Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 78729639 | Creation of community compost pits for a group of Households | Sanitation | 846104 | XV Finance Commission | Tied Grant | 2023-02-27 00:00:00 |
2 | 78741386 | Creation of plastic waste storage unit | Sanitation | 740539 | XV Finance Commission | Tied Grant | 2023-04-22 00:00:00 |
3 | 79547715 | Construction of toilets in public institutions | Sanitation | 90000 | XV Finance Commission | Tied Grant | 2020-06-02 00:00:00 |
4 | 79550386 | Operation & maintenance of community sanitary complex | Sanitation | 62400 | XV Finance Commission | Tied Grant | 2023-04-17 00:00:00 |