Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 45795935 | Sanitation | Sanitation | 84773 | XV Finance Commission | Tied Grant | 2023-11-13 00:00:00 |
2 | 45796071 | Sanitation | Sanitation | 50000 | XV Finance Commission | Tied Grant | 2023-06-08 00:00:00 |
3 | 45796185 | Sanitation | Sanitation | 165000 | Own Funds | Own Funds | 2023-05-03 00:00:00 |
4 | 45796434 | Drinking water | Drinking water | 144227 | XV Finance Commission | Tied Grant | 2023-06-05 00:00:00 |
5 | 45797312 | Rural Electrificition | Rural electrification | 174546 | XV Finance Commission | Basic Grant (untied) | 2023-04-09 00:00:00 |
6 | 45797412 | Road work | Roads | 215000 | XV Finance Commission | Basic Grant (untied) | 2023-08-12 00:00:00 |