Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 64497927 | PROVIDING PUMP ROOM AT COLONY TIED | Drinking water | 100000 | XV Finance Commission | Tied Grant | 2021-10-12 00:00:00 |
2 | 64497961 | PROVIDING PIPELINE AT COLONY TIED | Drinking water | 146000 | XV Finance Commission | Tied Grant | 2023-11-06 00:00:00 |
3 | 64497991 | PROVIDING PIPELINE AT MATHANATHUR COLONY TIED | Drinking water | 200000 | XV Finance Commission | Tied Grant | 2022-11-29 00:00:00 |
4 | 64498527 | PROVIDING DRAINAGE TIED | Sanitation | 467393 | XV Finance Commission | Tied Grant | 2023-05-10 00:00:00 |
5 | 64498551 | PROVIDING PIPELINE TIED | Drinking water | 65957 | XV Finance Commission | Tied Grant | 2023-11-01 00:00:00 |
6 | 64499491 | PROVIDING PIPELINE UNTIED | Drinking water | 755106 | XV Finance Commission | Basic Grant (untied) | 2023-10-24 00:00:00 |