1 |
51550082 |
Providing FHTC with EPL at Periyapalayampatti HO Piranthagam |
180000 |
Providing FHTC with EPL at Periyapalayampatti HO Piranthagam1 |
Roof laid |
-
latitude : 11.241725594736636,11.241779616102576
Longitude : 78.02303904667497,78.02303452044725
file name : Image_29102021113811486.png
|
2021-10-29 11:38:11.584375 |
2 |
51550117 |
Providing FHTC with EPL at Piranthagam HO Piranthagam |
157000 |
Providing FHTC with EPL at Piranthagam HO Piranthagam1 |
Roof laid |
-
latitude : 11.250400487333536,11.250391309149563
Longitude : 78.03255527280271,78.03258796222508
file name : Image_29102021113030868.png
|
2021-10-29 11:30:30.951277 |
3 |
51550039 |
Providing FHTC with EPL from Vellakkalpatti Existing borewell to Thammanaickenpatti Ar street OHT |
340000 |
Providing FHTC with EPL from Vellakkalpatti Existing borewell to Thammanaickenpatti Ar street OHT1 |
Roof laid |
-
latitude : 11.25382273,11.25377698
Longitude : 78.02896597,78.0289891
file name : Image_04012022171842846.png
|
2022-01-04 17:18:42.98543 |
4 |
41024800 |
Construction of Retaining wall at Puliamarattupatti Composit pit |
93000 |
Construction of Retaining wall at Puliamarattupatti Composit pit 1 |
Roof laid |
-
latitude : 11.2508872
Longitude : 78.0297537
file name : Image_22032022152718022.png
|
2022-03-22 15:27:18.126867 |
5 |
41027601 |
Upgradation of SWM Shed at Karattur Hamlet |
65000 |
Upgradation of SWM Shed at Karattur Hamlet1 |
Roof laid |
-
latitude : 11.23708593
Longitude : 78.03353245
file name : Image_20092022122508540.png
|
2022-09-20 12:25:08.619052 |
6 |
41028078 |
Upgradation of IWSC at Periyapalayam Patti |
167864 |
Upgradation of IWSC at Periyapalayam Patti1 |
Roof laid |
-
latitude : 11.24223995
Longitude : 78.02405833
file name : Image_28122022131527538.png
|
2022-12-28 13:15:27.567871 |
7 |
86898046 |
Water Supply to villages |
125000 |
Water Supply to villages1 |
Completion of work |
-
latitude : 11.2559815
Longitude : 78.02618036
file name : Image_11082023142934742.png
|
2023-08-11 14:29:34.808552 |
8 |
86898046 |
Water Supply to villages |
125000 |
Water Supply to villages1 |
Completion of work |
-
latitude : 11.2559815
Longitude : 78.02618036
file name : Image_11082023142947448.png
|
2023-08-11 14:29:47.513129 |
9 |
48018256 |
Construction of Women Sanitary Complex at Thammanaickenpatti |
162932 |
Construction of Women Sanitary Complex at Thammanaickenpatti1 |
Completion of work |
-
latitude : 11.24191703
Longitude : 78.02380819
file name : Image_19012024133207673.png
|
2024-01-19 13:32:07.737369 |
10 |
88791641 |
Construction of Community Sanitary Complex |
264930 |
Construction of Community Sanitary Complex1 |
Completion of work |
-
latitude : 11.23715038
Longitude : 78.0334528
file name : Image_19012024134102522.png
|
2024-01-19 13:41:02.582126 |
11 |
48018108 |
Construction of Women Sanitary Complex at Puliyamarathupatti |
162932 |
Construction of Women Sanitary Complex at Puliyamarathupatti1 |
Completion of work |
-
latitude : 11.23836831
Longitude : 78.03116401
file name : Image_21122023121928167.png
|
2023-12-21 12:19:28.231553 |
12 |
48018108 |
Construction of Women Sanitary Complex at Puliyamarathupatti |
162932 |
Construction of Women Sanitary Complex at Puliyamarathupatti1 |
Completion of work |
-
latitude : 11.23836831
Longitude : 78.03116401
file name : Image_21122023121936106.png
|
2023-12-21 12:19:36.179426 |
13 |
88791602 |
CC Pavement |
141916 |
CC Pavement1 |
Completion of work |
-
latitude : 11.24705863,11.24702024
Longitude : 78.03236086,78.03234859
file name : Image_21122023121931684.png
|
2023-12-21 12:19:31.755503 |
14 |
88791602 |
CC Pavement |
141916 |
CC Pavement1 |
Completion of work |
-
latitude : 11.24705863,11.24702024
Longitude : 78.03236086,78.03234859
file name : Image_21122023121924263.png
|
2023-12-21 12:19:24.340193 |
15 |
88791582 |
CC Pavement |
176000 |
CC Pavement 1 |
Completion of work |
-
latitude : 11.24809174,11.24809753
Longitude : 78.03191498,78.03192198
file name : Image_21122023121919110.png
|
2023-12-21 12:19:19.178867 |