Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 57554278 | Water supply drinking water 2022-23 | Drinking water | 135300 | XV Finance Commission | Tied Grant | 2024-01-01 00:00:00 |
2 | 57688152 | Construction of street 2022-23 | Roads | 180400 | XV Finance Commission | Basic Grant (untied) | 2023-04-10 00:00:00 |
3 | 79247717 | Creation of community compost pits for a group of Households | Sanitation | 135300 | XV Finance Commission | Tied Grant | 2023-04-10 00:00:00 |