S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 66972230 | Water Supply to villages | Drinking water | 659380 | XV Finance Commission | Tied Grant | 2023-02-17 00:00:00 |
2 | 66972285 | Creation of Shed for segregation and processing of wet and dry waste | Sanitation | 114000 | XV Finance Commission | Tied Grant | 2022-10-19 00:00:00 |
3 | 66972471 | Creation of community compost pits for a group of Households | Sanitation | 116000 | XV Finance Commission | Tied Grant | 2022-10-19 00:00:00 |
4 | 66972512 | Creation of community compost pits for a group of Households | Sanitation | 82500 | XV Finance Commission | Tied Grant | 2022-10-19 00:00:00 |
5 | 66972567 | Creation of community compost pits for a group of Households | Sanitation | 15500 | XV Finance Commission | Tied Grant | 2022-10-19 00:00:00 |
6 | 66972616 | Creation of community compost pits for a group of Households | Sanitation | 15699 | XV Finance Commission | Tied Grant | 2022-10-19 00:00:00 |
7 | 66972788 | Water Supply to villages | Drinking water | 494545 | XV Finance Commission | Basic Grant (untied) | 2023-02-17 00:00:00 |
8 | 66972838 | Water Supply to villages | Drinking water | 300000 | XV Finance Commission | Basic Grant (untied) | 2023-02-17 00:00:00 |
9 | 66973285 | Construction of Community Sanitary Complex | Sanitation | 252210 | XV Finance Commission | Tied Grant | 2021-12-14 00:00:00 |