1 |
34537120 |
Construction of gutter from GPS Compound |
63901 |
Construction of gutter from GPS Compound 1 |
Completion of work |
-
latitude : 15.46106108,15.46111769,15.46113389,15.46109048
Longitude : 73.87857109,73.87857541,73.87858225,73.87857691
file name : Image_04032021172846643.png
|
2021-03-04 17:28:46.733003 |
2 |
34548921 |
Providing and Erecting the Structural |
167327 |
Providing and Erecting the Structural 1 |
Completion of work |
-
latitude : 15.46096457
Longitude : 73.86461484
file name : Image_04032021172824008.png
|
2021-03-04 17:28:24.112541 |
3 |
34548921 |
Providing and Erecting the Structural |
167327 |
Providing and Erecting the Structural 1 |
Completion of work |
-
latitude : 15.46096457
Longitude : 73.86461484
file name : Image_04032021172922604.png
|
2021-03-04 17:29:22.702685 |
4 |
34550813 |
Providing and Fixing Shot Blast Inerlocking Pavers |
467863 |
Providing and Fixing Shot Blast Inerlocking Pavers1 |
Completion of work |
-
latitude : 15.46317593,15.46300135
Longitude : 73.88325553,73.88351665
file name : Image_03032021125729969.png
|
2021-03-03 12:57:30.067206 |
5 |
34556229 |
Providing and Fixing Chequered Tiles to Pathway near Laxman |
60140 |
Providing and Fixing Chequered Tiles to Pathway near Laxman 1 |
Completion of work |
-
latitude : 15.45045771,15.45059493
Longitude : 73.87272585,73.87263374
file name : Image_04032021172806561.png
|
2021-03-04 17:28:06.654747 |
6 |
34556229 |
Providing and Fixing Chequered Tiles to Pathway near Laxman |
60140 |
Providing and Fixing Chequered Tiles to Pathway near Laxman 1 |
Completion of work |
-
latitude : 15.45045771,15.45059493
Longitude : 73.87272585,73.87263374
file name : Image_04032021172909234.png
|
2021-03-04 17:29:09.32162 |
7 |
34530343 |
Asphalting of existing road from main road to Noor Ahmad house |
298286 |
Asphalting of existing road from main road to Noor Ahmad house 1 |
Completion of work |
-
latitude : 15.46378742,15.4638266
Longitude : 73.88361374,73.88352809
file name : Image_03032021125737553.png
|
2021-03-03 12:57:37.639598 |
8 |
34545512 |
Construction of Shed to Existing Ganesh |
150036 |
Construction of Shed to Existing Ganesh 1 |
Completion of work |
-
latitude : 15.4639476
Longitude : 73.88517619
file name : Image_03032021125741165.png
|
2021-03-03 12:57:41.265714 |
9 |
34539704 |
Construction of Roadside Protection Wall near Pump |
495450 |
Construction of Roadside Protection Wall near Pump 1 |
Completion of work |
-
latitude : 15.47634052
Longitude : 73.88956756
file name : Image_03032021125751128.png
|
2021-03-03 12:57:51.233387 |
10 |
47217300 |
Re comstruction of Collapsed oneside of existing drain cum protection wall to existing road near |
181792 |
Re comstruction of Collapsed oneside of existing drain cum protection wall to existing road near 1 |
Completion of work |
-
latitude : 15.45826934,15.4582101
Longitude : 73.86217532,73.86198107
file name : Image_04032021172837750.png
|
2021-03-04 17:28:37.853789 |
11 |
47217300 |
Re comstruction of Collapsed oneside of existing drain cum protection wall to existing road near |
181792 |
Re comstruction of Collapsed oneside of existing drain cum protection wall to existing road near 1 |
Completion of work |
-
latitude : 15.45826934,15.4582101
Longitude : 73.86217532,73.86198107
file name : Image_04032021172949484.png
|
2021-03-04 17:29:49.581203 |
12 |
34555692 |
Providing and Fixing Chequered Tiles to existing Steps and Pathway near Joana |
89209 |
Providing and Fixing Chequered Tiles to existing Steps and Pathway near Joana1 |
Completion of work |
-
latitude : 15.46065161,15.46065123
Longitude : 73.88035801,73.88035908
file name : Image_04032021145428223.png
|
2021-03-04 14:54:28.333512 |
13 |
34557759 |
Repair to existing Ganesh Visarjan Platform at Wadwad |
51155 |
Repair to existing Ganesh Visarjan Platform at Wadwad 1 |
Completion of work |
-
latitude : 15.45122618
Longitude : 73.87362605
file name : Image_04032021172810794.png
|
2021-03-04 17:28:10.887548 |
14 |
34557759 |
Repair to existing Ganesh Visarjan Platform at Wadwad |
51155 |
Repair to existing Ganesh Visarjan Platform at Wadwad 1 |
Completion of work |
-
latitude : 15.45122618
Longitude : 73.87362605
file name : Image_04032021172912385.png
|
2021-03-04 17:29:12.48023 |
15 |
47232351 |
Repair to the existing crematorium in ward No.6 |
373511 |
Repair to the existing crematorium in ward No.61 |
Completion of work |
-
latitude : 15.45171786
Longitude : 73.87338094
file name : Image_04032021172815708.png
|
2021-03-04 17:28:15.827692 |
16 |
47232351 |
Repair to the existing crematorium in ward No.6 |
373511 |
Repair to the existing crematorium in ward No.61 |
Completion of work |
-
latitude : 15.45171786
Longitude : 73.87338094
file name : Image_04032021172915908.png
|
2021-03-04 17:29:15.989468 |
17 |
47218386 |
Reconstruction of existing protection wall cum pathway near shagun Kankonkar house at Detto , nauxim |
498210 |
Reconstruction of existing protection wall cum pathway near shagun Kankonkar house at Detto , nauxim1 |
Completion of work |
-
latitude : 15.46214926
Longitude : 73.87479691
file name : Image_04032021172853805.png
|
2021-03-04 17:28:53.888684 |
18 |
47218386 |
Reconstruction of existing protection wall cum pathway near shagun Kankonkar house at Detto , nauxim |
498210 |
Reconstruction of existing protection wall cum pathway near shagun Kankonkar house at Detto , nauxim1 |
Completion of work |
-
latitude : 15.45238544
Longitude : 73.84571668
file name : Image_04032021172831128.png
|
2021-03-04 17:28:31.2331 |
19 |
47218386 |
Reconstruction of existing protection wall cum pathway near shagun Kankonkar house at Detto , nauxim |
498210 |
Reconstruction of existing protection wall cum pathway near shagun Kankonkar house at Detto , nauxim1 |
Completion of work |
-
latitude : 15.45238544
Longitude : 73.84571668
file name : Image_04032021172943004.png
|
2021-03-04 17:29:43.101562 |
20 |
47216794 |
Re Construction of protection wall from Sharma house to Ramakant Talwar house at Old bambolim |
457155 |
Re Construction of protection wall from Sharma house to Ramakant Talwar house at Old bambolim 1 |
Completion of work |
-
latitude : 15.45817811
Longitude : 73.86197617
file name : Image_04032021172841739.png
|
2021-03-04 17:28:41.842421 |
21 |
47216794 |
Re Construction of protection wall from Sharma house to Ramakant Talwar house at Old bambolim |
457155 |
Re Construction of protection wall from Sharma house to Ramakant Talwar house at Old bambolim 1 |
Completion of work |
-
latitude : 15.45817811
Longitude : 73.86197617
file name : Image_04032021172959473.png
|
2021-03-04 17:29:59.578258 |
22 |
47217549 |
Reconstruction of existing drain from Gopal Naik house to Ganesham Halankar house and shamba sawant |
240740 |
Reconstruction of existing drain from Gopal Naik house to Ganesham Halankar house and shamba sawant 1 |
Completion of work |
-
latitude : 15.45023937,15.45009996
Longitude : 73.87129942,73.87163115
file name : Image_04032021172803068.png
|
2021-03-04 17:28:03.164507 |
23 |
47217549 |
Reconstruction of existing drain from Gopal Naik house to Ganesham Halankar house and shamba sawant |
240740 |
Reconstruction of existing drain from Gopal Naik house to Ganesham Halankar house and shamba sawant 1 |
Completion of work |
-
latitude : 15.45023937,15.45009996
Longitude : 73.87129942,73.87163115
file name : Image_04032021172905986.png
|
2021-03-04 17:29:06.089075 |
24 |
47217679 |
Recopnstruction of existing drain near rama Shirodkar house at Canturulim |
452483 |
Recopnstruction of existing drain near rama Shirodkar house at Canturulim1 |
Completion of work |
-
latitude : 15.46215492,15.46238327
Longitude : 73.87481619,73.87490091
file name : Image_05032021103208632.png
|
2021-03-05 10:32:08.740938 |
25 |
47216916 |
Construction of Roadside drain from fatima Pinto house to laura D Souza |
456359 |
Construction of Roadside drain from fatima Pinto house to laura D Souza 1 |
Completion of work |
-
latitude : 15.45805604,15.45758596
Longitude : 73.86117452,73.86078694
file name : Image_04032021172834537.png
|
2021-03-04 17:28:34.637069 |
26 |
47216916 |
Construction of Roadside drain from fatima Pinto house to laura D Souza |
456359 |
Construction of Roadside drain from fatima Pinto house to laura D Souza 1 |
Completion of work |
-
latitude : 15.45805604,15.45758596
Longitude : 73.86117452,73.86078694
file name : Image_04032021172946287.png
|
2021-03-04 17:29:46.382107 |
27 |
47217432 |
Reconstruction of Exzisiting drain and Cross drain near rohidas Kundaikar house to |
499175 |
Reconstruction of Exzisiting drain and Cross drain near rohidas Kundaikar house to 1 |
Completion of work |
-
latitude : 15.46070178,15.46074949
Longitude : 73.87815324,73.87828944
file name : Image_04032021172850088.png
|
2021-03-04 17:28:50.193588 |
28 |
47218537 |
Reconstruction of existing roadside protection wall from Sachin Betekar house to Anthony |
70000 |
Reconstruction of existing roadside protection wall from Sachin Betekar house to Anthony 1 |
Completion of work |
-
latitude : 15.4614709
Longitude : 73.87677788
file name : Image_03032021125759801.png
|
2021-03-03 12:57:59.904225 |
29 |
34556879 |
Renovation to Existing Ganesh Visarjan Platform |
345508 |
Renovation to Existing Ganesh Visarjan Platform 1 |
Completion of work |
-
latitude : 15.45159158
Longitude : 73.84299102
file name : Image_04032021172827223.png
|
2021-03-04 17:28:27.327869 |
30 |
34556879 |
Renovation to Existing Ganesh Visarjan Platform |
345508 |
Renovation to Existing Ganesh Visarjan Platform 1 |
Completion of work |
-
latitude : 15.45159158
Longitude : 73.84299102
file name : Image_04032021172937218.png
|
2021-03-04 17:29:37.318324 |
31 |
34538851 |
Construction of Roadside Protection Wall near Umesh |
155479 |
Construction of Roadside Protection Wall near Umesh 1 |
Completion of work |
-
latitude : 15.4772698
Longitude : 73.89111967
file name : Image_04032021145421868.png
|
2021-03-04 14:54:21.975375 |
32 |
47217065 |
providing band fixing of Interlocking shot blast pavers to pathway from Existing pathway nr. nagesh |
365883 |
providing band fixing of Interlocking shot blast pavers to pathway from Existing pathway nr. nagesh 1 |
Completion of work |
-
latitude : 15.45343819,15.45312185
Longitude : 73.87152483,73.87212201
file name : Image_04032021172819165.png
|
2021-03-04 17:28:19.258522 |
33 |
47217065 |
providing band fixing of Interlocking shot blast pavers to pathway from Existing pathway nr. nagesh |
365883 |
providing band fixing of Interlocking shot blast pavers to pathway from Existing pathway nr. nagesh 1 |
Completion of work |
-
latitude : 15.45343819,15.45312185
Longitude : 73.87152483,73.87212201
file name : Image_04032021172919314.png
|
2021-03-04 17:29:19.404949 |
34 |
34541552 |
Construction of Protection Wall |
461645 |
Construction of Protection Wall 1 |
Completion of work |
-
latitude : 15.47061292
Longitude : 73.89976088
file name : Image_04032021145425102.png
|
2021-03-04 14:54:25.202435 |
35 |
34553540 |
Providing and Fixing Shot Blast Inerlocking Pavers from Road to Mohan Kuttikar |
186786 |
Providing and Fixing Shot Blast Inerlocking Pavers from Road to Mohan Kuttikar1 |
Completion of work |
-
latitude : 15.460952,15.46119433
Longitude : 73.87856861,73.87858651
file name : Image_09032021155222604.png
|
2021-03-09 15:52:22.731628 |
36 |
34553540 |
Providing and Fixing Shot Blast Inerlocking Pavers from Road to Mohan Kuttikar |
186786 |
Providing and Fixing Shot Blast Inerlocking Pavers from Road to Mohan Kuttikar1 |
Completion of work |
-
latitude : 15.46078776,15.46082616
Longitude : 73.87885023,73.87888229
file name : Image_03032021125754697.png
|
2021-03-03 12:57:54.799944 |
37 |
34555115 |
Providing and Fixing Shot Blast Inerlocking Pavers for Road side Shoulder |
819621 |
Providing and Fixing Shot Blast Inerlocking Pavers for Road side Shoulder1 |
Completion of work |
-
latitude : 15.4609047,15.4609048
Longitude : 73.8781722,73.8781687
file name : Image_12042021123719052.png
|
2021-04-12 12:37:19.155755 |
38 |
47232673 |
Construction to shed to the existing ganesh Visarjan Platform at Mole bhat in ward No, 7 |
693318 |
Construction to shed to the existing ganesh Visarjan Platform at Mole bhat in ward No, 71 |
Completion of work |
-
latitude : 15.45302842
Longitude : 73.87284901
file name : Image_12042021123730030.png
|
2021-04-12 12:37:30.121635 |
39 |
47294895 |
Reconstruction of existing drain from Oscar D Costa house to opp. Antush Monteiro house at bambolim |
999256 |
Reconstruction of existing drain from Oscar D Costa house to opp. Antush Monteiro house at bambolim 1 |
Completion of work |
-
latitude : 15.46052746,15.46081082
Longitude : 73.85946177,73.85983755
file name : Image_12042021123734047.png
|
2021-04-12 12:37:34.150702 |
40 |
34538328 |
Construction of Roadside Protection Wall near Pond |
498173 |
Construction of Roadside Protection Wall near Pond 1 |
Completion of work |
-
latitude : 15.47375958
Longitude : 73.88779457
file name : Image_12042021142355763.png
|
2021-04-12 14:23:55.857726 |
41 |
34538328 |
Construction of Roadside Protection Wall near Pond |
498173 |
Construction of Roadside Protection Wall near Pond 1 |
Completion of work |
-
latitude : 15.4738074
Longitude : 73.88777593
file name : Image_12042021131046117.png
|
2021-04-12 13:10:46.474759 |
42 |
34538328 |
Construction of Roadside Protection Wall near Pond |
498173 |
Construction of Roadside Protection Wall near Pond 1 |
Completion of work |
-
latitude : 15.47376852
Longitude : 73.88774669
file name : Image_03032021125744383.png
|
2021-03-03 12:57:44.486904 |
43 |
47217191 |
Providing and erecting structure steel Thrie beam crash barrier on existing retaining wall |
322271 |
Providing and erecting structure steel Thrie beam crash barrier on existing retaining wall 1 |
Completion of work |
-
latitude : 15.45255431
Longitude : 73.8711612
file name : Image_04032021172759738.png
|
2021-03-04 17:27:59.829399 |
44 |
45904181 |
Solar Electricity genration for Village Panchayat |
416050 |
Solar Electricity genration for Village Panchayat1 |
Plinth level |
-
latitude : 15.460968
Longitude : 73.8781235
file name : Image_16082021104157076.png
|
2021-08-16 10:41:57.182564 |
45 |
56383674 |
Reconstruction of retaining wall from Shrikant Chari house to Benny D'Silva house at Canturlim Curca |
990993 |
Reconstruction of retaining wall from Shrikant Chari house to Benny D'Silva house at Canturlim Curca1 |
Roof laid |
-
latitude : 15.4612175
Longitude : 73.8793317
file name : Image_02012023121911568.png
|
2023-01-02 12:19:11.668999 |
46 |
56383739 |
Reconstruction of retaining wall from Sonu GAuns house to Deu Gauns cow shed at Bambolim |
524223 |
Reconstruction of retaining wall from Sonu GAuns house to Deu Gauns cow shed at Bambolim1 |
Roof laid |
-
latitude : 15.45617334
Longitude : 73.85954563
file name : Image_03022023163420802.png
|
2023-02-03 16:34:20.921242 |
47 |
56383864 |
Reconstruction of retaining wall from Albert D'costa house to Antush Monteiro house at Bambolim |
524114 |
Reconstruction of retaining wall from Albert D'costa house to Antush Monteiro house at Bambolim1 |
Roof laid |
-
latitude : 15.46069831
Longitude : 73.85973925
file name : Image_03022023160541914.png
|
2023-02-03 16:05:42.012839 |