Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 86942763 | Creation of community compost pits for a group of Households | Sanitation | 72012 | XV Finance Commission | Tied Grant | 2023-06-15 00:00:00 |
2 | 86942809 | Solid Waste Management (Untied) | Water Conservation | 96016 | XV Finance Commission | Basic Grant (untied) | 2023-06-15 00:00:00 |