Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 47845164 | DEEPENING BOREWELL | Drinking water | 1300000 | XV Finance Commission | Tied Grant | 2023-05-23 00:00:00 |
2 | 47845741 | DRAINAGE | Roads | 1400000 | XV Finance Commission | Basic Grant (untied) | 2023-12-29 00:00:00 |
3 | 47846155 | DEEPENING BOREWELL | Drinking water | 1220000 | XV Finance Commission | Tied Grant | 2023-05-16 00:00:00 |
4 | 48425660 | Drainage | Sanitation | 1678000 | XV Finance Commission | Basic Grant (untied) | 2023-01-25 00:00:00 |
5 | 48425770 | Water supply | Drinking water | 1850000 | XV Finance Commission | Tied Grant | 2023-01-25 00:00:00 |