S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 50025183 | Drainage | Sanitation | 80000 | XV Finance Commission | Tied Grant | 2023-06-13 00:00:00 |
2 | 50025369 | Drainage | Sanitation | 64012 | XV Finance Commission | Tied Grant | 2023-06-13 00:00:00 |
3 | 50025743 | Water Supply | Drinking water | 80000 | XV Finance Commission | Tied Grant | 2023-06-13 00:00:00 |
4 | 50025984 | Water Supply | Drinking water | 64012 | XV Finance Commission | Tied Grant | 2023-06-13 00:00:00 |
5 | 50026844 | office Exp | Administrative & Technical Support | 48024 | XV Finance Commission | Basic Grant (untied) | 2023-06-13 00:00:00 |
6 | 50027242 | Solar Light | Rural electrification | 240000 | XV Finance Commission | Basic Grant (untied) | 2023-06-13 00:00:00 |