Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 68582093 | Purchase of equipment (including safety equipment) for waste management | Sanitation | 18000 | XV Finance Commission | Tied Grant | 2023-01-23 00:00:00 |
2 | 68582192 | Purchase of equipment (including safety equipment) for waste management | Sanitation | 3000 | XV Finance Commission | Tied Grant | 2023-01-23 00:00:00 |
3 | 68583246 | Operation & maintenance of community compost pits | Sanitation | 10800 | XV Finance Commission | Tied Grant | 2023-09-13 00:00:00 |
4 | 68583345 | Providing new CC Paver Block Main Road Cross Street | Roads | 265898 | XV Finance Commission | Basic Grant (untied) | 2023-11-07 00:00:00 |