Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 57101878 | हैंडपंप संधारण कार्य | Drinking water | 150000 | XV Finance Commission | Tied Grant | 2023-10-04 00:00:00 |
2 | 57102709 | बोर रिपेयरिंग कार्य | Drinking water | 50000 | XV Finance Commission | Tied Grant | 2023-12-18 00:00:00 |
3 | 57106022 | कूड़ादान की सफाई कार्य | Sanitation | 150000 | XV Finance Commission | Tied Grant | 2023-07-05 00:00:00 |
4 | 57107239 | स्ट्रीट लाइट संधारण कार्य | Rural electrification | 150000 | XV Finance Commission | Basic Grant (untied) | 2023-08-03 00:00:00 |
5 | 57108236 | कार्यालयीन व्यवस्था हेतु तकनिकी एवम प्रशासकीय व्यय | Administrative & Technical Support | 41560 | XV Finance Commission | Basic Grant (untied) | 2023-07-05 00:00:00 |
6 | 57159138 | समतलीकरण कार्य | Land improvement | 50000 | Own Funds | Own Funds | 2023-12-19 00:00:00 |