Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 64018019 | Providing new pipeline extension in periya eari to ADC | Drinking water | 352473 | XV Finance Commission | Tied Grant | 2022-06-16 00:00:00 |
2 | 64018106 | Construction of Segregation shed | Sanitation | 35000 | XV Finance Commission | Tied Grant | 2022-04-13 00:00:00 |
3 | 64018140 | Construction of compost pit | Sanitation | 20000 | XV Finance Commission | Tied Grant | 2022-04-21 00:00:00 |
4 | 64018326 | Providing tricycle | Sanitation | 20000 | XV Finance Commission | Tied Grant | 2022-03-31 00:00:00 |
5 | 64018363 | Providing of Uniform | Sanitation | 14960 | XV Finance Commission | Tied Grant | 2022-03-15 00:00:00 |
6 | 64018424 | Providing Implements | Sanitation | 27200 | XV Finance Commission | Tied Grant | 2022-03-10 00:00:00 |
7 | 64018465 | Construction of Vertical Soak pit | Sanitation | 140000 | XV Finance Commission | Tied Grant | 2022-04-21 00:00:00 |
8 | 64018602 | Construction of Drainage | Sanitation | 69964 | XV Finance Commission | Basic Grant (untied) | 2022-04-14 00:00:00 |
9 | 64018602 | Construction of Drainage | Sanitation | 40313 | XV Finance Commission | Tied Grant | 2022-04-14 00:00:00 |
10 | 64018777 | Construction of Culvert in SLWBM Road | Roads | 200000 | XV Finance Commission | Basic Grant (untied) | 2022-06-06 00:00:00 |
11 | 64018952 | CONSTRUCTION OF THRESHING FLOOR NEAR AYYANAR KOIL | Agriculture | 200000 | XV Finance Commission | Basic Grant (untied) | 2022-06-06 00:00:00 |
12 | 64179981 | CONSTRUCTION OF VERMI COMPOST | Sanitation | 55000 | XV Finance Commission | Tied Grant | 2022-08-09 00:00:00 |