1 |
40236230 |
To construct underground drainage ward no.2 |
277814 |
To construct underground drainage ward no.21 |
Completion of work |
-
latitude : 18.7465544,18.7465544
Longitude : 73.8608758,73.8608758
file name : Image_24022022150017642.png
|
2022-02-24 15:00:17.73934 |
2 |
40236230 |
To construct underground drainage ward no.2 |
277814 |
To construct underground drainage ward no.21 |
Completion of work |
-
latitude : 18.7465544,18.7465544
Longitude : 73.8608758,73.8608758
file name : Image_24022022150033303.png
|
2022-02-24 15:00:33.389375 |
3 |
40236515 |
To construct underground drainage ward no.3 |
277814 |
To construct underground drainage ward no.31 |
Completion of work |
-
latitude : 18.7461379,18.7461379
Longitude : 73.861901,73.861901
file name : Image_24022022150020330.png
|
2022-02-24 15:00:20.426312 |
4 |
40236515 |
To construct underground drainage ward no.3 |
277814 |
To construct underground drainage ward no.31 |
Completion of work |
-
latitude : 18.7461379,18.7461379
Longitude : 73.861901,73.861901
file name : Image_24022022150036007.png
|
2022-02-24 15:00:36.092788 |
5 |
40231966 |
Increasing pipeline to pipeline scheme IN WARD NO 2 |
300000 |
Increasing pipeline to pipeline scheme IN WARD NO 21 |
Completion of work |
-
latitude : 18.7459816,18.7459816
Longitude : 73.860815,73.860815
file name : Image_24022022150014813.png
|
2022-02-24 15:00:14.914039 |
6 |
40231966 |
Increasing pipeline to pipeline scheme IN WARD NO 2 |
300000 |
Increasing pipeline to pipeline scheme IN WARD NO 21 |
Completion of work |
-
latitude : 18.7459816,18.7459816
Longitude : 73.860815,73.860815
file name : Image_24022022150030655.png
|
2022-02-24 15:00:30.747496 |
7 |
40232409 |
Increasing pipeline to pipeline scheme in ward no 3 |
300000 |
Increasing pipeline to pipeline scheme in ward no 31 |
Completion of work |
-
latitude : 18.7442047,18.7442047
Longitude : 73.8618322,73.8618322
file name : Image_24022022150012162.png
|
2022-02-24 15:00:12.264502 |
8 |
40232409 |
Increasing pipeline to pipeline scheme in ward no 3 |
300000 |
Increasing pipeline to pipeline scheme in ward no 31 |
Completion of work |
-
latitude : 18.7442047,18.7442047
Longitude : 73.8618322,73.8618322
file name : Image_24022022150028008.png
|
2022-02-24 15:00:28.100267 |
9 |
40231233 |
Plumbing scheme Increased pipeline spraying |
300000 |
Plumbing scheme Increased pipeline spraying1 |
Completion of work |
-
latitude : 18.739100312814116,18.73907923232764
Longitude : 73.8625103328377,73.86244252324104
file name : Image_24022022142602414.png
|
2022-02-24 14:26:02.487261 |
10 |
40242963 |
To Installation of high mast lamps at Shankarnagar and its environs in backward class areas |
114632 |
To Installation of high mast lamps at Shankarnagar and its environs in backward class areas1 |
Completion of work |
-
latitude : 18.796674725599587
Longitude : 73.87397719547153
file name : Image_27012022223004747.png
|
2022-01-27 22:30:04.83565 |
11 |
40237366 |
To construct underground drainage ward no.5 |
277814 |
To construct underground drainage ward no.51 |
Completion of work |
-
latitude : 18.74423326458782,18.74423326458782
Longitude : 73.86319002136588,73.86319002136588
file name : Image_29032022231124259.png
|
2022-03-29 23:11:24.33048 |
12 |
40235911 |
To construct underground drainage ward no.1 |
277814 |
To construct underground drainage ward no.11 |
Completion of work |
-
latitude : 18.738954216241837,18.738981247879565
Longitude : 73.86486154049635,73.86483094654977
file name : Image_24022022150008797.png
|
2022-02-24 15:00:08.901889 |
13 |
40237038 |
To construct underground drainage ward no.4 |
277814 |
To construct underground drainage ward no.41 |
Completion of work |
-
latitude : 18.7451209,18.7451209
Longitude : 73.8617007,73.8617007
file name : Image_29032022231120739.png
|
2022-03-29 23:11:20.806305 |
14 |
40237796 |
To construct underground drainage ward no.6 |
277813 |
To construct underground drainage ward no.61 |
Completion of work |
-
latitude : 18.7504424,18.7504424
Longitude : 73.873884,73.873884
file name : Image_29032022231128109.png
|
2022-03-29 23:11:28.178775 |
15 |
40229559 |
Purchasing and spraying disinfectants |
300000 |
Purchasing and spraying disinfectants1 |
Completion of work |
-
latitude : 18.7467523
Longitude : 73.8694002
file name : Image_30032022145115558.png
|
2022-03-30 14:51:15.65244 |
16 |
40243700 |
Installing light poles in ward no 1 and 2 |
300000 |
Installing light poles in ward no 1 and 21 |
Completion of work |
-
latitude : 18.739538
Longitude : 73.8650828
file name : Image_23052022173210529.png
|
2022-05-23 17:32:10.615331 |
17 |
40243963 |
Installing light poles in ward no 3 and 4 |
300000 |
Installing light poles in ward no 3 and 41 |
Completion of work |
-
latitude : 18.7460896
Longitude : 73.8618829
file name : Image_23052022173803308.png
|
2022-05-23 17:38:03.392747 |
18 |
40244240 |
Installing light poles in ward no 5 and 6 |
300000 |
Installing light poles in ward no 5 and 61 |
Completion of work |
-
latitude : 18.7455462
Longitude : 73.8660715
file name : Image_23052022172525320.png
|
2022-05-23 17:25:25.397977 |
19 |
40239549 |
To distribution of PT dress to school children |
300000 |
To distribution of PT dress to school children1 |
Completion of work |
-
latitude : 18.7467307
Longitude : 73.8694336
file name : Image_30062022122404371.png
|
2022-06-30 12:24:04.440873 |
20 |
57090677 |
गावातील महिलांना स्वयंरोजगार प्रशिक्षण देणे |
179914 |
गावातील महिलांना स्वयंरोजगार प्रशिक्षण देणे 1 |
Completion of work |
-
latitude : 18.7970872
Longitude : 73.8737065
file name : Image_30062022120815006.png
|
2022-06-30 12:08:15.082883 |
21 |
40244546 |
Installing led lights in ward no 1 and 2 |
300000 |
Installing led lights in ward no 1 and 21 |
Completion of work |
-
latitude : 18.746816
Longitude : 73.8695743
file name : Image_30062022123211385.png
|
2022-06-30 12:32:11.461145 |
22 |
40244778 |
Installing led lights in ward no 3 and 4 |
300000 |
Installing led lights in ward no 3 and 41 |
Completion of work |
-
latitude : 18.7469756
Longitude : 73.8695128
file name : Image_30062022123214251.png
|
2022-06-30 12:32:14.333374 |
23 |
40245018 |
Installing led lights in ward no 5 and 6 |
300000 |
Installing led lights in ward no 5 and 61 |
Completion of work |
-
latitude : 18.7466486
Longitude : 73.869497
file name : Image_30062022123217329.png
|
2022-06-30 12:32:17.400646 |
24 |
50835094 |
To Construct concrete road in sant tukaram colony banglawasti |
300000 |
To Construct concrete road in sant tukaram colony banglawasti1 |
Completion of work |
-
latitude : 18.7389719,18.7389719,18.7389719
Longitude : 73.8618297,73.8618297,73.8618297
file name : Image_29082022193907024.png
|
2022-08-29 19:39:07.102118 |
25 |
50834684 |
To construct concrete road in magaswargiy wasti dnyansagar colony |
300000 |
To construct concrete road in magaswargiy wasti dnyansagar colony1 |
Completion of work |
-
latitude : 18.7392385,18.7392385,18.7392385
Longitude : 73.8609419,73.8609419,73.8609419
file name : Image_29082022195741268.png
|
2022-08-29 19:57:41.361964 |
26 |
40239983 |
To distribution of eductional kits to school children |
147549 |
To distribution of eductional kits to school children1 |
Completion of work |
-
latitude : 18.74658313114196
Longitude : 73.86954459361732
file name : Image_25082022162405994.png
|
2022-08-25 16:24:06.059933 |
27 |
50835218 |
To construct concrete road in vrundavan colony banglawasti |
300000 |
To construct concrete road in vrundavan colony banglawasti1 |
Completion of work |
-
latitude : 18.7395943,18.7395943,18.7395943
Longitude : 73.8621145,73.8621145,73.8621145
file name : Image_29082022193506139.png
|
2022-08-29 19:35:06.213408 |
28 |
50833975 |
To distribute dress for ZP school childrens |
300000 |
To distribute dress for ZP school childrens1 |
Completion of work |
-
latitude : 18.746109888888896
Longitude : 73.86941224336624
file name : Image_30062022122401800.png
|
2022-06-30 12:24:01.867883 |
29 |
50835481 |
To construct concrete road in ward no 5 |
300000 |
To construct concrete road in ward no 51 |
Completion of work |
-
latitude : 18.745231591165066,18.745312518440187,18.74521302524954
Longitude : 73.86452584527433,73.86455979198217,73.86453540064394
file name : Image_29082022195754969.png
|
2022-08-29 19:57:55.055389 |
30 |
40240605 |
To distribution of mediclore in village |
100000 |
To distribution of mediclore in village1 |
Completion of work |
-
latitude : 18.7467539
Longitude : 73.8694777
file name : Image_30082022150825673.png
|
2022-08-30 15:08:25.737333 |
31 |
50789317 |
To Construct Underground Drainage in ward no 4 |
300000 |
To Construct Underground Drainage in ward no 41 |
Completion of work |
-
latitude : 18.744099782779813,18.744077109731734
Longitude : 73.86289053596556,73.86297209188342
file name : Image_30092022191212726.png
|
2022-09-30 19:12:12.784356 |
32 |
50790417 |
To construct underground drainage from shantaram bhujbal house to machhindra bhujbal house |
300000 |
To construct underground drainage from shantaram bhujbal house to machhindra bhujbal house1 |
Completion of work |
-
latitude : 18.7464814,18.7464814
Longitude : 73.8700264,73.8700264
file name : Image_30092022185526125.png
|
2022-09-30 18:55:26.197792 |
33 |
50834988 |
To construct Underground drainage in Magaswargiy wasti |
146622 |
To construct Underground drainage in Magaswargiy wasti1 |
Completion of work |
-
latitude : 18.741123410873115,18.74109440948814
Longitude : 73.87144636362791,73.87144996784627
file name : Image_30092022184433203.png
|
2022-09-30 18:44:33.26748 |
34 |
40238344 |
Spraying medicine in the village |
199360 |
Spraying medicine in the village1 |
Completion of work |
-
latitude : 18.7447539
Longitude : 73.8671906
file name : Image_28012022105637097.png
|
2022-01-28 10:56:37.195437 |
35 |
50835662 |
To construct Concrete road in gajanan maharaj nagar from gawai house to khanande house |
300000 |
To construct Concrete road in gajanan maharaj nagar from gawai house to khanande house1 |
Completion of work |
-
latitude : 18.751177210360765,18.75119850039482,18.751199087128043
Longitude : 73.87275846675038,73.87274228967726,73.87271907180548
file name : Image_09122022154411529.png
|
2022-12-09 15:44:11.595439 |
36 |
50836358 |
To construct concrete road in gajanan maharaj nagar from bhavsar house to ingale house |
300000 |
To construct concrete road in gajanan maharaj nagar from bhavsar house to ingale house1 |
Completion of work |
-
latitude : 18.751787329092622,18.751787329092622,18.75174839515239
Longitude : 73.87237382121384,73.87237382121384,73.87236912734807
file name : Image_09122022184101887.png
|
2022-12-09 18:41:01.951223 |
37 |
40241572 |
To Setup CCTV cameras in village for protection of womens |
239020 |
To Setup CCTV cameras in village for protection of womens 1 |
Completion of work |
-
latitude : 18.7466353
Longitude : 73.8694997
file name : Image_09122022164903414.png
|
2022-12-09 16:49:03.475023 |
38 |
50789637 |
To Construct Underground Drainage in ward no 5 |
300000 |
To Construct Underground Drainage in ward no 51 |
Completion of work |
-
latitude : 18.7467284,18.7467284
Longitude : 73.8643541,73.8643541
file name : Image_15122022115209704.png
|
2022-12-15 11:52:09.79021 |
39 |
50833153 |
To construct Class Room of ZP school |
976009 |
To construct Class Room of ZP school 1 |
Completion of work |
-
latitude : 18.7465453
Longitude : 73.8695079
file name : Image_13122022164703598.png
|
2022-12-13 16:47:03.67379 |
40 |
50792749 |
to construct GI water supply line from sarpanch chowk to rithdm |
300000 |
to construct GI water supply line from sarpanch chowk to rithdm 1 |
Completion of work |
-
latitude : 18.7479697,18.747818,18.747818,18.747818
Longitude : 73.8690747,73.8690834,73.8690834,73.8690834
file name : Image_25032023145712946.png
|
2023-03-25 14:57:13.014949 |
41 |
50793132 |
To construct water supply line in village |
184454 |
To construct water supply line in village1 |
Completion of work |
-
latitude : 18.735984382219613,18.735949178226292
Longitude : 73.86265684850514,73.86272767558694
file name : Image_25032023142427514.png
|
2023-03-25 14:24:27.580523 |
42 |
57097314 |
ग्रामपंचायतमध्ये CCTV कंट्रोल रूम व इतर सुविधा करणे |
449218 |
ग्रामपंचायतमध्ये CCTV कंट्रोल रूम व इतर सुविधा करणे 1 |
Completion of work |
-
latitude : 18.7500051
Longitude : 73.8678965
file name : Image_25032023150021736.png
|
2023-03-25 15:00:21.806455 |
43 |
50785643 |
ghankachara vyavasthapan suvidha uplabdh karne |
668909 |
ghankachara vyavasthapan suvidha uplabdh karne 1 |
Completion of work |
-
latitude : 18.7467613
Longitude : 73.8694088
file name : Image_25032023153228285.png
|
2023-03-25 15:32:28.355871 |
44 |
57026848 |
घनकचरा व्यवस्थापन |
2332614 |
घनकचरा व्यवस्थापन1 |
Completion of work |
-
latitude : 18.7469052
Longitude : 73.8694587
file name : Image_25032023153324012.png
|
2023-03-25 15:33:24.068083 |
45 |
57072666 |
महिलांना सँनिटरी पँडचे वाटप करणे |
200000 |
महिलांना सँनिटरी पँडचे वाटप करणे 1 |
Completion of work |
-
latitude : 18.746273503638804
Longitude : 73.87002294883132
file name : Image_25032023153529965.png
|
2023-03-25 15:35:30.031498 |
46 |
50790981 |
To construct 3 inch GI Water Supply Line from bhagatwasti corner to haribhau khule house |
300000 |
To construct 3 inch GI Water Supply Line from bhagatwasti corner to haribhau khule house1 |
Completion of work |
-
latitude : 18.7372172,18.7372172,18.7372172
Longitude : 73.8608459,73.8608459,73.8608459
file name : Image_25032023142338584.png
|
2023-03-25 14:23:38.645761 |
47 |
50791181 |
To construct 3 inch GI Water supply line from sant dnyaneshwar colony to shreerang medankar house |
300000 |
To construct 3 inch GI Water supply line from sant dnyaneshwar colony to shreerang medankar house1 |
Completion of work |
-
latitude : 18.735780576243997,18.735801614820957,18.735831496305764
Longitude : 73.86273723095655,73.86273102834821,73.86282792314887
file name : Image_25032023142855436.png
|
2023-03-25 14:28:55.496493 |
48 |
50791499 |
To construct 3 inch GI water supply line from pandurang medankar house to shivtej colony |
300000 |
To construct 3 inch GI water supply line from pandurang medankar house to shivtej colony 1 |
Completion of work |
-
latitude : 18.735127206891775,18.735127206891775,18.735140031203628
Longitude : 73.86463799513876,73.86463799513876,73.86463724076748
file name : Image_25032023143637315.png
|
2023-03-25 14:36:37.378606 |
49 |
50792033 |
to construct GI water supply line in ward no 2 |
300000 |
to construct GI water supply line in ward no 21 |
Completion of work |
-
latitude : 18.7471216,18.747168
Longitude : 73.8602303,73.8602432
file name : Image_25032023144849655.png
|
2023-03-25 14:48:49.716988 |
50 |
50792458 |
To construct 3 inch GI Water supply line from baban medankar house to kalp residency |
300000 |
To construct 3 inch GI Water supply line from baban medankar house to kalp residency1 |
Completion of work |
-
latitude : 18.7500231,18.7499418
Longitude : 73.8680216,73.8681327
file name : Image_25032023150334397.png
|
2023-03-25 15:03:34.461876 |
51 |
57094736 |
मागासवर्गीय वस्ती गावठाण मध्ये सौर ऊर्जा प्रकल्प करणे |
320221 |
मागासवर्गीय वस्ती गावठाण मध्ये सौर ऊर्जा प्रकल्प करणे 1 |
Completion of work |
-
latitude : 18.7467851
Longitude : 73.8694914
file name : Image_31032023185353399.png
|
2023-03-31 18:53:53.455693 |
52 |
57072253 |
गावात धूर औषध फवारणी करणे |
200000 |
गावात धूर औषध फवारणी करणे 1 |
Completion of work |
-
latitude : 18.7469799
Longitude : 73.8694978
file name : Image_31032023185053437.png
|
2023-03-31 18:50:53.499345 |
53 |
57028253 |
पाणी शुद्धीकरण साहित्य खरेदी करणे TCL व मेडीक्लोर |
500000 |
पाणी शुद्धीकरण साहित्य खरेदी करणे TCL व मेडीक्लोर 1 |
Completion of work |
-
latitude : 18.7465424
Longitude : 73.8695071
file name : Image_31032023185939998.png
|
2023-03-31 18:59:40.055328 |
54 |
40243388 |
Installation of Led Lamp in Backward Classes |
214233 |
Installation of Led Lamp in Backward Classes1 |
Completion of work |
-
latitude : 18.7467978
Longitude : 73.8694852
file name : Image_31032023185547660.png
|
2023-03-31 18:55:47.72101 |
55 |
40234815 |
Increasing pipeline to pipeline scheme in ward no 5 |
300000 |
Increasing pipeline to pipeline scheme in ward no 51 |
Completion of work |
-
latitude : 18.7472731,18.747018864378333,18.747015176340938
Longitude : 73.8671889,73.86741039343178,73.86738055385649
file name : Image_25082023153443696.png
|
2023-08-25 15:34:43.806008 |
56 |
40234003 |
Increasing pipeline to pipeline scheme in ward no 4 |
300000 |
Increasing pipeline to pipeline scheme in ward no 41 |
Completion of work |
-
latitude : 18.746624286286533,18.746570223011076,18.74655228573829
Longitude : 73.86703823693097,73.86674989946187,73.86674076318741
file name : Image_25082023155342509.png
|
2023-08-25 15:53:42.594233 |
57 |
50790057 |
To Construct Underground Drainage in ward no 6 |
300000 |
To Construct Underground Drainage in ward no 61 |
Completion of work |
-
latitude : 18.74527777545154,18.74527777545154,18.745302418246865
Longitude : 73.87153445743024,73.87153445743024,73.87155809439719
file name : Image_25082023155451949.png
|
2023-08-25 15:54:52.029766 |
58 |
50836580 |
To setup Hymast in Martand nagar and gajanan maharaj nagar |
291001 |
To setup Hymast in Martand nagar and gajanan maharaj nagar 1 |
Completion of work |
-
latitude : 18.74444532673806
Longitude : 73.86464050970972
file name : Image_25082023161112706.png
|
2023-08-25 16:11:12.833201 |
59 |
50835383 |
To construct concrete road in balajinagar |
300000 |
To construct concrete road in balajinagar1 |
Completion of work |
-
latitude : 18.7463027,18.7463027,18.7463027
Longitude : 73.8608956,73.8608956,73.8608956
file name : Image_28082023000759777.png
|
2023-08-28 00:07:59.836332 |
60 |
83879550 |
Equipment for Hospital |
200000 |
Equipment for Hospital1 |
|
-
latitude : 18.7467168
Longitude : 73.8694709
file name : Image_30082023162455760.png
|
2023-08-30 16:24:55.824054 |
61 |
83855109 |
Chlorinization of drinking water source |
120000 |
Chlorinization of drinking water source1 |
Roof laid |
-
latitude : 18.7467285
Longitude : 73.8694785
file name : Image_30082023172651973.png
|
2023-08-30 17:26:52.0385 |
62 |
83855109 |
Chlorinization of drinking water source |
120000 |
Chlorinization of drinking water source1 |
Plinth level |
-
latitude : 18.7467035
Longitude : 73.8694921
file name : Image_30082023172459873.png
|
2023-08-30 17:24:59.936676 |
63 |
83855109 |
Chlorinization of drinking water source |
120000 |
Chlorinization of drinking water source1 |
Completion of work |
-
latitude : 18.7467141
Longitude : 73.8694749
file name : Image_30082023170941819.png
|
2023-08-30 17:09:41.882577 |
64 |
83855109 |
Chlorinization of drinking water source |
120000 |
Chlorinization of drinking water source1 |
Completion of work |
-
latitude : 18.7468633
Longitude : 73.8693738
file name : Image_30082023170326499.png
|
2023-08-30 17:03:26.562266 |
65 |
83852116 |
Construction of toilets in public institutions |
108000 |
Construction of toilets in public institutions1 |
Roof laid |
-
latitude : 18.743435852229595
Longitude : 73.86313922703266
file name : Image_28082023173928204.png
|
2023-08-28 17:39:28.28176 |
66 |
83852116 |
Construction of toilets in public institutions |
108000 |
Construction of toilets in public institutions1 |
Plinth level |
-
latitude : 18.743557473644614
Longitude : 73.86317258700728
file name : Image_28082023171549953.png
|
2023-08-28 17:15:50.033964 |
67 |
83852116 |
Construction of toilets in public institutions |
108000 |
Construction of toilets in public institutions1 |
Completion of work |
-
latitude : 18.743543014861643
Longitude : 73.86308600194752
file name : Image_25082023161658070.png
|
2023-08-25 16:16:58.140173 |
68 |
57091424 |
अंगणवाडी दुरुस्ती करणे |
100000 |
अंगणवाडी दुरुस्ती करणे 1 |
Completion of work |
-
latitude : 18.7474633
Longitude : 73.8694615
file name : Image_19122023135316019.png
|
2023-12-19 13:53:16.118811 |
69 |
50792916 |
To construct Gi water supply line inward no 5 |
184455 |
To construct Gi water supply line inward no 51 |
Completion of work |
-
latitude : 18.7446685,18.7446685,18.7446685
Longitude : 73.864627,73.864627,73.864627
file name : Image_19122023125939575.png
|
2023-12-19 12:59:39.666851 |
70 |
57096185 |
गावातील अंतर्गत रस्त्यांच्या साईड पट्ट्या काँक्रिटीकरण करणे |
500000 |
गावातील अंतर्गत रस्त्यांच्या साईड पट्ट्या काँक्रिटीकरण करणे 1 |
Completion of work |
-
latitude : 18.74661561101675,18.746602116152644
Longitude : 73.86666557751596,73.86668385006487
file name : Image_19122023145239196.png
|
2023-12-19 14:52:39.313405 |
71 |
57095319 |
साईनगर येथे सभागृह बांधणे |
550000 |
साईनगर येथे सभागृह बांधणे 1 |
Completion of work |
-
latitude : 18.7426787
Longitude : 73.861465
file name : Image_19122023150042569.png
|
2023-12-19 15:00:42.648834 |
72 |
50834440 |
To distribute dress and essential material for anganwadi childrens |
90404 |
To distribute dress and essential material for anganwadi childrens1 |
|
-
latitude : 18.797102705575526
Longitude : 73.87368475086987
file name : Image_26122023231828596.png
|
2023-12-26 23:18:28.686516 |