S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 58128490 | shamshanghat | Maintenance of community system | 41945 | XV Finance Commission | Basic Grant (untied) | 2023-04-18 00:00:00 |
2 | 58128794 | street and drain | Roads | 215000 | Own Funds | Own Funds | 2023-04-06 00:00:00 |
3 | 87951012 | Creation of a new source of drinking water | Drinking water | 75504 | XV Finance Commission | Tied Grant | 2023-10-17 00:00:00 |
4 | 87951028 | Creation of drainage channel for management of grey water | Sanitation | 75504 | XV Finance Commission | Tied Grant | 2023-10-17 00:00:00 |
5 | 87951087 | Road........ | Roads | 58723 | XV Finance Commission | Basic Grant (untied) | 2023-10-17 00:00:00 |