S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 47688395 | Water Pipe Line | Drinking water | 363304 | XV Finance Commission | Tied Grant | 2023-03-30 00:00:00 |
2 | 47688861 | disposale of sullage water | Sanitation | 363304 | XV Finance Commission | Tied Grant | 2023-06-14 00:00:00 |
3 | 47689808 | street& Drain | Roads | 208600 | Own Funds | Own Funds | 2023-03-29 00:00:00 |