Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 46437654 | sanitation of pipe line | Sanitation | 150000 | XV Finance Commission | Tied Grant | 2023-08-28 00:00:00 |
2 | 54668199 | drainage of water over flowing in balmiki basti | Administrative & Technical Support | 30871 | XV Finance Commission | Basic Grant (untied) | 2021-07-30 00:00:00 |
3 | 54668246 | cleaning of village nala | Sanitation | 499000 | XV Finance Commission | Tied Grant | 2022-03-02 00:00:00 |
4 | 54668281 | laying of pipe line | Sanitation | 500000 | XV Finance Commission | Tied Grant | 2022-03-02 00:00:00 |
5 | 54668543 | sanitation | Sanitation | 499000 | XV Finance Commission | Tied Grant | 2022-03-02 00:00:00 |