Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 58250526 | Water supply pipeline 2022-23 | Drinking water | 73216 | XV Finance Commission | Tied Grant | 2023-11-10 00:00:00 |
2 | 58251006 | Construction of street 2022-23 | Roads | 97622 | XV Finance Commission | Basic Grant (untied) | 2023-10-18 00:00:00 |
3 | 88004731 | Creation of community compost pits for a group of Households | Sanitation | 73216 | XV Finance Commission | Tied Grant | 2023-10-18 00:00:00 |