEI AND POKHANAGUDA 1 |
Completion of work |
-
latitude : 18.83417626,18.83419761
Longitude : 82.53239323,82.53229967
file name : Image_29052021115016572.png
|
2021-05-29 11:50:16.658909 |
17 |
48366855 |
WATER CONNECTION TO BISOIPUT AWC |
60000 |
WATER CONNECTION TO BISOIPUT AWC1 |
Completion of work |
-
latitude : 18.8190398,18.81899806
Longitude : 82.51844017,82.51844073
file name : Image_30042021160832976.png
|
2021-04-30 16:08:33.084173 |
18 |
43938656 |
CONST OF STAND POST REPAIR OF VALUE CHAMBER & EXTENSION PIPE LINE |
300000 |
CONST OF STAND POST REPAIR OF VALUE CHAMBER & EXTENSION PIPE LINE1 |
Completion of work |
-
latitude : 18.81876079,18.81890228,18.8316058,18.83138135
Longitude : 82.50702982,82.50691916,82.54164875,82.54321954
file name : Image_30042021160843494.png
|
2021-04-30 16:08:43.568231 |
19 |
43938656 |
CONST OF STAND POST REPAIR OF VALUE CHAMBER & EXTENSION PIPE LINE |
300000 |
CONST OF STAND POST REPAIR OF VALUE CHAMBER & EXTENSION PIPE LINE1 |
Completion of work |
-
latitude : 18.83142922,18.83148152,18.83170692,18.83178393
Longitude : 82.5432214,82.54323475,82.54164473,82.54174212
file name : Image_30042021160909699.png
|
2021-04-30 16:09:09.781 |
20 |
43937349 |
REPAIR & MAINTENANCE DRINKING WELLS CHANDINI |
30000 |
REPAIR & MAINTENANCE DRINKING WELLS CHANDINI1 |
Completion of work |
-
latitude : 18.8432664
Longitude : 82.50197192
file name : Image_25052021130627279.png
|
2021-05-25 13:06:27.334157 |
21 |
48368035 |
WATER CONNECTION TO NUAPUT PRY. SCHOOL, NUAPUT AWC - 1 AND REPAIR & WASHING OF TUBE WELL |
90000 |
WATER CONNECTION TO NUAPUT PRY. SCHOOL, NUAPUT AWC - 1 AND REPAIR & WASHING OF TUBE WELL1 |
Completion of work |
-
latitude : 18.8433145
Longitude : 82.50185379
file name : Image_25052021130633185.png
|
2021-05-25 13:06:33.241481 |
22 |
43937276 |
CONST/REPAIR OF TW PLATFORMS |
70000 |
CONST/REPAIR OF TW PLATFORMS1 |
Completion of work |
-
latitude : 18.83668939
Longitude : 82.5266527
file name : Image_25052021125542552.png
|
2021-05-25 12:55:42.648344 |
23 |
52177122 |
BLEACHING POWDER PURCHAGEING BALIA |
4999 |
BLEACHING POWDER PURCHAGEING BALIA1 |
Completion of work |
-
latitude : 18.8687331
Longitude : 82.5733805
file name : Image_27072021140415416.png
|
2021-07-27 14:04:15.472989 |
24 |
48371231 |
CONST. OF SOAK PITS AT BALIA G.P. |
125000 |
CONST. OF SOAK PITS AT BALIA G.P.1 |
Completion of work |
-
latitude : 18.83688867
Longitude : 82.52687952
file name : Image_03082021171111253.png
|
2021-08-03 17:11:11.332542 |
25 |
48371231 |
CONST. OF SOAK PITS AT BALIA G.P. |
125000 |
CONST. OF SOAK PITS AT BALIA G.P.1 |
Completion of work |
-
latitude : 18.83631539
Longitude : 82.52647436
file name : Image_03082021171115903.png
|
2021-08-03 17:11:15.963513 |
26 |
48371231 |
CONST. OF SOAK PITS AT BALIA G.P. |
125000 |
CONST. OF SOAK PITS AT BALIA G.P.1 |
Completion of work |
-
latitude : 18.83688704
Longitude : 82.52687603
file name : Image_03082021171120200.png
|
2021-08-03 17:11:20.297804 |
27 |
48371231 |
CONST. OF SOAK PITS AT BALIA G.P. |
125000 |
CONST. OF SOAK PITS AT BALIA G.P.1 |
Completion of work |
-
latitude : 18.83422296
Longitude : 82.52535088
file name : Image_30072021151449610.png
|
2021-07-30 15:14:49.663652 |
28 |
52175751 |
COMP OF UNCOMP AWC AT KUNTARKHAL |
100000 |
COMP OF UNCOMP AWC AT KUNTARKHAL1 |
Completion of work |
-
latitude : 18.8509487
Longitude : 82.5762694
file name : Image_30072021151453394.png
|
2021-07-30 15:14:53.447277 |
29 |
52176461 |
WIRING AND WATER SUPPLY TO 10 NOS OF AWC |
200000 |
WIRING AND WATER SUPPLY TO 10 NOS OF AWC1 |
Completion of work |
-
latitude : 18.8417063
Longitude : 82.50091275
file name : Image_30072021140416152.png
|
2021-07-30 14:04:16.217527 |
30 |
52177670 |
CONST OF MANDAP AT BALIA |
200000 |
CONST OF MANDAP AT BALIA1 |
Completion of work |
-
latitude : 18.81911227
Longitude : 82.50534959
file name : Image_22092021121136961.png
|
2021-09-22 12:11:37.053598 |
31 |
80585318 |
Functional Equipment |
94000 |
Functional Equipment1 |
Completion of work |
-
latitude : 18.84677333333333,18.846815
Longitude : 82.54285499999999,82.54290166666667
file name : Image_03042024153637986.png
|
2024-04-03 15:36:38.043507 |
32 |
75679685 |
Functional Equipment |
94000 |
Functional Equipment1 |
Completion of work |
-
latitude : 18.8502891
Longitude : 82.5484423
file name : Image_03042024153230183.png
|
2024-04-03 15:32:30.28331 |
33 |
52176033 |
COMP O UNCOMP TANK AT NUAPUT |
200000 |
COMP O UNCOMP TANK AT NUAPUT1 |
Completion of work |
-
latitude : 18.8410142
Longitude : 82.50532859
file name : Image_04102021120809575.png
|
2021-10-04 12:08:09.637771 |
34 |
52176965 |
MASS CLEANING AT BALIA |
60000 |
MASS CLEANING AT BALIA1 |
Completion of work |
-
latitude : 18.83465728
Longitude : 82.52519022
file name : Image_29122021154257499.png
|
2021-12-29 15:42:57.6249 |
35 |
52176965 |
MASS CLEANING AT BALIA |
60000 |
MASS CLEANING AT BALIA1 |
Completion of work |
-
latitude : 18.83473786
Longitude : 82.5251924
file name : Image_29122021154303024.png
|
2021-12-29 15:43:03.132795 |
36 |
52176965 |
MASS CLEANING AT BALIA |
60000 |
MASS CLEANING AT BALIA1 |
Completion of work |
-
latitude : 18.83470062
Longitude : 82.52525453
file name : Image_29122021154308943.png
|
2021-12-29 15:43:09.092575 |
37 |
52177748 |
JALACHATRA MAINTANCE BALIA |
70000 |
JALACHATRA MAINTANCE BALIA1 |
Completion of work |
-
latitude : 18.82834613
Longitude : 82.51714266
file name : Image_29122021135141315.png
|
2021-12-29 13:51:41.463268 |
38 |
52176533 |
ENERGEY CHARGES TO PWS SYSTEM |
256732 |
ENERGEY CHARGES TO PWS SYSTEM1 |
Completion of work |
-
latitude : 18.8692604
Longitude : 82.5735034
file name : Image_29122021122111284.png
|
2021-12-29 12:21:11.394711 |
39 |
52177027 |
MAN POWER AND TC FOR CLEANING OF CC DRAIN |
120000 |
MAN POWER AND TC FOR CLEANING OF CC DRAIN1 |
Completion of work |
-
latitude : 18.82821664,18.82812981
Longitude : 82.51657662,82.51661453
file name : Image_29122021154251548.png
|
2021-12-29 15:42:51.663314 |
40 |
52177027 |
MAN POWER AND TC FOR CLEANING OF CC DRAIN |
120000 |
MAN POWER AND TC FOR CLEANING OF CC DRAIN1 |
Completion of work |
-
latitude : 18.8349686,18.83444147
Longitude : 82.52547726,82.52583629
file name : Image_04102021120036571.png
|
2021-10-04 12:00:36.641089 |
41 |
52177027 |
MAN POWER AND TC FOR CLEANING OF CC DRAIN |
120000 |
MAN POWER AND TC FOR CLEANING OF CC DRAIN1 |
Completion of work |
-
latitude : 18.83495335,18.83484848
Longitude : 82.52541715,82.52545238
file name : Image_30072021151445478.png
|
2021-07-30 15:14:45.526651 |
42 |
52176397 |
REPAIR AND MAINTANCE OF PWS AT BALIA AND KUNTARKHAL |
100000 |
REPAIR AND MAINTANCE OF PWS AT BALIA AND KUNTARKHAL1 |
Completion of work |
-
latitude : 18.8419483,18.84194333
Longitude : 82.53382138,82.53383243
file name : Image_07102021161337019.png
|
2021-10-07 16:13:37.11031 |
43 |
43806993 |
REPAIR AND MAINTENANCE OF SUB CENTER AT BALIA |
71756 |
REPAIR AND MAINTENANCE OF SUB CENTER AT BALIA1 |
Completion of work |
-
latitude : 18.8410437
Longitude : 82.50531933
file name : Image_31012022130931317.png
|
2022-01-31 13:09:31.426315 |
44 |
52176592 |
SALLARY PAID TO SEM |
120000 |
SALLARY PAID TO SEM 1 |
Completion of work |
-
latitude : 18.8690475
Longitude : 82.5735321
file name : Image_20042022130936345.png
|
2022-04-20 13:09:36.413155 |
45 |
61696945 |
SEGREGATION SHED 1 NOS |
90000 |
SEGREGATION SHED 1 NOS1 |
Completion of work |
-
latitude : 18.831266666666668
Longitude : 82.54204
file name : Image_07062022133149106.png
|
2022-06-07 13:31:49.174927 |
46 |
61696975 |
COMMUNITY COMPOST PIT @ RS 25000 |
50000 |
COMMUNITY COMPOST PIT @ RS 250001 |
Completion of work |
-
latitude : 18.831168333333334
Longitude : 82.54278000000001
file name : Image_07062022133404901.png
|
2022-06-07 13:34:04.972012 |
47 |
61696581 |
REMUNERATION TO SEM AND PD |
120000 |
REMUNERATION TO SEM AND PD1 |
Completion of work |
-
latitude : 18.8694574
Longitude : 82.5735709
file name : Image_18072022164640017.png
|
2022-07-18 16:46:40.129747 |
48 |
83628137 |
COMPLETION OF INCOMPLETE TANK AT NUAPUT PHASE-2 RS 66762 |
66762 |
COMPLETION OF INCOMPLETE TANK AT NUAPUT PHASE-2 RS 667621 |
Completion of work |
-
latitude : 18.840948333333333
Longitude : 82.50527833333332
file name : Image_21072023121409462.png
|
2023-07-21 12:14:09.535876 |
49 |
83628104 |
COMPLETION OF INCOMPLETE TANK AT NUAPUT PHASE-1 RS 200000 |
200000 |
COMPLETION OF INCOMPLETE TANK AT NUAPUT PHASE-1 RS 2000001 |
Completion of work |
-
latitude : 18.840901666666664
Longitude : 82.50529166666665
file name : Image_21072023121240560.png
|
2023-07-21 12:12:40.635516 |
50 |
61697051 |
ANNUALLY MASS CLEANING DRIVE @ 20 |
55000 |
ANNUALLY MASS CLEANING DRIVE @ 201 |
Completion of work |
-
latitude : 18.819538333333334
Longitude : 82.50566166666667
file name : Image_09092022165447951.png
|
2022-09-09 16:54:48.039826 |
51 |
61697051 |
ANNUALLY MASS CLEANING DRIVE @ 20 |
55000 |
ANNUALLY MASS CLEANING DRIVE @ 201 |
Completion of work |
-
latitude : 18.81946333333333
Longitude : 82.50562
file name : Image_09092022165451473.png
|
2022-09-09 16:54:51.562624 |
52 |
61697051 |
ANNUALLY MASS CLEANING DRIVE @ 20 |
55000 |
ANNUALLY MASS CLEANING DRIVE @ 201 |
Completion of work |
-
latitude : 18.819200000000002
Longitude : 82.50653499999999
file name : Image_09092022165454938.png
|
2022-09-09 16:54:55.032394 |
53 |
61697069 |
DRAIN CLEANING |
150000 |
DRAIN CLEANING 1 |
Completion of work |
-
latitude : 18.812475,18.81247
Longitude : 82.50375000000001,82.50374666666667
file name : Image_09092022164136989.png
|
2022-09-09 16:41:37.066229 |
54 |
61697086 |
UNFORSEEN ITEMS |
60347 |
UNFORSEEN ITEMS 1 |
Completion of work |
-
latitude : 18.8690312
Longitude : 82.5735404
file name : Image_17092022185246313.png
|
2022-09-17 18:52:46.412776 |
55 |
61696646 |
MAINTENANCE OF PWS |
100347 |
MAINTENANCE OF PWS 1 |
Completion of work |
-
latitude : 18.842523333333336
Longitude : 82.53984833333334
file name : Image_16092022162744931.png
|
2022-09-16 16:27:45.021757 |
56 |
65726739 |
PAVER BLOCK ROAD FROM PAKNAGUDA AND BADAUJEI AWC |
200000 |
PAVER BLOCK ROAD FROM PAKNAGUDA AND BADAUJEI AWC1 |
Completion of work |
-
latitude : 18.834228333333332,18.834235
Longitude : 82.53242833333334,82.53240166666667
file name : Image_16112022155748308.png
|
2022-11-16 15:57:48.386752 |
57 |
61697336 |
PAVER BLOCK ROAD AT NUAPUT |
200000 |
PAVER BLOCK ROAD AT NUAPUT1 |
Completion of work |
-
latitude : 18.840953333333335,18.84093
Longitude : 82.501325,82.50130499999999
file name : Image_17122022125005873.png
|
2022-12-17 12:50:05.954906 |
58 |
43984259 |
REPAIR AND MAINTENANCE OF BAMUNIPUT UP SCHOOL |
132000 |
REPAIR AND MAINTENANCE OF BAMUNIPUT UP SCHOOL1 |
Completion of work |
-
latitude : 18.84095803
Longitude : 82.50525701
file name : Image_31012022130953155.png
|
2022-01-31 13:09:53.259464 |
59 |
38525171 |
CONTINGENCY |
124851 |
CONTINGENCY1 |
Completion of work |
-
latitude : 18.8281868
Longitude : 82.5170405
file name : Image_13042021123742083.png
|
2021-04-13 12:37:42.212664 |
60 |
61697691 |
MAINTENANCE OF STREET LIGHT |
32440 |
MAINTENANCE OF STREET LIGHT1 |
Completion of work |
-
latitude : 18.813193333333334
Longitude : 82.50180166666665
file name : Image_09092022163437959.png
|
2022-09-09 16:34:38.024794 |
61 |
61697691 |
MAINTENANCE OF STREET LIGHT |
32440 |
MAINTENANCE OF STREET LIGHT1 |
Completion of work |
-
latitude : 18.813193333333334
Longitude : 82.50179833333335
file name : Image_09092022163422806.png
|
2022-09-09 16:34:22.879986 |
62 |
61697691 |
MAINTENANCE OF STREET LIGHT |
32440 |
MAINTENANCE OF STREET LIGHT1 |
Completion of work |
-
latitude : 18.813193333333334
Longitude : 82.50180166666665
file name : Image_09092022163450084.png
|
2022-09-09 16:34:50.148684 |
63 |
43936361 |
HONOURARIUM OF SEM/PUMP DRIVERS |
100000 |
HONOURARIUM OF SEM/PUMP DRIVERS1 |
Completion of work |
-
latitude : 18.8691822
Longitude : 82.5735404
file name : Image_06082021115658806.png
|
2021-08-06 11:56:58.881958 |
64 |
48367195 |
CONST. OF ROAD FROM SATI NADI TO GORAHANDIA TOTA |
50000 |
CONST. OF ROAD FROM SATI NADI TO GORAHANDIA TOTA1 |
Completion of work |
-
latitude : 18.84067172,18.84158832
Longitude : 82.50257159,82.50305476
file name : Image_30072021151441745.png
|
2021-07-30 15:14:41.800693 |
65 |
48367262 |
CONST.OF ROAD FROM R.D. ROAD TO RATI GHARA |
50000 |
CONST.OF ROAD FROM R.D. ROAD TO RATI GHARA1 |
Completion of work |
-
latitude : 18.84166359,18.84164164
Longitude : 82.5009273,82.50091743
file name : Image_30072021151438218.png
|
2021-07-30 15:14:38.272807 |
66 |
48367048 |
REPAIR AND MAINTENANCE OF MISSION SHAKTI AT KUNTHARKHAL |
46500 |
REPAIR AND MAINTENANCE OF MISSION SHAKTI AT KUNTHARKHAL1 |
Completion of work |
-
latitude : 18.84271466
Longitude : 82.53998368
file name : Image_30072021134056953.png
|
2021-07-30 13:40:57.032038 |
67 |
61697571 |
SOLAR STREET LIGHT |
200000 |
SOLAR STREET LIGHT1 |
Completion of work |
-
latitude : 18.81212
Longitude : 82.50429166666666
file name : Image_09092022163857729.png
|
2022-09-09 16:38:57.812033 |
68 |
61696933 |
LEACH PIT 20 NOS @ 5000 |
100000 |
LEACH PIT 20 NOS @ 50001 |
Completion of work |
-
latitude : 18.84772
Longitude : 82.54231666666668
file name : Image_07062022132355075.png
|
2022-06-07 13:23:55.138843 |
69 |
48368041 |
WATER CONNECTION TO PALIGUDA PRY. SCHOOL |
60000 |
WATER CONNECTION TO PALIGUDA PRY. SCHOOL1 |
Completion of work |
-
latitude : 18.81167487,18.81168676
Longitude : 82.5052076,82.50499217
file name : Image_25052021132103703.png
|
2021-05-25 13:21:03.773752 |
70 |
48368057 |
WATER CONNECTION TO PALIGUDA AWC |
60000 |
WATER CONNECTION TO PALIGUDA AWC1 |
Completion of work |
-
latitude : 18.81362786,18.81355865
Longitude : 82.50140535,82.50141247
file name : Image_25052021132459567.png
|
2021-05-25 13:24:59.63658 |
71 |
48336744 |
MOTOR CONNECTION TO SUNANAGAR AWC |
20000 |
MOTOR CONNECTION TO SUNANAGAR AWC1 |
Completion of work |
-
latitude : 18.84864095
Longitude : 82.54288753
file name : Image_21052021125509745.png
|
2021-05-21 12:55:09.86564 |
72 |
48336744 |
MOTOR CONNECTION TO SUNANAGAR AWC |
20000 |
MOTOR CONNECTION TO SUNANAGAR AWC1 |
Completion of work |
-
latitude : 18.84864095
Longitude : 82.54288753
file name : Image_21052021125540933.png
|
2021-05-21 12:55:41.023794 |
73 |
66223922 |
CONSTRUCTION OF MANDAP AT BALIA |
100000 |
CONSTRUCTION OF MANDAP AT BALIA1 |
Completion of work |
-
latitude : 18.819188333333333
Longitude : 82.50528666666666
file name : Image_18012023170345436.png
|
2023-01-18 17:03:45.47954 |
74 |
66891439 |
DISTEMPERING OF GODOWN AND NEW BUILDING |
50000 |
DISTEMPERING OF GODOWN AND NEW BUILDING1 |
Completion of work |
-
latitude : 18.82835
Longitude : 82.51708666666667
file name : Image_17022023131023552.png
|
2023-02-17 13:10:23.6285 |
75 |
66891369 |
CONST OF CC ROAD FROM CHALAN SAHI CHOWK TO NAYAK SAHI GOLI |
200000 |
CONST OF CC ROAD FROM CHALAN SAHI CHOWK TO NAYAK SAHI GOLI1 |
Completion of work |
-
latitude : 18.84016,18.84044833333333
Longitude : 82.50057999999999,82.500305
file name : Image_17022023130135574.png
|
2023-02-17 13:01:35.650849 |
76 |
66223937 |
STREET LIGHT ELECTRIFICATION |
200000 |
STREET LIGHT ELECTRIFICATION1 |
Completion of work |
-
latitude : 18.875774999999997
Longitude : 82.58613833333332
file name : Image_16022023135054872.png
|
2023-02-16 13:50:54.942122 |
77 |
61696514 |
LEACH PIT 20 NOS @ 5000 |
100000 |
LEACH PIT 20 NOS @ 50001 |
Completion of work |
-
latitude : 18.82831
Longitude : 82.517005
file name : Image_20052023101047313.png
|
2023-05-20 10:10:47.374559 |
78 |
61696904 |
DUSTBIN TO AWC AND PRIMARY SCHOOL 20 NOS @ 5000 |
100000 |
DUSTBIN TO AWC AND PRIMARY SCHOOL 20 NOS @ 50001 |
Completion of work |
-
latitude : 18.82755166666667
Longitude : 82.51339833333334
file name : Image_20052023102610450.png
|
2023-05-20 10:26:10.521025 |
79 |
61697664 |
REPAIR MAINTENANCE OF PWS |
100000 |
REPAIR MAINTENANCE OF PWS1 |
Completion of work |
-
latitude : 18.841803333333335
Longitude : 82.53498833333333
file name : Image_20052023200553061.png
|
2023-05-20 20:05:53.119392 |
80 |
61696440 |
STANDPOST 5 NOS |
100000 |
STANDPOST 5 NOS 1 |
Completion of work |
-
latitude : 18.847133333333332
Longitude : 82.54256500000001
file name : Image_20052023102854388.png
|
2023-05-20 10:28:54.443021 |
81 |
52176749 |
SHOCK PIT AT PWC BALIA |
120000 |
SHOCK PIT AT PWC BALIA1 |
Completion of work |
-
latitude : 18.831171666666666
Longitude : 82.54309833333333
file name : Image_23062023133039720.png
|
2023-06-23 13:30:39.783786 |
82 |
66223964 |
CONSTRUCTION OF CC ROAD FROM BAMUNIPUT UPORGUDA SCHOOL CHAKA TO TOLAGUDA ROAD |
300000 |
CONSTRUCTION OF CC ROAD FROM BAMUNIPUT UPORGUDA SCHOOL CHAKA TO TOLAGUDA ROAD1 |
Completion of work |
-
latitude : 18.8695604,18.8695642
Longitude : 82.5733261,82.5733268
file name : Image_30062023165055434.png
|
2023-06-30 16:50:55.421386 |
83 |
66223981 |
CONSTRUCTION OF CC ROAD FROM RD ROAD TANK TO RATI GHARA |
250000 |
CONSTRUCTION OF CC ROAD FROM RD ROAD TANK TO RATI GHARA1 |
Completion of work |
-
latitude : 18.8695619,18.8695614
Longitude : 82.5733204,82.5733221
file name : Image_30062023165252005.png
|
2023-06-30 16:52:52.075607 |
84 |
66223901 |
CONSTRUCTION OF CC ROAD FROM SANOUJEI SCHOOL TO VILLAGE |
300000 |
CONSTRUCTION OF CC ROAD FROM SANOUJEI SCHOOL TO VILLAGE1 |
Completion of work |
-
latitude : 18.8695617,18.8695617
Longitude : 82.5733213,82.5733213
file name : Image_30062023165424411.png
|
2023-06-30 16:54:24.39768 |
85 |
66224022 |
DIS TEMPERING OF GP OFFICE |
50000 |
DIS TEMPERING OF GP OFFICE 1 |
Completion of work |
-
latitude : 18.8695617
Longitude : 82.5733213
file name : Image_30062023170911002.png
|
2023-06-30 17:09:10.991204 |
86 |
66224022 |
DIS TEMPERING OF GP OFFICE |
50000 |
DIS TEMPERING OF GP OFFICE 1 |
Completion of work |
-
latitude : 18.8695617
Longitude : 82.5733213
file name : Image_30062023170914282.png
|
2023-06-30 17:09:14.260802 |
87 |
61697387 |
SOLAR STREET LIGHTING |
100000 |
SOLAR STREET LIGHTING 1 |
Completion of work |
-
latitude : 18.840788333333332
Longitude : 82.50506500000002
file name : Image_19072023161034267.png
|
2023-07-19 16:10:34.370855 |
88 |
80578358 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste |
52500 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste1 |
|
-
latitude : 18.82851833333333
Longitude : 82.51691000000001
file name : Image_20072023160013266.png
|
2023-07-20 16:00:13.318476 |
89 |
80578358 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste |
52500 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste1 |
|
-
latitude : 18.82862833333333
Longitude : 82.51683999999999
file name : Image_20072023160221853.png
|
2023-07-20 16:02:21.905309 |
90 |
80578358 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste |
52500 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste1 |
|
-
latitude : 18.828595
Longitude : 82.51698833333333
file name : Image_20072023160410835.png
|
2023-07-20 16:04:10.907796 |
91 |
80578358 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste |
52500 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste1 |
|
-
latitude : 18.828488333333333
Longitude : 82.51695999999998
file name : Image_20072023160543382.png
|
2023-07-20 16:05:43.438558 |
92 |
80578358 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste |
52500 |
Purchase of Tricycles/other battery -operated vehicles for door to door collection of waste1 |
|
-
latitude : 18.8283225
Longitude : 82.5169562
file name : Image_20072023160847565.png
|
2023-07-20 16:08:47.633917 |
93 |
52176652 |
ADMN CONTIGENCY |
26428 |
ADMN CONTIGENCY1 |
Completion of work |
-
latitude : 18.82830166666667
Longitude : 82.51732333333332
file name : Image_20072023161536490.png
|
2023-07-20 16:15:36.554077 |
94 |
61696708 |
CONTINGENCY EXPENSES |
15663 |
CONTINGENCY EXPENSES1 |
Completion of work |
-
latitude : 18.869276
Longitude : 82.5733554
file name : Image_27072023175229981.png
|
2023-07-27 17:52:30.059824 |
95 |
61696708 |
CONTINGENCY EXPENSES |
15663 |
CONTINGENCY EXPENSES1 |
Completion of work |
-
latitude : 18.8692732
Longitude : 82.5733531
file name : Image_27072023175234365.png
|
2023-07-27 17:52:34.443623 |
96 |
61696611 |
PWS TO BADALIGUDA AWC WITH NEW TUBE WELL |
200000 |
PWS TO BADALIGUDA AWC WITH NEW TUBE WELL1 |
Completion of work |
-
latitude : 18.84354
Longitude : 82.53822
file name : Image_28072023175758278.png
|
2023-07-28 17:57:58.344704 |
97 |
61697712 |
REPAIR AND MAINTENANCE OF AWC PAKNAGUDA |
150000 |
REPAIR AND MAINTENANCE OF AWC PAKNAGUDA1 |
Completion of work |
-
latitude : 18.834121666666665
Longitude : 82.532475
file name : Image_28072023180456117.png
|
2023-07-28 18:04:56.189352 |
98 |
61697497 |
REPAIR AND MAINTENANCE OF AWC BADAUJEI |
50000 |
REPAIR AND MAINTENANCE OF AWC BADAUJEI1 |
Completion of work |
-
latitude : 18.834285
Longitude : 82.53222833333332
file name : Image_28072023180312447.png
|
2023-07-28 18:03:12.521254 |
99 |
52176319 |
SINKING OF TUBE WELL AT BALIA |
130000 |
SINKING OF TUBE WELL AT BALIA 1 |
Completion of work |
-
latitude : 18.843565
Longitude : 82.53823833333333
file name : Image_28072023175631200.png
|
2023-07-28 17:56:31.268152 |
100 |
61696995 |
TRI CYCLE SANITATION |
9000 |
TRI CYCLE SANITATION 1 |
Completion of work |
-
latitude : 18.828516666666665
Longitude : 82.516915
file name : Image_19072023163617504.png
|
2023-07-19 16:36:17.634125 |
101 |
61696995 |
TRI CYCLE SANITATION |
9000 |
TRI CYCLE SANITATION 1 |
Completion of work |
-
latitude : 18.828525
Longitude : 82.51698999999999
file name : Image_19072023163625067.png
|
2023-07-19 16:36:25.132112 |
102 |
61696995 |
TRI CYCLE SANITATION |
9000 |
TRI CYCLE SANITATION 1 |
Completion of work |
-
latitude : 18.82852
Longitude : 82.51691833333334
file name : Image_19072023163631295.png
|
2023-07-19 16:36:31.366553 |
103 |
61696995 |
TRI CYCLE SANITATION |
9000 |
TRI CYCLE SANITATION 1 |
Completion of work |
-
latitude : 18.8283214
Longitude : 82.5169558
file name : Image_19072023163639809.png
|
2023-07-19 16:36:39.890476 |
104 |
61696995 |
TRI CYCLE SANITATION |
9000 |
TRI CYCLE SANITATION 1 |
Completion of work |
-
latitude : 18.8283228
Longitude : 82.5169565
file name : Image_19072023163751481.png
|
2023-07-19 16:37:51.55056 |
105 |
61697419 |
SOLAR ELECTRIFICATION |
50000 |
SOLAR ELECTRIFICATION1 |
Completion of work |
-
latitude : 18.840685
Longitude : 82.50567000000001
file name : Image_19072023161525826.png
|
2023-07-19 16:15:25.910728 |
106 |
80584071 |
Maintenance of school buildings |
300000 |
Maintenance of school buildings1 |
Roof laid |
-
latitude : 18.847604999999998
Longitude : 82.54377333333332
file name : Image_20062024161054099.png
|
2024-06-20 16:10:54.178111 |
107 |
80584071 |
Maintenance of school buildings |
300000 |
Maintenance of school buildings1 |
Roof laid |
-
latitude : 18.82762166666667
Longitude : 82.51338166666667
file name : Image_19102023123824441.png
|
2023-10-19 12:38:24.496197 |
108 |
80584071 |
Maintenance of school buildings |
300000 |
Maintenance of school buildings1 |
Plinth level |
-
latitude : 18.827771666666667
Longitude : 82.51333666666666
file name : Image_19102023121049994.png
|
2023-10-19 12:10:50.053451 |
109 |
80584071 |
Maintenance of school buildings |
300000 |
Maintenance of school buildings1 |
Completion of work |
-
latitude : 18.827713333333335
Longitude : 82.51328
file name : Image_18102023115738796.png
|
2023-10-18 11:57:38.859446 |
110 |
80571404 |
Operation and Maintenance of piped water supply system |
120000 |
Operation and Maintenance of piped water supply system1 |
Completion of work |
-
latitude : 18.82841833333333
Longitude : 82.51710666666668
file name : Image_19102023125214444.png
|
2023-10-19 12:52:15.847087 |
111 |
80571404 |
Operation and Maintenance of piped water supply system |
120000 |
Operation and Maintenance of piped water supply system1 |
Completion of work |
-
latitude : 18.828375
Longitude : 82.51706666666665
file name : Image_19102023122649496.png
|
2023-10-19 12:26:49.622273 |
112 |
80570000 |
Operation and Maintenance of drinking water supply system |
150000 |
Operation and Maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 18.84179333333333
Longitude : 82.53498499999999
file name : Image_19102023132736353.png
|
2023-10-19 13:27:36.417949 |
113 |
75677579 |
Installation of Tubewell |
130000 |
Installation of Tubewell1 |
Completion of work |
-
latitude : 18.83425
Longitude : 82.53437833333334
file name : Image_30042024130759501.png
|
2024-04-30 13:07:59.564063 |
114 |
80578914 |
Retrofitting of single pit toilets to twin pit toilets |
105000 |
Retrofitting of single pit toilets to twin pit toilets1 |
Completion of work |
-
latitude : 18.84787
Longitude : 82.5429
file name : Image_30042024131805721.png
|
2024-04-30 13:18:05.77758 |
115 |
87935956 |
CONSTRUCTION OF GLOW SIGN BOARD AT GRAM PANCHAYAT OFFICE |
180000 |
CONSTRUCTION OF GLOW SIGN BOARD AT GRAM PANCHAYAT OFFICE1 |
Completion of work |
-
latitude : 18.828480000000003
Longitude : 82.51710166666665
file name : Image_08052024123704105.png
|
2024-05-08 12:37:04.167792 |
116 |
75669844 |
Operation and Maintenance of piped water supply system |
200000 |
Operation and Maintenance of piped water supply system1 |
Completion of work |
-
latitude : 18.84176
Longitude : 82.53509333333335
file name : Image_14032024163736423.png
|
2024-03-14 16:37:36.483566 |
117 |
80585645 |
Installation of Street Lights |
48664 |
Installation of Street Lights1 |
Completion of work |
-
latitude : 18.8499197,18.849925
Longitude : 82.547883,82.5479089
file name : Image_20062024160716978.png
|
2024-06-20 16:07:17.038755 |
118 |
80585084 |
Maintenance of school buildings |
102000 |
Maintenance of school buildings1 |
Completion of work |
-
latitude : 18.868799
Longitude : 82.5736536
file name : Image_21062024171753995.png
|
2024-06-21 17:17:54.062178 |
119 |
80585084 |
Maintenance of school buildings |
102000 |
Maintenance of school buildings1 |
Completion of work |
-
latitude : 18.868651666666665
Longitude : 82.57391833333334
file name : Image_21062024171750406.png
|
2024-06-21 17:17:50.466964 |
120 |
80585084 |
Maintenance of school buildings |
102000 |
Maintenance of school buildings1 |
Completion of work |
-
latitude : 18.8690221
Longitude : 82.5739249
file name : Image_21062024171744188.png
|
2024-06-21 17:17:44.247775 |
121 |
80585084 |
Maintenance of school buildings |
102000 |
Maintenance of school buildings1 |
Completion of work |
-
latitude : 18.8690459
Longitude : 82.5738717
file name : Image_21062024171740847.png
|
2024-06-21 17:17:40.909051 |
122 |
75681056 |
Drinking water facility |
43470 |
Drinking water facility1 |
|
-
latitude : 18.8284
Longitude : 82.51738333333333
file name : Image_23082024123606439.png
|
2024-08-23 12:36:06.553479 |
123 |
104216806 |
Operation and Maintenance of drinking/piped water supply system |
200000 |
Operation and Maintenance of drinking/piped water supply system1 |
Completion of work |
-
latitude : 18.8691154
Longitude : 82.573454
file name : Image_23082024123805507.png
|
2024-08-23 12:38:05.659746 |