1 |
62718969 |
Construction of Road |
410800 |
Hardan H/o to Gadaram H/o Road Nirman |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/6/2022/Image_11052022124246572.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/6/2022/Image_11052022124246572.png)
latitude : 27.81864316,27.81864307,27.81864307
Longitude : 76.19313072,76.19313097,76.19313096
file name : Image_11052022124246572.png
|
2022-05-11 12:42:46.659371 |
2 |
80977644 |
Construction of roads |
160000 |
NH 148B to Ramkuwar SO Kanaram H/o Road Nirman |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_06102023140100119.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_06102023140100119.png)
latitude : 27.8063559,27.80635936
Longitude : 76.18538619,76.18538626
file name : Image_06102023140100119.png
|
2023-10-06 14:01:00.208315 |
3 |
80977644 |
Construction of roads |
160000 |
NH 148B to Ramkuwar SO Kanaram H/o Road Nirman |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_06102023135637975.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_06102023135637975.png)
latitude : 27.80637855,27.80636787
Longitude : 76.18539646,76.1853947
file name : Image_06102023135637975.png
|
2023-10-06 13:56:38.096943 |
4 |
80973641 |
Drainage Construction |
399100 |
RCC Pipe Line, Gi Pipe Line, Drain Repair and Water Tanki Nirman |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_29032024122126514.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_29032024122126514.png)
latitude : 27.80516836
Longitude : 76.18623989
file name : Image_29032024122126514.png
|
2024-03-29 12:21:26.602837 |
5 |
80973641 |
Drainage Construction |
399100 |
RCC Pipe Line, Gi Pipe Line, Drain Repair and Water Tanki Nirman |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_19032024113921648.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_19032024113921648.png)
latitude : 27.80762421
Longitude : 76.18867126
file name : Image_19032024113921648.png
|
2024-03-19 11:39:21.775802 |
6 |
80952632 |
Greywater management system |
130000 |
RCC Pipe line laying & Hodi Nirman |
Plinth level |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_26062024133652396.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_26062024133652396.png)
latitude : 27.80569256
Longitude : 76.18626115
file name : Image_26062024133652396.png
|
2024-06-26 13:36:52.487327 |
7 |
80952632 |
Greywater management system |
130000 |
RCC Pipe line laying & Hodi Nirman |
Completion of work |
-
![/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_26062024133340570.png](getMactionPhoto.do?imgId=/opt/actionsoft/attachment/mActionSoft/photoupload/6/2023/Image_26062024133340570.png)
latitude : 27.80570041
Longitude : 76.18626549
file name : Image_26062024133340570.png
|
2024-06-26 13:33:40.666958 |