Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 46613853 | Motor Pump Khareed | Drinking water | 200000 | XV Finance Commission | Tied Grant | 2022-12-13 00:00:00 |
2 | 85527966 | Cost of preparation of project reports and technical plans for the sanitation projects. | Sanitation | 50000 | Own Funds | Own Funds | 2023-07-02 00:00:00 |
3 | 85527966 | Cost of preparation of project reports and technical plans for the sanitation projects. | Sanitation | 50000 | XV Finance Commission | Tied Grant | 2023-07-02 00:00:00 |
4 | 87576203 | Creation of drainage channel for management of grey water | Sanitation | 150000 | XV Finance Commission | Tied Grant | 2023-09-20 00:00:00 |
5 | 87765933 | Greywater management system | Sanitation | 472000 | Own Funds | Own Funds | 2023-10-04 00:00:00 |
6 | 87765933 | Greywater management system | Sanitation | 472000 | XV Finance Commission | Tied Grant | 2023-10-04 00:00:00 |
7 | 106694924 | Greywater management system | Sanitation | 200000 | Own Funds | Own Funds | 2024-06-16 00:00:00 |
8 | 106694924 | Greywater management system | Sanitation | 200000 | XV Finance Commission | Tied Grant | 2024-06-16 00:00:00 |