Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 65221697 | Providing piped water supply to public institutions | Drinking water | 374970 | XV Finance Commission | Tied Grant | 2022-03-15 00:00:00 |
2 | 65221720 | Creation of community compost pits for a group of Households | Sanitation | 250000 | XV Finance Commission | Tied Grant | 2022-11-16 00:00:00 |
3 | 65221741 | Construction of toilets in public institutions | Sanitation | 18000 | XV Finance Commission | Tied Grant | 2023-01-24 00:00:00 |
4 | 65221775 | Construction of Community Sanitary Complex | Sanitation | 6000 | XV Finance Commission | Tied Grant | 2023-01-24 00:00:00 |
5 | 65221795 | Construction of toilets in public institutions | Sanitation | 80000 | XV Finance Commission | Tied Grant | 2023-04-11 00:00:00 |
6 | 65221880 | Providing Interlocking Paver Block @ thotti colony | Roads | 199960 | XV Finance Commission | Basic Grant (untied) | 2022-09-07 00:00:00 |