1 | 57298011 | BOUNDRY BHAWARLA | Roads | 213000 | XV Finance Commission | Basic Grant (untied) | 2022-12-16 00:00:00 |
2 | 57298177 | BOUNDRY | Roads | 124000 | XV Finance Commission | Basic Grant (untied) | 2023-07-08 00:00:00 |
3 | 57302331 | NADEP | Sanitation | 75000 | XV Finance Commission | Tied Grant | 2023-12-08 00:00:00 |
4 | 86920163 | Construction of Community Sanitary Complex | Sanitation | 210000 | XV Finance Commission | Tied Grant | 2023-08-05 00:00:00 |
5 | 87395441 | BOUNDARYWAL PS SHALA BHAWAN PARISAR CTAKALI | Social welfare | 497000 | XV Finance Commission | Basic Grant (untied) | 2023-09-11 00:00:00 |
6 | 88709138 | Setting up of Faecal Sludge Management Plant | Sanitation | 186000 | XV Finance Commission | Tied Grant | 2023-09-14 00:00:00 |