Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 46420204 | Construction of Under ground drainages (Side Drain) | Sanitation | 170000 | XV Finance Commission | Tied Grant | 2023-10-27 00:00:00 |
2 | 46420345 | PWS Motor Repairs (Single Phase & 5HP) | Drinking water | 80000 | XV Finance Commission | Tied Grant | 2022-07-01 00:00:00 |
3 | 46420436 | Purchase of PWS motors (Single Phase & 5HP) | Drinking water | 80000 | XV Finance Commission | Tied Grant | 2023-11-01 00:00:00 |
4 | 46420695 | Administration Expenditure | Administrative & Technical Support | 47996 | Own Funds | Own Funds | 2023-01-01 00:00:00 |
5 | 46420793 | Construction of New CC Roads | Roads | 250000 | XV Finance Commission | Basic Grant (untied) | 2022-05-01 00:00:00 |
6 | 46420838 | Purchase of LED Bulbs | Rural electrification | 70000 | XV Finance Commission | Basic Grant (untied) | 2022-05-01 00:00:00 |