S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 49995894 | 15th fc tied | Drinking water | 161819 | XV Finance Commission | Tied Grant | 2023-01-11 00:00:00 |
2 | 49995974 | 15th fc tied | Sanitation | 161819 | XV Finance Commission | Tied Grant | 2023-01-11 00:00:00 |
3 | 49996098 | 15th fc untied | Roads | 323638 | XV Finance Commission | Basic Grant (untied) | 2023-01-11 00:00:00 |