Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 67448957 | Construction of Community Sanitary Complex | Sanitation | 98100 | XV Finance Commission | Tied Grant | 2023-04-01 00:00:00 |
2 | 67449033 | Construction of Community Sanitary Complex | Sanitation | 98100 | XV Finance Commission | Tied Grant | 2023-04-01 00:00:00 |
3 | 67676453 | Retrofitting of single pit toilets to twin pit toilets or connecting septic tanks with soak pits | Sanitation | 1068245 | XV Finance Commission | Tied Grant | 2024-02-01 00:00:00 |
4 | 86041314 | 2nos of Volleyball Playground | Administrative & Technical Support | 139000 | XV Finance Commission | Basic Grant (untied) | 2023-07-08 00:00:00 |