Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 58218517 | Water supply pipeline 2022-23 | Drinking water | 266525 | XV Finance Commission | Tied Grant | 2023-05-05 00:00:00 |
2 | 58218982 | Construction of street 2022-23 | Roads | 355366 | XV Finance Commission | Basic Grant (untied) | 2023-05-05 00:00:00 |
3 | 83169528 | Creation of community compost pits for a group of Households | Sanitation | 266525 | XV Finance Commission | Tied Grant | 2023-05-05 00:00:00 |