Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 63988954 | Construction of 30000 lit OHT in new colony at irumaram panchayat | Drinking water | 67320 | XV Finance Commission | Basic Grant (untied) | 2022-02-02 00:00:00 |
2 | 63988954 | Construction of 30000 lit OHT in new colony at irumaram panchayat | Drinking water | 238629 | XV Finance Commission | Tied Grant | 2022-02-02 00:00:00 |
3 | 63988972 | Uniform & Implements | Sanitation | 34680 | XV Finance Commission | Tied Grant | 2022-05-04 00:00:00 |
4 | 63988985 | Vermi compost pit | Sanitation | 35000 | XV Finance Commission | Tied Grant | 2022-03-28 00:00:00 |
5 | 63988991 | Segregation shed | Sanitation | 34000 | XV Finance Commission | Tied Grant | 2022-03-28 00:00:00 |
6 | 63989004 | Compost pit | Sanitation | 35000 | XV Finance Commission | Tied Grant | 2022-03-28 00:00:00 |
7 | 63989015 | Tricycle | Sanitation | 20000 | XV Finance Commission | Tied Grant | 2022-08-08 00:00:00 |
8 | 63989038 | Creation of Individual soak pit for onsite GWM any when community soak pit are not feasible | Sanitation | 75600 | XV Finance Commission | Tied Grant | 2022-06-01 00:00:00 |
9 | 63989064 | Providing paver Block to ST kudi irupu in irumaram panchayat 58m | Roads | 250852 | XV Finance Commission | Basic Grant (untied) | 2022-06-06 00:00:00 |