Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 55773749 | Sanitation Maintenance | Sanitation | 180000 | XV Finance Commission | Basic Grant (untied) | 2022-12-26 00:00:00 |
2 | 55773878 | Fogging machine | Sanitation | 120680 | XV Finance Commission | Tied Grant | 2024-01-02 00:00:00 |
3 | 55774216 | Brush cutter | Sanitation | 60000 | XV Finance Commission | Tied Grant | 2024-01-03 00:00:00 |
4 | 55774388 | New pipeline | Drinking water | 400000 | XV Finance Commission | Tied Grant | 2024-01-03 00:00:00 |
5 | 55774524 | pws maintenance & pipeline leakages repair | Drinking water | 200000 | XV Finance Commission | Basic Grant (untied) | 2022-12-26 00:00:00 |
6 | 55774662 | Low lying areas filling with morom | Poverty allevation programme | 200000 | XV Finance Commission | Basic Grant (untied) | 2024-01-03 00:00:00 |