1 |
44135078 |
REPAIR OF KITCHEN ROOM AT PUJARIPARA PS |
100000 |
REPAIR OF KITCHEN ROOM AT PUJARIPARA PS1 |
Completion of work |
-
latitude : 19.88939341
Longitude : 82.07365939
file name : Image_10102021103359160.png
|
2021-10-10 10:33:59.249947 |
2 |
44135093 |
REPAIR OF KITCHEN ROOM AT KHALEPARA PS |
100000 |
REPAIR OF KITCHEN ROOM AT KHALEPARA PS1 |
Completion of work |
-
latitude : 19.88939674
Longitude : 82.07366107
file name : Image_10102021103550209.png
|
2021-10-10 10:35:50.301156 |
3 |
46958259 |
PIPE WATER SUPPLY AT TIMANPUR AWC |
60000 |
PIPE WATER SUPPLY AT TIMANPUR AWC1 |
Completion of work |
-
latitude : 19.959484040737152,19.959425828419626
Longitude : 82.12036519311368,82.12033267132938
file name : Image_18052021101403612.png
|
2021-05-18 10:14:03.712875 |
4 |
46958504 |
PIPE WATER SUPPLY AT DHARAMPUR AWC |
60000 |
PIPE WATER SUPPLY AT DHARAMPUR AWC1 |
Completion of work |
-
latitude : 19.997997460886836,19.997979565523565
Longitude : 82.15865657664835,82.15857812203467
file name : Image_03032021201137929.png
|
2021-03-03 20:11:38.026696 |
5 |
46958504 |
PIPE WATER SUPPLY AT DHARAMPUR AWC |
60000 |
PIPE WATER SUPPLY AT DHARAMPUR AWC1 |
Completion of work |
-
latitude : 19.99799913726747,19.997977721504867
Longitude : 82.15853529050946,82.1585990767926
file name : Image_18052021103710925.png
|
2021-05-18 10:37:11.03218 |
6 |
46958939 |
PIPE WATER SUPPLY AT SOBHAPARA AWC |
60000 |
PIPE WATER SUPPLY AT SOBHAPARA AWC1 |
Completion of work |
-
latitude : 19.973320509307086,19.973272942006588
Longitude : 82.16811086051166,82.16807305812836
file name : Image_18052021105249317.png
|
2021-05-18 10:52:49.438201 |
7 |
46960364 |
PIPE WATER SUPPLY AT SARGIPARA NPS |
100000 |
PIPE WATER SUPPLY AT SARGIPARA NPS1 |
Completion of work |
-
latitude : 19.951427564956248,19.951472911052406
Longitude : 82.1610786113888,82.16107986867428
file name : Image_18052021110407507.png
|
2021-05-18 11:04:07.615979 |
8 |
46960689 |
PIPE WATER SUPPLY AT GOPALPUR NPS |
100000 |
PIPE WATER SUPPLY AT GOPALPUR NPS1 |
Completion of work |
-
latitude : 19.988750503398478,19.988775146193802
Longitude : 82.16834312304854,82.16831328347325
file name : Image_18052021103734013.png
|
2021-05-18 10:37:34.112909 |
9 |
46960689 |
PIPE WATER SUPPLY AT GOPALPUR NPS |
100000 |
PIPE WATER SUPPLY AT GOPALPUR NPS1 |
Completion of work |
-
latitude : 19.988750503398478,19.988775146193802
Longitude : 82.16834312304854,82.16831328347325
file name : Image_18052021103750504.png
|
2021-05-18 10:37:50.599415 |
10 |
46961159 |
PIPE WATER SUPPLY AT DHARAMPUR NPS |
100000 |
PIPE WATER SUPPLY AT DHARAMPUR NPS1 |
Completion of work |
-
latitude : 19.994514025747776,19.99448129441589
Longitude : 82.16073956340551,82.1607714984566
file name : Image_03032021201143404.png
|
2021-03-03 20:11:43.508164 |
11 |
46961159 |
PIPE WATER SUPPLY AT DHARAMPUR NPS |
100000 |
PIPE WATER SUPPLY AT DHARAMPUR NPS1 |
Completion of work |
-
latitude : 19.994552289135754,19.994558072648942
Longitude : 82.16080334968865,82.16084349900484
file name : Image_03032021201149170.png
|
2021-03-03 20:11:49.260986 |
12 |
46961159 |
PIPE WATER SUPPLY AT DHARAMPUR NPS |
100000 |
PIPE WATER SUPPLY AT DHARAMPUR NPS1 |
Completion of work |
-
latitude : 19.994725584983826,19.994698301889002
Longitude : 82.16066831722856,82.16065976768732
file name : Image_18052021103723212.png
|
2021-05-18 10:37:23.324212 |
13 |
46961159 |
PIPE WATER SUPPLY AT DHARAMPUR NPS |
100000 |
PIPE WATER SUPPLY AT DHARAMPUR NPS1 |
Completion of work |
-
latitude : 19.994725584983826,19.994698301889002
Longitude : 82.16066831722856,82.16065976768732
file name : Image_18052021103743032.png
|
2021-05-18 10:37:43.130485 |
14 |
46961351 |
PIPE WATER SUPPLY AT PUJARIPARA NPS |
100000 |
PIPE WATER SUPPLY AT PUJARIPARA NPS1 |
Completion of work |
-
latitude : 19.957361198030412,19.95739937759936
Longitude : 82.1311348490417,82.1310209389776
file name : Image_09032021130342298.png
|
2021-03-09 13:03:42.391872 |
15 |
46961351 |
PIPE WATER SUPPLY AT PUJARIPARA NPS |
100000 |
PIPE WATER SUPPLY AT PUJARIPARA NPS1 |
Completion of work |
-
latitude : 19.95754434261471,19.95763742364943
Longitude : 82.13100551627576,82.13112059980631
file name : Image_18052021112006051.png
|
2021-05-18 11:20:06.138764 |
16 |
46955669 |
REPAIR OF MARKET COMPLEX AT SARGIPARA |
150000 |
REPAIR OF MARKET COMPLEX AT SARGIPARA1 |
Completion of work |
-
latitude : 19.948278861120343
Longitude : 82.16005207970738
file name : Image_09032021120907318.png
|
2021-03-09 12:09:07.393652 |
17 |
46955669 |
REPAIR OF MARKET COMPLEX AT SARGIPARA |
150000 |
REPAIR OF MARKET COMPLEX AT SARGIPARA1 |
Completion of work |
-
latitude : 19.948290889151394
Longitude : 82.15998334810138
file name : Image_09032021120943066.png
|
2021-03-09 12:09:43.143105 |
18 |
46956092 |
REPAIR OF AWC BUILDING AT CHINGADABHATA |
150000 |
REPAIR OF AWC BUILDING AT CHINGADABHATA1 |
Completion of work |
-
latitude : 19.929513037204742
Longitude : 82.1322104986757
file name : Image_06042021141037821.png
|
2021-04-06 14:10:37.964085 |
19 |
44135177 |
CONST OF CC DRAIN AT BINAYPUR |
192936 |
CONST OF CC DRAIN AT BINAYPUR1 |
Completion of work |
-
latitude : 19.988823300227523,19.98884718865156
Longitude : 82.14777435176075,82.14767628349364
file name : Image_09032021120851518.png
|
2021-03-09 12:08:51.605536 |
20 |
44135177 |
CONST OF CC DRAIN AT BINAYPUR |
192936 |
CONST OF CC DRAIN AT BINAYPUR1 |
Completion of work |
-
latitude : 19.989461665973067,19.989456301555037
Longitude : 82.1473418455571,82.14729105122387
file name : Image_09032021120859601.png
|
2021-03-09 12:08:59.68116 |
21 |
46966389 |
EXTENSION OF PWS AT BALIBEDA PS |
100000 |
EXTENSION OF PWS AT BALIBEDA PS1 |
Completion of work |
-
latitude : 19.947151076048613,19.947212054394186
Longitude : 82.10790197364986,82.10810833610594
file name : Image_02032021114506982.png
|
2021-03-02 11:45:07.090186 |
22 |
46966389 |
EXTENSION OF PWS AT BALIBEDA PS |
100000 |
EXTENSION OF PWS AT BALIBEDA PS1 |
Completion of work |
-
latitude : 19.947102419100702,19.947109250351787
Longitude : 82.1080225892365,82.1081637404859
file name : Image_18052021095747560.png
|
2021-05-18 09:57:47.686872 |
23 |
44135199 |
SOLID WASTE MANAGEMENT,SEM REMUNERATION,GPDP,JALACHHATRA,AUDIT,COMPUTER REPAIR |
328936 |
SOLID WASTE MANAGEMENT,SEM REMUNERATION,GPDP,JALACHHATRA,AUDIT,COMPUTER REPAIR1 |
Completion of work |
-
latitude : 19.658856857568026,19.658817630261183
Longitude : 82.21465615555644,82.2146724164486
file name : Image_05072021120557198.png
|
2021-07-05 12:05:57.352408 |
24 |
66302770 |
Creation of a new source of drinking water |
100000 |
Creation of a new source of drinking water1 |
Completion of work |
-
latitude : 19.85197294,19.85197294
Longitude : 82.11708443,82.11708443
file name : Image_31072023215640346.png
|
2023-07-31 21:56:40.422565 |
25 |
66231107 |
REPAIR OF OLD GODOWN AT GP OFFICE |
100000 |
REPAIR OF OLD GODOWN AT GP OFFICE1 |
Completion of work |
-
latitude : 19.85197294
Longitude : 82.11708443
file name : Image_31072023215725229.png
|
2023-07-31 21:57:25.295496 |
26 |
46956514 |
CONST OF CC DRAIN AT SARGIPARA |
200000 |
CONST OF CC DRAIN AT SARGIPARA1 |
Completion of work |
-
latitude : 19.88948946,19.88947026
Longitude : 82.07369801,82.07367469
file name : Image_12112021110915350.png
|
2021-11-12 11:09:15.44741 |
27 |
46959139 |
PIPR WATER SUPPLY AT SARGIPARA AWC |
60000 |
PIPR WATER SUPPLY AT SARGIPARA AWC1 |
Completion of work |
-
latitude : 19.8893423,19.89075423
Longitude : 82.0736965,82.08029078
file name : Image_24092021094953663.png
|
2021-09-24 09:49:53.767974 |
28 |
46959139 |
PIPR WATER SUPPLY AT SARGIPARA AWC |
60000 |
PIPR WATER SUPPLY AT SARGIPARA AWC1 |
Completion of work |
-
latitude : 19.8893423,19.89075423
Longitude : 82.0736965,82.08029078
file name : Image_24092021095022358.png
|
2021-09-24 09:50:22.454593 |
29 |
46958703 |
PIPE WATER SUPPLY AT BUDRAPARA AWC |
60000 |
PIPE WATER SUPPLY AT BUDRAPARA AWC1 |
Completion of work |
-
latitude : 19.88937378,19.88937331
Longitude : 82.07369633,82.07369362
file name : Image_24092021094957122.png
|
2021-09-24 09:49:57.239215 |
30 |
46958703 |
PIPE WATER SUPPLY AT BUDRAPARA AWC |
60000 |
PIPE WATER SUPPLY AT BUDRAPARA AWC1 |
Completion of work |
-
latitude : 19.88937378,19.88937331
Longitude : 82.07369633,82.07369362
file name : Image_24092021095025447.png
|
2021-09-24 09:50:25.547517 |
31 |
46960159 |
PIPE WATER SUPPLY AT BALIBEDA AWC |
60000 |
PIPE WATER SUPPLY AT BALIBEDA AWC1 |
Completion of work |
-
latitude : 19.88936568,19.88936567
Longitude : 82.07366347,82.07366339
file name : Image_24092021095000259.png
|
2021-09-24 09:50:00.361351 |
32 |
46960159 |
PIPE WATER SUPPLY AT BALIBEDA AWC |
60000 |
PIPE WATER SUPPLY AT BALIBEDA AWC1 |
Completion of work |
-
latitude : 19.88936568,19.88936567
Longitude : 82.07366347,82.07366339
file name : Image_24092021095028421.png
|
2021-09-24 09:50:28.522531 |
33 |
46959975 |
PIPE WATER SUPPLY AT JUNANI AWC |
60000 |
PIPE WATER SUPPLY AT JUNANI AWC1 |
Completion of work |
-
latitude : 19.88936609,19.889366
Longitude : 82.07366423,82.07366372
file name : Image_24092021095003582.png
|
2021-09-24 09:50:03.679392 |
34 |
46959975 |
PIPE WATER SUPPLY AT JUNANI AWC |
60000 |
PIPE WATER SUPPLY AT JUNANI AWC1 |
Completion of work |
-
latitude : 19.88936609,19.889366
Longitude : 82.07366423,82.07366372
file name : Image_24092021095031682.png
|
2021-09-24 09:50:31.781949 |
35 |
46959698 |
PIPE WATER SUPPLY AT CHINGADABHATA AWC |
60000 |
PIPE WATER SUPPLY AT CHINGADABHATA AWC1 |
Completion of work |
-
latitude : 19.8893423,19.8893423
Longitude : 82.0736965,82.0736965
file name : Image_24092021094950287.png
|
2021-09-24 09:49:50.396794 |
36 |
46959505 |
PIPE WATER SUPPLY AT METPARA AWC |
60000 |
PIPE WATER SUPPLY AT METPARA AWC1 |
Completion of work |
-
latitude : 19.8893412,19.8893423
Longitude : 82.073695,82.0736965
file name : Image_24092021091239860.png
|
2021-09-24 09:12:39.951715 |
37 |
46959308 |
PIPE WATER SUPPLY AT KHALEPARA AWC |
60000 |
PIPE WATER SUPPLY AT KHALEPARA AWC1 |
Completion of work |
-
latitude : 19.88937345,19.88936704
Longitude : 82.07366101,82.07366386
file name : Image_24092021095006679.png
|
2021-09-24 09:50:06.787952 |
38 |
46959308 |
PIPE WATER SUPPLY AT KHALEPARA AWC |
60000 |
PIPE WATER SUPPLY AT KHALEPARA AWC1 |
Completion of work |
-
latitude : 19.88937345,19.88936704
Longitude : 82.07366101,82.07366386
file name : Image_24092021095034915.png
|
2021-09-24 09:50:35.019763 |
39 |
46961532 |
PIPE WATER SUPPLY AT BIJAPUR NPS |
100000 |
PIPE WATER SUPPLY AT BIJAPUR NPS1 |
Completion of work |
-
latitude : 19.88936582,19.8893678
Longitude : 82.07367032,82.07367097
file name : Image_24092021095009800.png
|
2021-09-24 09:50:09.897462 |
40 |
46961532 |
PIPE WATER SUPPLY AT BIJAPUR NPS |
100000 |
PIPE WATER SUPPLY AT BIJAPUR NPS1 |
Completion of work |
-
latitude : 19.88936582,19.8893678
Longitude : 82.07367032,82.07367097
file name : Image_24092021095038221.png
|
2021-09-24 09:50:38.320842 |
41 |
46961718 |
PIPE WATER SUPPLY AT CHINGADABHATA PUPS |
100000 |
PIPE WATER SUPPLY AT CHINGADABHATA PUPS1 |
Completion of work |
-
latitude : 19.88936524,19.88936512
Longitude : 82.07366823,82.07366434
file name : Image_24092021095012779.png
|
2021-09-24 09:50:12.883043 |
42 |
46961718 |
PIPE WATER SUPPLY AT CHINGADABHATA PUPS |
100000 |
PIPE WATER SUPPLY AT CHINGADABHATA PUPS1 |
Completion of work |
-
latitude : 19.88936524,19.88936512
Longitude : 82.07366823,82.07366434
file name : Image_24092021095041192.png
|
2021-09-24 09:50:41.295441 |
43 |
44135121 |
CONST OF CC DRAIN AND CULVERT AT TIMANPUR |
216000 |
CONST OF CC DRAIN AND CULVERT AT TIMANPUR1 |
Completion of work |
-
latitude : 19.88938499,19.88975938
Longitude : 82.07365729,82.07388919
file name : Image_24092021095015948.png
|
2021-09-24 09:50:16.075933 |
44 |
44135121 |
CONST OF CC DRAIN AND CULVERT AT TIMANPUR |
216000 |
CONST OF CC DRAIN AND CULVERT AT TIMANPUR1 |
Completion of work |
-
latitude : 19.88938499,19.88975938
Longitude : 82.07365729,82.07388919
file name : Image_24092021095044434.png
|
2021-09-24 09:50:44.534541 |
45 |
44135148 |
CONST OF CC DRAIN AT JUNANI |
200000 |
CONST OF CC DRAIN AT JUNANI1 |
Completion of work |
-
latitude : 19.88938439,19.88938369
Longitude : 82.0736614,82.07366059
file name : Image_24092021095047751.png
|
2021-09-24 09:50:47.852366 |
46 |
44135148 |
CONST OF CC DRAIN AT JUNANI |
200000 |
CONST OF CC DRAIN AT JUNANI1 |
Completion of work |
-
latitude : 19.88938439,19.88938369
Longitude : 82.0736614,82.07366059
file name : Image_24092021095019260.png
|
2021-09-24 09:50:19.354399 |
47 |
46957540 |
EXTENSION OF PWS AT BINAYPUR GOVT UGH |
100000 |
EXTENSION OF PWS AT BINAYPUR GOVT UGH1 |
Completion of work |
-
latitude : 19.88939326,19.8894149
Longitude : 82.0736521,82.07365266
file name : Image_24092021100056306.png
|
2021-09-24 10:00:56.393282 |
48 |
46957246 |
EXTENSION OF PWS AT JUNANI PUPS |
100000 |
EXTENSION OF PWS AT JUNANI PUPS1 |
Completion of work |
-
latitude : 19.8893886,19.88938828
Longitude : 82.07363238,82.07363223
file name : Image_24092021100240763.png
|
2021-09-24 10:02:40.8487 |
49 |
47492003 |
CONST OF BOUNDARYWALL AT SOBHAPARA SCHOOL |
150000 |
CONST OF BOUNDARYWALL AT SOBHAPARA SCHOOL1 |
Completion of work |
-
latitude : 19.8894008
Longitude : 82.07363612
file name : Image_08032022133330432.png
|
2022-03-08 13:33:30.52593 |
50 |
47491767 |
CONST OF BOUNDARYWALL AT JUNANI SCHOOL |
200000 |
CONST OF BOUNDARYWALL AT JUNANI SCHOOL1 |
Completion of work |
-
latitude : 19.8896075
Longitude : 82.0734322
file name : Image_08032022133326973.png
|
2022-03-08 13:33:27.078904 |
51 |
47492207 |
CONST OF BOUNDARYWALL AT BIJAPUR SCHOOL |
200000 |
CONST OF BOUNDARYWALL AT BIJAPUR SCHOOL1 |
Completion of work |
-
latitude : 19.88940768
Longitude : 82.07362441
file name : Image_08032022133454616.png
|
2022-03-08 13:34:54.715525 |
52 |
47492998 |
CONST OF BOUNDARYWALL AT METPARA SCHOOL |
232440 |
CONST OF BOUNDARYWALL AT METPARA SCHOOL1 |
Completion of work |
-
latitude : 19.88940286
Longitude : 82.07363179
file name : Image_08032022133804349.png
|
2022-03-08 13:38:04.462607 |
53 |
47492415 |
CONST OF PUCCA DRAIN AND CULVERT AT BIJAPUR NEAR SCHOOL |
300000 |
CONST OF PUCCA DRAIN AND CULVERT AT BIJAPUR NEAR SCHOOL1 |
Completion of work |
-
latitude : 19.8893424,19.8893417
Longitude : 82.0736965,82.0736963
file name : Image_30042022212212356.png
|
2022-04-30 21:22:12.455813 |
54 |
66303804 |
Any other operation and maintenance needs related to solid waste management |
151379 |
Any other operation and maintenance needs related to solid waste management1 |
Completion of work |
-
latitude : 19.88931728
Longitude : 82.07237213
file name : Image_13022023140351080.png
|
2023-02-13 14:03:51.146871 |
55 |
44135213 |
GP CONTRIBUTION FOR MEGHA PROJECT |
1000000 |
GP CONTRIBUTION FOR MEGHA PROJECT1 |
Completion of work |
-
latitude : 19.8892796
Longitude : 82.0724141
file name : Image_08062021134349187.png
|
2021-06-08 13:43:49.293081 |
56 |
66303832 |
Construction of Community Sanitary Complex |
90000 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 19.8885832
Longitude : 82.072207
file name : Image_13022023140317655.png
|
2023-02-13 14:03:17.725079 |
57 |
66215001 |
TRANSFER OF FUNDS TOWARDS THE 5T HIGH SCHOOL AT BINAYPUR HIGH SCHOOL |
818621 |
TRANSFER OF FUNDS TOWARDS THE 5T HIGH SCHOOL AT BINAYPUR HIGH SCHOOL1 |
Completion of work |
-
latitude : 19.92929722
Longitude : 82.08969171
file name : Image_13022023140105716.png
|
2023-02-13 14:01:05.825209 |
58 |
66214848 |
TRANSFER OF FUNDS TOWARDS THE 5t hIGH sCHOOL AT bINAYAPUR |
440000 |
TRANSFER OF FUNDS TOWARDS THE 5t hIGH sCHOOL AT bINAYAPUR1 |
Completion of work |
-
latitude : 19.92929722
Longitude : 82.08969171
file name : Image_13022023140034583.png
|
2023-02-13 14:00:34.690393 |
59 |
47482554 |
SOLID WASTE MANAGEMENT |
500000 |
SOLID WASTE MANAGEMENT5 |
Completion of work |
-
latitude : 19.9506034
Longitude : 82.11764904
file name : Image_15022023202323630.png
|
2023-02-15 20:23:23.769399 |
60 |
47491222 |
COLOURING OF GP OFFICE |
122936 |
COLOURING OF GP OFFICE1 |
Completion of work |
-
latitude : 19.8956013
Longitude : 82.07384691
file name : Image_17022023144406399.png
|
2023-02-17 14:44:06.479752 |
61 |
67192508 |
Const. of Hatapindi at Timanpur Hata |
150000 |
Const. of Hatapindi at Timanpur Hata1 |
Completion of work |
-
latitude : 19.89403338
Longitude : 82.07273836
file name : Image_14032023202401446.png
|
2023-03-14 20:24:01.504985 |
62 |
66302470 |
Augmentation of the existing source of drinking water |
120000 |
Augmentation of the existing source of drinking water1 |
Completion of work |
-
latitude : 19.88929759
Longitude : 82.07240333
file name : Image_31032023164427079.png
|
2023-03-31 16:44:27.151552 |
63 |
66231529 |
Augmentation of the existing source of drinking water |
100000 |
Augmentation of the existing source of drinking water1 |
Completion of work |
-
latitude : 19.88955133
Longitude : 82.07265636
file name : Image_31032023164221060.png
|
2023-03-31 16:42:21.154534 |
64 |
82817249 |
Water Supply to villages |
75000 |
Water Supply to villages1 |
Roof laid |
-
latitude : 19.66818827
Longitude : 82.20777957
file name : Image_30082024194040345.png
|
2024-08-30 19:40:40.96697 |
65 |
82817249 |
Water Supply to villages |
75000 |
Water Supply to villages1 |
Plinth level |
-
latitude : 19.66826187
Longitude : 82.20780413
file name : Image_30082024193501210.png
|
2024-08-30 19:35:01.775439 |
66 |
82817249 |
Water Supply to villages |
75000 |
Water Supply to villages1 |
Completion of work |
-
latitude : 19.66235457
Longitude : 82.21227361
file name : Image_30082024192820854.png
|
2024-08-30 19:28:21.329363 |
67 |
65185099 |
Const.of Boundary wall at Timanpur AWC |
150000 |
Const.of Boundary wall at Timanpur AWC1 |
Completion of work |
-
latitude : 19.85592622
Longitude : 82.11994146
file name : Image_19042023102404114.png
|
2023-04-19 10:24:04.176849 |
68 |
65185169 |
Const of Boundary Wall at Junani AWC |
150000 |
Const of Boundary Wall at Junani AWC1 |
Completion of work |
-
latitude : 19.88942622
Longitude : 82.07230317
file name : Image_19042023102805932.png
|
2023-04-19 10:28:05.994375 |
69 |
65185169 |
Const of Boundary Wall at Junani AWC |
150000 |
Const of Boundary Wall at Junani AWC1 |
Completion of work |
-
latitude : 19.88916212
Longitude : 82.07248145
file name : Image_19042023103149056.png
|
2023-04-19 10:31:49.119652 |
70 |
67192034 |
Const. of Boundary Wall at Balibeda School |
150000 |
Const. of Boundary Wall at Balibeda School1 |
Completion of work |
-
latitude : 19.88916212
Longitude : 82.07248145
file name : Image_19042023103027382.png
|
2023-04-19 10:30:27.447081 |
71 |
67191980 |
Const. of Boundary Wall at Khalepara School |
200000 |
Const. of Boundary Wall at Khalepara School1 |
Completion of work |
-
latitude : 19.88916212
Longitude : 82.07248145
file name : Image_19042023103104978.png
|
2023-04-19 10:31:05.043983 |
72 |
67192054 |
Const. of Boundary Wall at Chingadabhatta School |
200000 |
Const. of Boundary Wall at Chingadabhatta School1 |
Completion of work |
-
latitude : 19.8881985
Longitude : 82.0718666
file name : Image_29052023163230171.png
|
2023-05-29 16:32:30.258264 |
73 |
47484332 |
EXTENSION OF PIPE WATER SUPPLY AT GOPALPUR |
140000 |
EXTENSION OF PIPE WATER SUPPLY AT GOPALPUR1 |
Completion of work |
-
latitude : 19.85197294,19.85197294
Longitude : 82.11708443,82.11708443
file name : Image_31072023214405905.png
|
2023-07-31 21:44:05.971643 |
74 |
47485254 |
MANINTANANCE OF PIPE WATER SUPPLY AT TIMANPUR GP OFFICE |
180000 |
MANINTANANCE OF PIPE WATER SUPPLY AT TIMANPUR GP OFFICE1 |
Completion of work |
-
latitude : 19.85197294,19.85197294
Longitude : 82.11708443,82.11708443
file name : Image_31072023213648692.png
|
2023-07-31 21:36:48.760342 |
75 |
47484613 |
EXTENSION OF PIPE WATER SUPPLY AT CHINGADABHATA |
140000 |
EXTENSION OF PIPE WATER SUPPLY AT CHINGADABHATA1 |
Completion of work |
-
latitude : 19.85197294,19.85197294
Longitude : 82.11708443,82.11708443
file name : Image_31072023214057088.png
|
2023-07-31 21:40:57.160427 |
76 |
67192265 |
Any other operation and maintenance needs related to solid waste management |
200000 |
Any other operation and maintenance needs related to solid waste management1 |
Completion of work |
-
latitude : 19.85197294
Longitude : 82.11708443
file name : Image_31072023213415751.png
|
2023-07-31 21:34:15.816837 |
77 |
67192070 |
Const. of Boundary Wall at Budrapara School |
200000 |
Const. of Boundary Wall at Budrapara School1 |
Completion of work |
-
latitude : 19.85197294
Longitude : 82.11708443
file name : Image_31072023214208388.png
|
2023-07-31 21:42:08.458266 |
78 |
66264248 |
Operation & maintenance of drinking water supply system |
45000 |
Operation & maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 19.85638901
Longitude : 82.12027547
file name : Image_26092023131409903.png
|
2023-09-26 13:14:09.444325 |
79 |
82817433 |
Operation and Maintenance of drinking water supply system |
175000 |
Operation and Maintenance of drinking water supply system1 |
Completion of work |
-
latitude : 19.8894362
Longitude : 82.0721466
file name : Image_02072024121552471.png
|
2024-07-02 12:15:52.59587 |
80 |
66303854 |
Any other operation and maintenance needs related to solid waste management |
150985 |
Any other operation and maintenance needs related to solid waste management1 |
Completion of work |
-
latitude : 19.88932369
Longitude : 82.07250115
file name : Image_19102023131605712.png
|
2023-10-19 13:16:05.776112 |
81 |
82049487 |
Construction of Boundary Wall |
150000 |
Construction of Boundary Wall1 |
Roof laid |
-
latitude : 19.8893794
Longitude : 82.0721326
file name : Image_06092024170210643.png
|
2024-09-06 17:02:59.494223 |
82 |
82049487 |
Construction of Boundary Wall |
150000 |
Construction of Boundary Wall1 |
Plinth level |
-
latitude : 19.8893837
Longitude : 82.0721324
file name : Image_06092024165828356.png
|
2024-09-06 16:58:28.465906 |
83 |
82049487 |
Construction of Boundary Wall |
150000 |
Construction of Boundary Wall1 |
Completion of work |
-
latitude : 19.95973702
Longitude : 82.11997554
file name : Image_06092024165132037.png
|
2024-09-06 16:51:32.138551 |
84 |
82049596 |
Construction of Boundary Wall |
150000 |
Construction of Boundary Wall1 |
Roof laid |
-
latitude : 19.88928582
Longitude : 82.07240563
file name : Image_06092024171126214.png
|
2024-09-06 17:11:26.329071 |
85 |
82049596 |
Construction of Boundary Wall |
150000 |
Construction of Boundary Wall1 |
Plinth level |
-
latitude : 19.88927997
Longitude : 82.07244947
file name : Image_06092024170902555.png
|
2024-09-06 17:09:02.68989 |
86 |
82049596 |
Construction of Boundary Wall |
150000 |
Construction of Boundary Wall1 |
Completion of work |
-
latitude : 19.88929787
Longitude : 82.07243073
file name : Image_06092024170551080.png
|
2024-09-06 17:05:51.413638 |
87 |
82817320 |
Augmentation of existing sources of Drinking Water |
120000 |
Augmentation of existing sources of Drinking Water1 |
Roof laid |
-
latitude : 19.889431
Longitude : 82.0721376
file name : Image_04072024121434445.png
|
2024-07-04 12:14:34.549924 |
88 |
82817320 |
Augmentation of existing sources of Drinking Water |
120000 |
Augmentation of existing sources of Drinking Water1 |
Plinth level |
-
latitude : 19.88934543
Longitude : 82.07251208
file name : Image_04072024120046465.png
|
2024-07-04 12:00:46.559874 |
89 |
82817320 |
Augmentation of existing sources of Drinking Water |
120000 |
Augmentation of existing sources of Drinking Water1 |
Completion of work |
-
latitude : 19.8892649
Longitude : 82.0724838
file name : Image_04072024115805114.png
|
2024-07-04 11:58:05.238633 |
90 |
82049309 |
Maintenance of school buildings |
800000 |
Maintenance of school buildings1 |
Roof laid |
-
latitude : 19.82843882
Longitude : 82.11770825
file name : Image_04072024170403757.png
|
2024-07-04 17:04:03.856789 |
91 |
82049309 |
Maintenance of school buildings |
800000 |
Maintenance of school buildings1 |
Plinth level |
-
latitude : 19.87692454
Longitude : 82.08446174
file name : Image_04072024165248571.png
|
2024-07-04 16:52:48.714777 |
92 |
82049309 |
Maintenance of school buildings |
800000 |
Maintenance of school buildings1 |
Completion of work |
-
latitude : 19.88932524
Longitude : 82.07246078
file name : Image_04072024161528550.png
|
2024-07-04 16:15:28.672449 |