1 | 59352559 | पेयजल सम्बंधित कार्य | Drinking water | 150000 | XV Finance Commission | Tied Grant | 2023-10-01 00:00:00 |
2 | 59353269 | स्वच्छता सम्बंधित कार्य | Sanitation | 48000 | XV Finance Commission | Tied Grant | 2022-11-04 00:00:00 |
3 | 59353916 | own Source Fund Work | Administrative & Technical Support | 49000 | XV Finance Commission | Basic Grant (untied) | 2023-05-03 00:00:00 |
4 | 66478282 | Construction of Community Sanitary Complex | Sanitation | 49000 | XV Finance Commission | Tied Grant | 2022-12-02 00:00:00 |
5 | 76094212 | Construction of Community Sanitary Complex | Sanitation | 49000 | XV Finance Commission | Tied Grant | 2023-03-06 00:00:00 |
6 | 76094783 | Operation & maintenance of community compost pits | Sanitation | 49000 | XV Finance Commission | Tied Grant | 2023-03-07 00:00:00 |
7 | 76095356 | Water Supply to villages | Drinking water | 150000 | XV Finance Commission | Tied Grant | 2023-03-06 00:00:00 |
8 | 87662353 | Construction of Community Sanitary Complex | Sanitation | 133000 | XV Finance Commission | Tied Grant | 2023-08-01 00:00:00 |
9 | 87662437 | Construction of Community Sanitary Complex | Sanitation | 133000 | XV Finance Commission | Tied Grant | 2023-08-01 00:00:00 |
10 | 87662500 | Construction of Community Sanitary Complex | Sanitation | 134000 | XV Finance Commission | Tied Grant | 2023-08-01 00:00:00 |
11 | 87662697 | Construction of Community Sanitary Complex | Sanitation | 45000 | XV Finance Commission | Tied Grant | 2023-10-26 00:00:00 |