S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 66767724 | UNTIED(GENERAL) | Roads | 79648 | XV Finance Commission | Basic Grant (untied) | 2023-03-06 00:00:00 |
2 | 66767750 | UNTIED(SC) | Roads | 26270 | XV Finance Commission | Basic Grant (untied) | 2023-03-06 00:00:00 |
3 | 66767763 | Creation of drainage channel for management of grey water | Sanitation | 58757 | XV Finance Commission | Tied Grant | 2023-01-04 00:00:00 |
4 | 66767779 | Creation of drainage channel for management of grey water | Sanitation | 19693 | XV Finance Commission | Tied Grant | 2023-01-04 00:00:00 |
5 | 66767788 | Water Supply to villages | Drinking water | 58757 | XV Finance Commission | Tied Grant | 2023-04-01 00:00:00 |
6 | 66767795 | Water Supply to villages | Drinking water | 19693 | XV Finance Commission | Tied Grant | 2023-04-01 00:00:00 |