Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 58207730 | Water supply pipeline 2022-23 | Drinking water | 250315 | XV Finance Commission | Tied Grant | 2023-11-10 00:00:00 |
2 | 58208458 | Construction of of street 2022-2]3 | Roads | 333752 | XV Finance Commission | Basic Grant (untied) | 2023-04-05 00:00:00 |
3 | 78046271 | Creation of community compost pits for a group of Households | Sanitation | 250315 | XV Finance Commission | Tied Grant | 2023-04-05 00:00:00 |