Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 64162228 | Providing pipeline in kalaignar nagar | Drinking water | 128949 | XV Finance Commission | Tied Grant | 2022-05-31 00:00:00 |
2 | 64162249 | Providing Motor and Pipeline in Nemeliyapuram | Drinking water | 100000 | XV Finance Commission | Tied Grant | 2022-05-31 00:00:00 |
3 | 64162264 | Construction of vermi compost | Sanitation | 55000 | XV Finance Commission | Tied Grant | 2022-04-27 00:00:00 |
4 | 64162276 | Construction of Segregation shed | Sanitation | 35000 | XV Finance Commission | Tied Grant | 2022-02-15 00:00:00 |
5 | 64162307 | Providing tricycle | Sanitation | 20000 | XV Finance Commission | Tied Grant | 2022-03-17 00:00:00 |
6 | 64162360 | Construction of Horizontal Soak pit | Sanitation | 60731 | XV Finance Commission | Basic Grant (untied) | 2022-06-10 00:00:00 |
7 | 64162360 | Construction of Horizontal Soak pit | Sanitation | 69268 | XV Finance Commission | Tied Grant | 2022-06-10 00:00:00 |
8 | 64162383 | Providing Uniform | Sanitation | 7480 | XV Finance Commission | Tied Grant | 2022-02-24 00:00:00 |
9 | 64162409 | Providing of Implements | Sanitation | 27200 | XV Finance Commission | Tied Grant | 2022-02-24 00:00:00 |
10 | 64162438 | Construction of Threshing floor | Agriculture | 244534 | XV Finance Commission | Basic Grant (untied) | 2022-05-31 00:00:00 |