1 |
66770055 |
cc road sah nali nirman karya |
279000 |
cc road sah nali nirman karya 1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2022/Image_20042023131321914.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2022/Image_20042023131321914.png)
latitude : 23.3037324,23.3037233
Longitude : 78.4346172,78.4346179
file name : Image_20042023131321914.png
|
2023-04-20 13:13:22.072454 |
2 |
80077622 |
Construction of roads |
229000 |
Construction of roads1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2023/Image_10072023142230990.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2023/Image_10072023142230990.png)
latitude : 23.3037077,23.3037087
Longitude : 78.4346164,78.4346161
file name : Image_10072023142230990.png
|
2023-07-10 14:22:31.085584 |
3 |
80077622 |
Construction of roads |
229000 |
Construction of roads1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2023/Image_05102023220214913.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2023/Image_05102023220214913.png)
latitude : 23.3037292,23.3037292
Longitude : 78.4345934,78.434594
file name : Image_05102023220214913.png
|
2023-10-05 22:02:15.004036 |
4 |
101126091 |
Construction of new Piped Water Supply schemes |
25000 |
moter pump sandharan karya |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_23062024130850661.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_23062024130850661.png)
latitude : 23.3034676
Longitude : 78.4349106
file name : Image_23062024130850661.png
|
2024-06-23 13:08:50.776056 |
5 |
101126091 |
Construction of new Piped Water Supply schemes |
25000 |
moter pump sandharan karya |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_23062024130743987.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_23062024130743987.png)
latitude : 23.303466
Longitude : 78.4349258
file name : Image_23062024130743987.png
|
2024-06-23 13:07:44.101752 |
6 |
101126091 |
Construction of new Piped Water Supply schemes |
25000 |
moter pump sandharan karya |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_12062024194817475.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_12062024194817475.png)
latitude : 23.3037145
Longitude : 78.4346316
file name : Image_12062024194817475.png
|
2024-06-12 19:48:17.658412 |
7 |
101126251 |
Construction of new Piped Water Supply schemes |
25000 |
Construction of new Piped Water Supply schemes1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_12062024174214372.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_12062024174214372.png)
latitude : 23.3035555
Longitude : 78.4348309
file name : Image_12062024174214372.png
|
2024-06-12 17:42:14.467312 |
8 |
101126251 |
Construction of new Piped Water Supply schemes |
25000 |
Construction of new Piped Water Supply schemes1 |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_12062024174313036.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_12062024174313036.png)
latitude : 23.3034709
Longitude : 78.4349242
file name : Image_12062024174313036.png
|
2024-06-12 17:43:13.153652 |
9 |
101127822 |
Construction of new Piped Water Supply schemes |
72908 |
karyalay anya vyay |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_12062024190533104.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/23/2024/Image_12062024190533104.png)
latitude : 23.303688
Longitude : 78.434648
file name : Image_12062024190533104.png
|
2024-06-12 19:05:33.185031 |