S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 77089471 | PEVER BLOCK WORK | Roads | 75284 | XV Finance Commission | Basic Grant (untied) | 2023-05-02 00:00:00 |
2 | 77090435 | PEVER BLOCK WORK | Roads | 75400 | XV Finance Commission | Basic Grant (untied) | 2023-04-27 00:00:00 |
3 | 86504677 | Greywater management system | Sanitation | 56469 | XV Finance Commission | Tied Grant | 2023-07-04 00:00:00 |
4 | 86504710 | Creation of Small-bore pipe conveyance system | Sanitation | 56469 | XV Finance Commission | Tied Grant | 2023-07-04 00:00:00 |