S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 58774125 | Tied water supply | Drinking water | 200000 | XV Finance Commission | Tied Grant | 2023-11-16 00:00:00 |
2 | 58812186 | Tied water supply | Drinking water | 793495 | XV Finance Commission | Tied Grant | 2023-09-12 00:00:00 |
3 | 58813325 | Tied Sanitation | Sanitation | 993495 | XV Finance Commission | Tied Grant | 2023-10-20 00:00:00 |
4 | 58816175 | Untied Road work | Roads | 400000 | XV Finance Commission | Basic Grant (untied) | 2023-11-16 00:00:00 |
5 | 58819780 | Untied Road work | Roads | 600000 | XV Finance Commission | Basic Grant (untied) | 2023-03-01 00:00:00 |
6 | 58823288 | Untied Road work | Roads | 324660 | XV Finance Commission | Basic Grant (untied) | 2023-05-16 00:00:00 |
7 | 58824241 | Water supply | Drinking water | 100000 | Own Funds | Own Funds | 2023-12-12 00:00:00 |