Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 69605035 | Purchase of equipment (including safety equipment) for waste management | Sanitation | 18000 | XV Finance Commission | Tied Grant | 2023-01-26 00:00:00 |
2 | 69608984 | Purchase of equipment (including safety equipment) for waste management | Sanitation | 3000 | XV Finance Commission | Tied Grant | 2023-02-07 00:00:00 |
3 | 69616217 | Operation & maintenance of community compost pits | Sanitation | 80000 | XV Finance Commission | Tied Grant | 2024-02-06 00:00:00 |
4 | 69619163 | Operation & maintenance of composting shed/center | Sanitation | 40000 | XV Finance Commission | Tied Grant | 2024-02-14 00:00:00 |