S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 64016320 | uniform | Sanitation | 11220 | XV Finance Commission | Tied Grant | 2022-07-06 00:00:00 |
2 | 64016329 | implements | Sanitation | 27200 | XV Finance Commission | Tied Grant | 2022-07-06 00:00:00 |
3 | 64016409 | Remaining amount of vermi compost | Sanitation | 55000 | XV Finance Commission | Tied Grant | 2022-10-04 00:00:00 |
4 | 64016484 | IWSC REPAIR WORK | Sanitation | 165437 | XV Finance Commission | Tied Grant | 2023-05-03 00:00:00 |
5 | 64016581 | Main pipeline at erumbur koodum karai OHT tank | Drinking water | 200000 | XV Finance Commission | Tied Grant | 2022-08-02 00:00:00 |
6 | 64016612 | providing 5 HP motor at koodu karai open well | Drinking water | 92858 | XV Finance Commission | Tied Grant | 2022-08-02 00:00:00 |
7 | 64016640 | culvert at thozhillalar st | Drinking water | 190478 | XV Finance Commission | Basic Grant (untied) | 2022-07-05 00:00:00 |
8 | 64016774 | culvert at new colony nadaga madai opp | Roads | 200000 | XV Finance Commission | Basic Grant (untied) | 2022-08-03 00:00:00 |