1 |
46208456 |
Providing FHTC and Extension of Pipeline at Panamarathupatti Arunthathir Colony H/O Keelkuppam |
533000 |
Providing FHTC and Extension of Pipeline at Panamarathupatti Arunthathir Colony H/O Keelkuppam1 |
Roof laid |
-
latitude : 12.21790773,12.21791732
Longitude : 78.52225222,78.5222518
file name : Image_22102021145922899.png
|
2021-10-22 14:59:22.997471 |
2 |
46410819 |
Consruction Of Soak Pit at Construction of soak pit at Keelkuppam (45 Nos) H/O Keelkuppam |
418500 |
Consruction Of Soak Pit at Construction of soak pit at Keelkuppam (45 Nos) H/O Keelkuppam1 |
Roof laid |
-
latitude : 12.215068333333333
Longitude : 78.52326666666666
file name : Image_03022022091110231.png
|
2022-02-03 09:11:10.331024 |
3 |
66959719 |
Operation & maintenance of composting shed/center |
54600 |
Operation & maintenance of composting shed/center1 |
Roof laid |
-
latitude : 12.23358496
Longitude : 78.51297326
file name : Image_22022023192117984.png
|
2023-02-22 19:21:18.0897 |
4 |
66959700 |
Operation & maintenance of community compost pits |
104567 |
Operation & maintenance of community compost pits1 |
Roof laid |
-
latitude : 12.21283691
Longitude : 78.52109946
file name : Image_23022023174957756.png
|
2023-02-23 17:49:57.847399 |
5 |
87745893 |
Water Supply to villages |
127046 |
Water Supply to villages1 |
Completion of work |
-
latitude : 12.2334893
Longitude : 78.51289253
file name : Image_04102023232723082.png
|
2023-10-04 23:27:23.153214 |
6 |
49461457 |
Providing FHTC, and Extension of Pipeline at Panamarathupatti Arunthathiyar Colony H/O Keelkuppam |
209400 |
Providing FHTC, and Extension of Pipeline at Panamarathupatti Arunthathiyar Colony H/O Keelkuppam1 |
Completion of work |
-
latitude : 12.23342904,12.23342904
Longitude : 78.51298844,78.51298844
file name : Image_04102023202342939.png
|
2023-10-04 20:23:43.03483 |
7 |
66959849 |
Operation & maintenance of community compost pits |
39000 |
Operation & maintenance of community compost pits1 |
Completion of work |
-
latitude : 12.23262547
Longitude : 78.51229756
file name : Image_04102023133120832.png
|
2023-10-04 13:31:20.928927 |
8 |
49461746 |
Providing FHTC, and Extension of Pipeline at Keelkuppam BC Street H/O Keelkuppam |
498000 |
Providing FHTC, and Extension of Pipeline at Keelkuppam BC Street H/O Keelkuppam1 |
Completion of work |
-
latitude : 12.2336079,12.2336079
Longitude : 78.51280883,78.51280883
file name : Image_05012024103616338.png
|
2024-01-05 10:36:16.438401 |
9 |
94813050 |
Construction of new Piped Water Supply schemes |
190000 |
Construction of new Piped Water Supply schemes1 |
Roof laid |
-
latitude : 12.17943562
Longitude : 78.56062815
file name : Image_20022024153932325.png
|
2024-02-20 15:39:32.4221 |
10 |
94813050 |
Construction of new Piped Water Supply schemes |
190000 |
Construction of new Piped Water Supply schemes1 |
Plinth level |
-
latitude : 12.17942359
Longitude : 78.56063849
file name : Image_20022024152915981.png
|
2024-02-20 15:29:16.112839 |
11 |
94813050 |
Construction of new Piped Water Supply schemes |
190000 |
Construction of new Piped Water Supply schemes1 |
Completion of work |
-
latitude : 12.17934202
Longitude : 78.56071449
file name : Image_20022024144106929.png
|
2024-02-20 14:41:07.010306 |
12 |
94815069 |
Construction of new Piped Water Supply schemes |
455780 |
Construction of new Piped Water Supply schemes1 |
Roof laid |
-
latitude : 12.1838418
Longitude : 78.5491674
file name : Image_25052024110954401.png
|
2024-05-25 11:09:54.483322 |
13 |
94815069 |
Construction of new Piped Water Supply schemes |
455780 |
Construction of new Piped Water Supply schemes1 |
Plinth level |
-
latitude : 12.2707339
Longitude : 78.5295686
file name : Image_24052024175154771.png
|
2024-05-24 17:51:54.849394 |
14 |
94815069 |
Construction of new Piped Water Supply schemes |
455780 |
Construction of new Piped Water Supply schemes1 |
Completion of work |
-
latitude : 12.18380616
Longitude : 78.54661201
file name : Image_23052024165201502.png
|
2024-05-23 16:52:01.582788 |
15 |
94815069 |
Construction of new Piped Water Supply schemes |
455780 |
Construction of new Piped Water Supply schemes1 |
Completion of work |
-
latitude : 12.18380616
Longitude : 78.54661201
file name : Image_23052024165153936.png
|
2024-05-23 16:51:54.016198 |
16 |
87745659 |
Water Supply to villages |
251000 |
Water Supply to villages1 |
Completion of work |
-
latitude : 12.18381015
Longitude : 78.54660941
file name : Image_23052024165157728.png
|
2024-05-23 16:51:57.811351 |
17 |
87745659 |
Water Supply to villages |
251000 |
Water Supply to villages1 |
Completion of work |
-
latitude : 12.18381015
Longitude : 78.54660941
file name : Image_23052024165150079.png
|
2024-05-23 16:51:50.154433 |
18 |
66959654 |
Water Supply to villages |
553015 |
Water Supply to villages1 |
Completion of work |
-
latitude : 12.18380014
Longitude : 78.54660111
file name : Image_23052024165146581.png
|
2024-05-23 16:51:46.659935 |
19 |
49113739 |
Providing FHTC, and Extension of Pipeline at Perumal Kovil Street H/O Keelkuppam |
20019 |
Providing FHTC, and Extension of Pipeline at Perumal Kovil Street H/O Keelkuppam1 |
Completion of work |
-
latitude : 12.2555909,12.2555909
Longitude : 78.5341439,78.5341439
file name : Image_26062024131711834.png
|
2024-06-26 13:17:11.927883 |
20 |
49462000 |
Providing FHTC, and Extension of pipeline at Perumal Kovil Street Keelkuppam |
98637 |
Providing FHTC, and Extension of pipeline at Perumal Kovil Street Keelkuppam1 |
Completion of work |
-
latitude : 12.2555905,12.2555905
Longitude : 78.5341429,78.5341429
file name : Image_26062024131744011.png
|
2024-06-26 13:17:44.116056 |
21 |
66959901 |
Water Supply to villages |
1106030 |
Water Supply to villages1 |
Completion of work |
-
latitude : 12.2335219
Longitude : 78.5129118
file name : Image_30092024103723279.png
|
2024-09-30 10:37:23.368046 |
22 |
87745813 |
Creation of drainage channel for management of grey water |
165338 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 12.2335103
Longitude : 78.5129118
file name : Image_17082024114825972.png
|
2024-08-17 11:48:26.061717 |
23 |
87745794 |
Creation of drainage channel for management of grey water |
150000 |
Creation of drainage channel for management of grey water1 |
Completion of work |
-
latitude : 12.2335111
Longitude : 78.5129103
file name : Image_17082024114804536.png
|
2024-08-17 11:48:04.624778 |
24 |
94813326 |
Construction of new Piped Water Supply schemes |
153335 |
Construction of new Piped Water Supply schemes1 |
Roof laid |
-
latitude : 12.2339171
Longitude : 78.5130162
file name : Image_17082024120930868.png
|
2024-08-17 12:09:30.956149 |
25 |
94813326 |
Construction of new Piped Water Supply schemes |
153335 |
Construction of new Piped Water Supply schemes1 |
Plinth level |
-
latitude : 12.2335106
Longitude : 78.5129118
file name : Image_17082024120159664.png
|
2024-08-17 12:01:59.746633 |
26 |
94813326 |
Construction of new Piped Water Supply schemes |
153335 |
Construction of new Piped Water Supply schemes1 |
Completion of work |
-
latitude : 12.2335109
Longitude : 78.5129116
file name : Image_17082024115722817.png
|
2024-08-17 11:57:22.902225 |
27 |
87745701 |
Water Supply to villages |
203338 |
Water Supply to villages1 |
Completion of work |
-
latitude : 12.2339171
Longitude : 78.5130162
file name : Image_17082024141722680.png
|
2024-08-17 14:17:22.766314 |