S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 58265806 | Water supply pipeline 2022-23 | Drinking water | 47555 | XV Finance Commission | Tied Grant | 2023-11-10 00:00:00 |
2 | 58266090 | Construction of street 2022-23 | Roads | 63406 | XV Finance Commission | Basic Grant (untied) | 2023-06-01 00:00:00 |
3 | 86805524 | Creation of community compost pits for a group of Households | Sanitation | 47555 | XV Finance Commission | Tied Grant | 2023-06-01 00:00:00 |